This document is a Statement of Work (SOW) for the Rehabilitate Engineering Officer's Quarters - Emergency Repairs project at Dry Tortugas National Park. The objective is to provide emergency exterior repairs to stabilize the Engineering Officer's Quarters, including repairing/replacing damaged copper gutters, wood shutters, roof flashing, and performing selective mortar repointing and wood carpentry/painting repairs. The contractor shall provide all labor, tools, equipment, materials, and supervision required to complete the necessary tasks. Site visits and park housing are available, and the work must be completed within 60 days after the Notice to Proceed. The contractor must comply with safety and environmental regulations, provide a technical approach, and submit various post-award documents for approval prior to starting work. The related federal contract opportunity is Solicitation Number 140P5424R0019 for the Rehabilitate Fort Jefferson Engineering Officer's Quarters at Dry Tortugas National Park.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions_and_Answers_0003.pdf | ||
| Sol_140P5424R0019_Amd_0003.pdf | ||
| Sol_140P5424R0019_Amd_0002.pdf | ||
| 140P5424R0019_0001.pdf | ||
| Sol_140P5424R0019_Amd_0001.pdf | ||
| Wage_Determination.pdf | ||
| Sol_140P5424R0019.pdf | ||
| Past_Performance_Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
Rehabilitate Engineering Officer’s Quarters - Emergency Repairs Statement of Work DRTO Page 1 of 8
Rehabilitate Engineering Officers Quarters
Emergency Repairs Fort Jefferson
Dry Tortugas National Park
PMIS 309351C
Feb 2024
Emergency Repairs Statement of Work DRTO Page 2 of 8
NATIONAL PARK SERVICE
TABLE OF CONTENTS
1. PARK INTRODUCTION
2. PROJECT OVERVIEW
3. REQUIRED SERVICES/TASKS
4. OTHER CONTRACTOR REQUIREMENTS
5. GOVERNMENT FURNISHED PROPERTY, MATERIALS & SUPPLIES
6. SITE VISITS
7. PARK HOUSING
8. TELEPHONE/INTERNET
9. WORKING HOURS
10. PERIOD OF PERFORMANCE
11. SAFETY & ENVIRONMENTAL COMPLIANCE
12. GENERAL TREATMENT
13. EMPLOYEE IDENTIFICATON BADGES AND PARKING
14. SUBMITTAL REQUIREMENTS LIST (POST-AWARD)
15. ATTACHMENTS
ACRONYMS
CDC Centers for Disease Control and Prevention
CFR Code of Federal Regulations
CO Contracting Officer
COR Contracting Officer’s Representative
COVID-19 Coronavirus Disease of 2019
CP Competent Persons
DRTO Dry Tortugas National Park
EPA Environmental Protection Agency
NPS National Park Service
OSHA Occupational Safety and Health Administration
PM Project Manager
PMIS Project Management Information System
SOW Statement of Work
Emergency Repairs Statement of Work DRTO Page 3 of 8
Rehabilitate Engineers Officers Quarters – Emergency Repairs
1. PARK INTRODUCTION
Almost 70 miles (113 km) west of Key West lies the remote Dry Tortugas National Park. This
100-square mile park is mostly open water with seven small islands. Accessible only by boat or seaplane, the park is known the world over as the home of magnificent Fort Jefferson, picturesque blue waters, superlative coral reefs and marine life, and the vast assortment of bird life that frequents the area.
Fort Jefferson is a 19th century “Third System” coastal defense fortification located approximately 60 nautical miles west of Key West, Florida in the Gulf of Mexico. Military engineers began construction on the fort in 1846 and stopped before it was completed in 1874. It was part of an organized effort by the United States government beginning in 1817 to generate a system of national defense. Each of these coastal defense works were designed to contain artillery, garrisons, and magazines of which could defend against an attack until further reinforcements could be dispatched. Fort Jefferson represents one of the highest achievements of
19th century American military architecture and engineering and is one of the largest Third
System forts constructed. The hexagonal fortification has three tiers and surrounds a parade ground with auxiliary structures and ruins.
