Statement of Work
DESCRIPTION OF WORK
The work consists of providing Magnesium Chloride application to gravel roads at Black Canyon National Park, and Curecanti National Recreation Area, in the Gunnison Colorado areas.
Statement of work: The work consists of providing Magnesium Chloride application to gravel roads at Black Canyon National Park, and Curecanti National Recreation Area, in the Gunnison Colorado Areas. Options: this Solicitation is for a Base year plus up to three (3) Option Years.
All work shall be performed under a single contract. Any contract resulting from this solicitation shall not exceed $150,000 including the base and any option periods exercised.
SPECIFICATIONS:
1 application per year of Magnesium Chloride dust abatement to be applied on or about: May 1, 2021, thru June 30, 2021. Material must be applied via computer calibration at the rate of .25 tenths gallon per square yard along roadway.
Roadway surface at Black Canyon is approximately 9 miles long by 18’ wide. Government will prepare road surface.
Roadway surface at Curecanti National Recreation Area is approximately 8.7 miles long by 18’ wide. Government will prepare road surface.
Application spray pattern must span the entire 18’ roadway in one pass, this saves government time and shortens the time of road closures to the public during the season.
Payment will be made based on actual material applied not to exceed award amount.
Magnesium Chloride Solution Specifications:
Chemical Properties Magnesium Chloride 30-33%; Sulfates 0-3.5%, Potassium 0-0.5%; Sodium 0-0.7%
Physical Properties Clear to yellow in color; 10.85-11lbs per gallon; 6-7.5 pH of a 5% solution
Constituents
Total Phosphorous, Barium, or Zinc < 10.00mg/L Molybdenum < 15.00 mg/L Cyanide or Mercury < 0.05 mg/L Arsenic < 3.00 mg/L Copper < 0.10 mg/L Lead < 0.50 mg/L Chromium < 0.10 mg/L Cadmium < 0.15 mg/L Selenium < 0.30 mg/L Ammonia or Nitrogen < 0.00 mg/L
DELIVERY SCHEDULE and CONTRACT PERIOD
The awarded vendor will be expected to provide the services requested upon receipt of “notice to proceed” from the contracting officer, or as may be coordinated sooner, or as otherwise arranged. The Contracting Officer or a Contracting Officer’s Representative shall coordinate with the awarded vendor for a date and time to begin the requested services.
Work Dates.
Performance period May 1st – June. 30. The exact date will be set based on ensuring that freezing conditions do not exist in the roads, yet ensuring there is still enough moisture in the roads and as approved by the contracting officer’s Representative.
LOCATION.
Black Canyon of the Gunnison National Park, North Rim Road, is located approximately 15 miles southeast of Crawford Colorado. Curecanti National Recreation Area is located approximately 15 miles west of Gunnison Colorado.
PARK REQUIREMENTS
-The contractor shall determine and adhere to roadway use regulations for all roads between the point of origin and the delivery site, and responsible for any applicable permits. -The contractor shall adhere to all park requirements, rules, regulations and posted speed limits within all park boundaries.
SUBMITTALS
The awarded contractor will be required to provide the following for review and approval prior to commencement of work:
-Submittals for all products, chemicals, etc., expected to be provided in the completion of this contract -Material Safety Data Sheets (MSDS) for any and all products, chemicals, etc. to be provided in the completion of this contract.
-Insurance Certificate
WARRANTY.
The Contractor shall ensure that the dust suppressant meets the requirements of these specifications and the submittals upon delivery.
CONTACT INFORMATION:
For information regarding this solicitation contact: Contracting Officer Veronica Brick Veronica_brick@nps.gov 505-470-9789
CONTRACT LINE ITEMS
Contract line item 0001:
Magnesium Chloride shall be applied to the road surface on the North Rim Road of Black Canyon of the Gunnison National Park. The supplier will spray/apply Magnesium Chloride at the rate of .25 tenths gallon per square yard. The application will cover nine (9) miles of road at a width of eighteen feet (18'). Application spray pattern must span the entire eighteen-foot roadway in one pass. The total estimated amount of gallons is 23,800 (rounded up). This work will be completed one (1) mile at a time, depending on moisture content, water trucks, and equipment. This process may take one to two days for completion.
North Rim Road- 9 miles
Total estimated amount of gallons is 23,800 per year mailto:Veronica_brick@nps.gov
Contract Line item 0002:
Magnesium Chloride shall be applied to the road surfaces at Curecanti National Recreation Area. The supplier will spray/apply Magnesium Chloride at the rate of .25 tenths gallon per square yard to 8.7 miles of road, at a width of eighteen feet (18'). Application spray pattern must span the entire eighteen-foot roadway in one pass. This work will consist of the application to multiple short roadways along highway 50 and Ponderosa Campground as follows:
Soap Creek Road - 3 and 1/10 miles (3.1) Ponderosa Campground Road - 2 and 8/10 miles (2.8) Red Creek Road - 4/10 mile (.4) Dry Gulch Road - 6/10 mile (.6) Bay of Chickens - 3/10 mile (.3) East Elk Creek - 1and 2/10 miles (1.2) North Willow Creek - 3/10 mile (.3)
The total estimated amount of gallons is 22,400 per year
Contract line item 0003:
This line item is an option item for the hauling and application of water to the North Rim Road of Black Canyon of the Gunnison National Park. The park intends to haul and provide water if possible, but may require assistance with this task. The quoter shall provide a quote price, on an hourly basis, which shall include the truck, driver and water. It is estimated that as much as 80,000 gallons of water could be required. The amount of this task that will be required cannot be determined until the time of the actual application. The Park Service may require the vendor to provide any amount of this service that the Park Service cannot provide, ranging from none to all, or any quantity in between.
File details come from the government source that posted it. Updated .