This is a Scope of Work document for the Iowa Department of Public Defense (DPD) regarding mechanical system repairs at the Storm Lake Readiness Center. The project involves comprehensive HVAC and water heating system upgrades at two locations: the Storm Lake RC and an FMS Maintenance Shop. At the Storm Lake RC, the scope includes demolition and replacement of six York RTUs with new Lennox Enlight units equipped with 208/3 phase power, Bacnet compatibility, two-stage heating and cooling, and smart thermostats with seven-day scheduling. Additionally, six existing radiant tube heaters will be replaced with new Shwank units featuring programmable controls, and one Ruud water heater with expansion tank will be installed. All work includes necessary electrical connections, gas line modifications, fire alarm reconnections, and roofing membrane repairs. The FMS Maintenance Shop work is priced as alternates and includes removal of one York RTU, Co-Ray-Vac system, and wash bay radiant system, with installation of one new Lennox RTU and two Shwank radiant tube heaters in the maintenance shop plus one moisture-resistant Shwank heater in the wash bay. A site visit is scheduled for Thursday, August 27 at 10:00 AM at 1601 Park Street, Storm Lake, Iowa 50588, with bids due and opened on Thursday, September 10 at 1:00 PM via the IMPACS portal.
The scope specifies detailed equipment specifications and installation requirements, including materials, labor for crane and scissor lift operations, and all associated electrical and plumbing work. Bidders must submit proposals through IMPACS and are required to bring photo identification to the mandatory site visit. The issuing officer is Philip Payton of Iowa DPD, reachable at 515-975-6211 or philip.payton@dpd.iowa.gov. The document does not specify pricing terms, contract duration, funding sources, or whether incumbent contractor preferences or set-asides apply.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1430704-event.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Storm Lake RC / Maintenance Shop (FMS)
Scope
Storm Lake RC:
Demolition
- Remove and dispose offsite 6 existing York RTU’s, t-stats and associated wiring
- Remove and dispose offsite 6 radiant tube heaters and associated wiring to BAS
- Remove and dispose offsite 1 Ruud water heater and expansion tank
Furnish and install
- 6 new Lennox Enlight RTUs to include the following
- 208/3 phase power
- Bacnet ready
- 2 stage heat
- Combination gas valve
- NG heat
- 2 stage cooling
- Barometric relief dampers
- Hinged access doors
- Condensate switch
- Hail guards
- Non-fused disconnects
- Fire smoke heads if units exceed 2000 cfm in the return and units that exceed 15,000 cfm in both supply and return
- Curb adapters w/ hurricane straps
- Any gas line alterations to include replacing ball valve and unions
- Smart thermostat to include 7-day scheduling
- Any electrical associated with the project include breakers, line voltage wiring and low voltage wiring
- Reconnect any fire alarm controls that may shut off equipment in the event of fire.
- Any roofing membrane repairs or changes that may be needed from the installation must be compatible with the roofing system
- Include crane use
- 6 new Shwank radiant tube heaters to include the following
- Combination gas valve
- NG heat
- 2-stage heat
- 26 GA aluminized steel reflector
- Direct-drive ECM motor
- 6 programmable t-sats for individual control
- Fresh air intake kits
- Horizontal wall vent kits
- Provide any electrical line voltage and low voltage needed for completing the project including wiring, conduit, and breakers
- Include scissor lift for project
- 1 new 100-gallon RUUD direct replacement water heater to include:
- 115V power
- NG fired
- All associated copper piping and copper fitting materials needed to install the replacement water heater
- Include any electrical needed
- Expansion tank
- Condensate neutralizer kit
- Fiber glass insulation and all associated materials needed to re-insulate damaged or nonrepairable insulation on water lines
FMS maintenance shop alternates priced separately
Demolition:
- Remove and dispose offsite 1 York RTU, thermostat, and associated wiring
- Remove existing Co-Ray-Vac system and dispose of offsite
- Remove wash bay radiant tube system and dispose of offsite
- Furnish and install the following
- 1 new Lennox Enlight RTU to include the following
- 208/3 phase power
- Bacnet ready
- 2 stage heat
- Combination gas valve
- NG heat
- 2 stage cooling
- Barometric relief dampers
- Hinged access doors
- Condensate switch
- Hail guards
- Non-fused disconnects
- Fire smoke heads if units exceed 2000 cfm in the return and units that exceed 15,000 cfm in both supply and return
- Curb adapters w/ hurricane straps
- Any gas line alterations to include replacing ball valve and unions
- Smart thermostat to include 7-day scheduling
- Any electrical associated with the project to include breakers, line voltage wiring and low voltage wiring
- Reconnect any fire alarm controls that may shut off equipment in the event of fire.
- To include replacement roof blocks to support the gas lines and electrical lines
- Any roofing membrane repairs or changes that may be needed from the installation must be compatible with the roofing system
- Include crane use
Maintenance shop:
- (2) 2 stage Schwank radiant tube heaters
- Heaters to run North – South one on the West side and 1 on the East side of the shop
- New holes drilled for intake and exhaust pipes
- Provide all material needed for venting materials needed to bring in combustion air from the South side of the building and exhaust materials needed to exhaust from the North side of building
- Provide all materials for gas lines to each radiant tube heater
- 2 each 7-day programmable tstats
- Provide any electrical line voltage and low voltage needed for completing the project including wiring, conduit, and breakers
- Patch hole with similar materials from the demoing of the Co-Ray-Vac vacuum pump
- Include scissor lift
Wash Bay:
- (1) 2 stage Schwank moisture resistant radiant tube heater
- Moisture proof t-stat
- Tie onto existing combustion air intake
- Run new exhaust thru the existing penetration on the North exterior wall
- Provide electrical, to include breakers, conduit, line voltage and low voltage as needed
- Include scissor lift