2. PROJECT OVERVIEW
The objective of this project is to provide emergency exterior repairs to stabilize the Engineering
Officer’s Quarters. Given the current condition of the EOQ, the structure is stable but vulnerable to moisture infiltration in the extreme conditions of the region and therefore emergency measures must be taken to secure the building and ensure preservation for future work. This project will repair/replace Building HS-08’s damaged copper gutters and operable wood shutters with hardware, copper roof flashing along parapet walls, chimneys, roof ridge and both exterior porches. Repairs include selective mortar repointing adjacent to affected repair locations or where mortar deficiency is discovered. Also included are selective wood carpentry/painting repairs to stabilize exterior wood porches and wood trim at roof eaves. All work performed will comply with the Department of the Interior’s Standards for the Treatment of Historic Properties.
The Engineering Officers’ Quarters (a.k.a. HS-08), which was reconstructed around 1935 and is on the List of Classified Structures and identified as a contributing resource on the 1974 Ft.
Jefferson National Monument National Register Nomination, is determined to be a necessary housing unit for full time NPS employees housed at Dry Tortugas. HS-08 is further broken down into two distinct structures. Structure 8A refers to the southernmost brick structure and the attached wood structure is known as the “Hyphen”. The north wall of the Hyphen is shared with the south wall of 8B. Due to the buildings current condition, historic designation and the lack of other housing options at Garden Key, it is imperative that the emergency repairs be completed is in an expedited manner.
DRTO Page 4 of 8
GENERAL PLAN DIAGRAM OF HS-08 AND COMMANDING OFFICERS RUIN
3. REQUIRED SERVICES/TASKS
The Contractor shall provide all labor, tools, equipment, materials, and supervision required to perform the following tasks:
• Complete all tasks required to achieve necessary permits. All requirements and cost to achieve the permit is the responsibility of the contractor. All requirements to follow and complete the permit through construction and permit closeout is the responsibility of the contractor.
• Delivery all materials, supplies, personnel, and equipment required to complete the scope of work including but not limited to barricades, safety equipment, power generators, sand screeners, scaffolding, water pumps/containers, materials, tools, food, drink, recreation equipment.
• Mockup and approval of slate roof repairs, mortar and masonry repairs, copper work and gutters, wood carpentry and painting are required and must be approved by Historic Architect or COR before commencing work.
• Sample of wood shutter shall be submitted for park approval or COR.
• All work shall match adjacent historic fabric in dimension, color, and physical characteristics.
• Ensure limbs of adjacent trees are trimmed so as not to contact building during work or wind events.
• Repair/reconstruct minor areas adjacent to work performed where bricks have collapsed or fallen from the walls. There may be several instances of this condition. Repair using salvaged brick that matches the existing in dimension, color, and physical characteristics. Maintain coursing, joint width and tooling.
• Repoint areas at or adjacent to work performed where mortar has deteriorated or lost it binding qualities. Develop compatible repair mortars based on results of materials analysis.
The pointing mortar used at the Engineers’ Quarters was determined to be a lime and natural cement mix (EOQ-Historic Structures Report-Appendix C)
• Any new hardware or fasteners shall be 316 stainless steel.
• All work shall be conducted under the guidance and in accordance with the The Secretary of the Interior’s Standards for the Treatment of Historic Properties with Guidelines for
Preserving, Rehabilitating, Restoring & Reconstructing Historic Buildings.
• Repairs shall be performed by qualified historic preservation contractors. Contractor shall submit references to demonstrate prior historic preservation construction expertise and experience.
Emergency Repairs Statement of Work DRTO Page 5 of 8
• Treatment Documentation – The repair areas for which treatment is planned shall be photographed and described in detail, before, during and after treatment so the accurate comparisons may be made when analyzing the effectiveness of the treated repair areas.
• Contractor shall at a minimum include daily project reporting and weekly progress calls.
• Assemble scaffolding in accordance with all applicable state and federal requirements.
• Remove all materials, supplies, and equipment from Dry Tortugas National Park upon completion of the project.
• Offerors are encouraged to propose process improvements and industry best practices in their proposals.
