This document is a request for proposal for the delivery of granite base SB-2 gravel to various locations at the Dale Bumpers White River National Wildlife Refuge in Arkansas. The U.S. Fish and Wildlife Service seeks to procure 690 tons per day of 1-inch minus granite base gravel with fines to support projects at the Ethel Bottoms area of the refuge under the Great American Outdoors Act. Proposals are due by July 11, 2022 for a period of performance concluding on October 30, 2022. Delivery will be tailgate spread to the specified locations on the southeast side of the refuge as shown in the attached map. The contract will be awarded using the lowest price technically acceptable criteria. All material must meet specifications and be approved in samples before delivery.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL
for
Granite Base SB 2 GRAVEL At The
Dale Bumpers White River National Wildlife Refuge South Atlantic-Gulf & Mississippi Basin Region
January 24, 2022
1. BACKGROUND
a. The U.S. Fish & Wildlife Service would like to procure SB 2 gravel for the Ethel Bottoms Area at the Dale Dumpers White River National Wildlife Refuge to support the Great American outdoors act (GAOA).
2. GENERAL INFORMATION
a. All Material must be delivered to the Dale Bumpers White River Refuge at various locations on the southeast side of the refuge. The Ethel Bottoms area.
(See Map).
b. Method of Documentation of Acceptance:
- Weight tickets for each load.
c. See attached Map for Levee Loop Delivery Location.
d. Period of Performance: July 11, 2022 – October 30, 2022
e. Contract requirement: 690 tons of gravel per day to the site.
f. Each load will be delivered to the location specified in the map and tailgate spread by the Contractor.
g. This is a very remote site and how long it will take to deliver 690 tons per day needs to be taken into careful consideration.
h. Lowest Price Technically Acceptable will be used for this contract.
i. Spec for Materials:
j. granite Base (SB-2) 1 ½” minus with fines.
k. materials samples must be approved before delivery.
The FWS Project Manager for this project is David McCaghren. Any questions regarding the scope of work and technical matters shall be directed to:
David McCaghren, MAT Project Coordinator U.S. Fish and Wildlife Service Infrastructure Management Branch Telephone: (256) 642-5417 Email: David_mcCaghren@fws.gov
****END STATEMENT OF WORK****