SOW.pdf
PDF 341 KB Posted
- Attached to
- HVAC Systems cleaning of all floors in bldg N239
- Solicitation number
- 80NSSC26941841Q
About this file
This is a Statement of Work (SOW) for HVAC systems cleaning services to be performed at NASA Ames Research Center (ARC), Building N239. The contractor shall perform comprehensive air duct cleaning in accordance with National Air Duct Cleaning Association (NADCA) Standards.
The scope of work encompasses cleaning of accessible supply main ducting and grill faces in the basement mechanical and boiler rooms; cleaning of all accessible supply ducting in North and South utility chases on the 1st, 2nd, and 3rd floors; cleaning of accessible supply secondary ducting leading to office spaces; and contact cleaning of accessible reheat coils to remove surface buildup. Grille faces must be removed, hand washed, and replaced to their original positions. Lab spaces require Level 1 containment implementation during cleaning operations to prevent cross contamination. The place of performance is NASA ARC (Building N239), with a performance period from August 17, 2026 through December 31, 2026.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
1. Objective/Requirements HVAC Systems cleaning per National Air Duct Cleaning Association (NADCA) Standards.
2. Characteristics, Scope, and Specs
The contractor shall perform the following duties:
Basement: Cleaning of accessible supply main ducting leading to risers and grill faces in the mechanical and boiler rooms.
1st, 2nd, 3rd floors: Cleaning of all accessible supply ducting located in North and
South utility chases, and all accessible supply secondary ducting leading to office spaces. Accessible reheat coils contact cleaned to remove any surface buildup. Grille faces removed, hand washed and replaced to their original position.
Lab spaces must be placed under level 1 containment to prevent cross contamination while cleaning.
3. Place of Performance
NASA ARC (Building N239)
4. Period of Performance Performance expected 8/17/2026 to 12/31/2026.