Engineers Officers Quarters - Exterior Repairs
• Remove and install new shutters (17). Rough openings 36x68 (9). 40x51 (8)
Fixed Louver Shutters | Timberlane
Repair approximately 45 lf of brick flashing on parapet walls Repair approximately 15 lf of brick flashing at chimney Repair approximately 30 lf of brick flashing at porch roof Repair approximately 35 lf of brick flashing at porch roof Repair approximately 30 lf of brick flashing at porch roof
• Install new copper gutters 75 lf
• Repair approximately 40 lf of copper gutters
• Repair approximately 50 lf of copper ridge cap
• Wood Carpentry/Painting Repairs
• Slate Roof Misc. Repairs Approx. 100 Sq. Ft.
• Mortar Repointing Repairs
• Site Mobilization/Demobilization/Debris Disposal
4. OTHER CONTRACTOR REQUIREMENTS
• Prices shall be presented in a Schedule of Values form to facilitate pricing analysis for
Proposal. The sum of the total construction cost on the Schedule of Values shall be equal to the proposal price.
• A Contractor Safety Plan is required for this project. Refer to the Safety and
Environmental Compliance Section of this document.
• Technical Proposal with project schedule to describe the plan to complete the project.
Contractors are encouraged to provide detailed and specific information on their technical proposal for the project. This document shall address the contractor’s plan to complete each of the two (2) bulleted tasks identified in Section 3 since many of these tasks require different specialty skills. This document allows the review of the contractor’s plan to ensure the contractor possesses a thorough understanding of what is required to complete the work. The Technical Proposal shall address who the proposed person/group/subcontractor is doing which items, and in what order with expected time durations. At a minimum, proposed persons/contractors shall be listed that will perform the following tasks:
o Rehabilitate Engineers Officer’s Quarters – Emergency Repairs https://www.timberlane.com/products/exterior-shutters/shutter-types/fixed-louver-shutters/?lb1
DRTO Page 6 of 8
A Technical Proposal is required as part of the proposal package and shall also be the basis for a Technical Approach. The Technical Approach shall be submitted and approved by the CO and COR prior to starting any work.
5. GOVERNMENT FURNISHED PROPERTY, MATERIALS & SUPPLIES
Local sand (un-sifted) and cistern water will be available for concrete/mortar mix
• Park will remove all furniture and park materials from adjacent work areas
• National Park Service Director’s Order 28 (NPS-28)
• Historic Photographs and Drawings of Fort Jefferson
• Other applicable park planning documents as requested including but not limited to:
o Historic Structures Report (HSR), Edwin Bearss, 1983 o Dry Tortugas National Park – Historic Preservation Report, Exterior Preservation
Plan – Engineering Officer’s Quarters, HS-08 o Historic Structures Report Amendment (HSR-A), LAS, 2006 o Historic Structure Reports for Engineering Officers’ Quarters and Bastion/Curtain
Magazines, Lord Aeck Sargent; 2017 o Documents also include materials analysis data.
6. SITE VISITS
Due to the remote location, specific site logistics, and challenging working conditions of any project at the Dry Tortugas, a site visit may be required prior to submission of your proposal.
Site visits can be used to collect or verify measurements and quantities, quantify materials, establish construction methods, and to have site familiarity. Site visits shall be rendered by the COR assigned to the project under this SOW. The NPS reserves the right to limit site visits to those which the CO or the COR determines to be sufficient.
Site visits prior to award will not be reimbursable by the government.
Transportation to Dry Tortugas is offered daily by two separate commercial operations:
Yankee Freedom III ferry; roughly 2.5 hours each way, 0800 departure from Key West to
Dry Tortugas and a 1430 departure from Dry Tortugas to Key West. Key West Seaplane
Adventures offers multiple seaplane departures from Key West to Dry Tortugas Daily.
Travel time is roughly 45 minutes each way.
Contractor can coordinate transportation of construction materials and supplies with the Park, pending availability and schedule of park vessel.
7. PARK HOUSING
Park housing will be made available to contractor for a crew of up to 4 (4) individuals. Park housing is a shared living situation. A walk through can be completed with a site visit and/or more information can be provided upon request. Housing rates are $45/person/night to be paid to park at the end of each month of occupation.
