This document is a Scope of Work (SOW) for a contract at the China Lake 8 Acres Site (contract number DC500035). The primary services required include constructing a perimeter fence and installing gates around an existing Tension Fabric Structure (TFS). Specific requirements involve building approximately 650 linear feet of 6-foot fence with 2 lockable drive-through gates, and laying and compacting approximately 27,000 square feet of Decomposed Granite (DG) to 90% compaction within the fenced area.

The contractor responsibilities include providing all necessary equipment, a qualified work team, and transportation for completing the project. The solicitation emphasizes the need for a vendor capable of executing the fence installation and ground preparation with precision, ensuring proper fence dimensions, gate functionality, and DG compaction standards. No specific pricing, response dates, or award information is included in this SOW document.

View the file

Other files

File Type Posted
Solicitation Amendment 2 N6893625Q51660002.pdf PDF
Questions and Answers.docx DOCX document
Updated SOW 2.docx DOCX document
Site Map.pptx PPTX presentation
Updated SOW.docx DOCX document
4_022_03 Fence - Gate configurations.pdf PDF
Solicitation Amendment N6893625P5166 P00001.pdf PDF
Wage Determination.pdf PDF
Part 2.pdf PDF
Solicitation - N6893625Q5166.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work for DC500035_Install Fence and Gates at 8 Acres

1. Overview: The IBO requires the services of a qualified vendor to build a perimeter fence with 2 gates in the China Lake 8 Acres Site. Additionally, requesting the vendor provide decomposed

Granite (DG) for approx. 27,000 square feet and compact the DG to 90% within the perimeter of the fenced area.

1. The contractor shall provide all necessary equipment for completing this job

2. The contractor shall provide a qualified team for providing the services

3. The contractor shall provide transportation for his team to accomplish all work as required

4. Performance requirements for required work are described below.

Service Required:

1. Build a perimeter fence around an existing Tension Fabric Structure (TFS) at the 8 Acre Site.

a. Approximately 650 liner feet of 6-foot fence with 2 lockable drive through gates.

2. Lay Decomposed Granite (DG) within the perimeter of the fence approx. 27,000 square feet. And compact DG to 90%.