Emergency Repairs Statement of Work DRTO Page 7 of 8
8. TELEPHONE/INTERNET
The internet provided to transient quarters is very limited, with capability for texting and browsing webpages. Very strict usage rules apply as it is a community system.
No government-provided phone service will be available to the contractor.
Contractor will be responsible for all telecommunications needs and systems beyond the capabilities of what is provided currently by the NPS. This must be heavily coordinated with the designated CO as options for phone and internet are incredibly limited on Garden Key.
9. WORKING HOURS
The contractor shall complete on-site work during normal business hour period of 8:00 am to
4:00 pm, Monday through Friday, excluding Federal holidays. Working outside these times and dates shall require a written request. Each request to work outside of normal business hours shall be date specific and shall be pre-approved by the CO and require minimum of 72 hours’ notice. Requests without this specified notification period will not be approved. The contractor shall coordinate specific on-site work schedule with the CO and COR with the submittal of a complete Project Schedule. Refer to the Submittal Section of this document.
Approval of a submitted project schedule shall not consist of inherent approval for work outside of normal hours. While on site, the COR or CO may be reached by mobile phone during these specified normal business hours.
10. PERIOD OF PERFORMANCE
Timing of the work shall be coordinated with the COR and will be based on the availability of government housing.
Dry Tortugas National Park is subject to seasonal Atlantic Hurricane conditions from June to
November. Contractor will be responsible for planning, scheduling, and executing any temporary closures or shutdowns of the work site due to severe weather, any time of the year, but particularly during the hurricane season. Evacuations and seasonal shutdowns may be required. No official contract work shall begin until after award and a Notice to Proceed have been provided by the Contracting Officer.
All work shall be completed within 60 days after CO issues the contract Notice to Proceed.
11. SAFETY & ENVIRONMENTAL COMPLIANCE
• The contractor shall submit a Contractor Safety Plan and identify a single Safety Person in Charge with a clear transfer of responsibility in cases when there are alternates for all on-site work. In additional to these requirements, designated person(s) shall meet and demonstrate competency in all Occupational Safety and Health Act (OSHA) standards related to Competent Persons (CP) under 29 CFR 1910 through 1926 for the applicable areas related to this project. The Contractor Safety Plan shall also include a separate
Emergency Repairs Statement of Work DRTO Page 8 of 8 subsection for COVID-19 safety provisions to specify the contractor’s methods to address CDC Guidelines while performing the project work.
• The contractor shall comply with pertinent Environmental Protection Agency (EPA) laws and regulations.
• The Park Safety Coordinator shall have the authority to issue restraint or cease-and-desist orders to the contractor when violations or unsafe acts are present and threaten
Government or contractor employees or damage to Government property. The contractor shall notify the CO and COR immediately if issued a cease-and-desist order.
12. GENERAL TREATMENT
Delivery of all materials, supplies, personnel, and equipment required to complete the scope of work including but not limited to barricades, safety equipment, power generators, sand screeners, scaffolding, water pumps/containers, materials, tools, food, drink, recreation equipment is the responsibility of the contractor.
Remove of all materials, supplies, and equipment from Dry Tortugas National Park upon completion of the project.
13. EMPLOYEE IDENTIFICATON BADGES
All Contractor and Subcontractor employees shall wear identifiable clothing on the work site, so Park visitors know they are Contractor employees.
14. SUBMITTAL REQUIREMENTS LIST (POST-AWARD)
The following items are to be submitted after the contract award. All submittals shall be approved prior to ordering or starting any work.
• Completed Schedule of Values form. Refer to Attachment B.
• Proposed Project Schedule and updates.
• Technical Approach to complete the work is required. The Technical Approach shall be based on the Technical Proposal that is required for the proposal phase of the project.
• Physical measurement summary report submittal is required. Refer to the Required
Services/Tasks Section.
• Debris Disposal Plan is required. This plan shall describe how records of debris taken from the site are tracked to a specific debris disposal facility. No materials shall be dumped or disposed of improperly.
• Contractor Safety Plan is required, which shall include sections on COVID-19 safety provisions, fall prevention plan, and an inclement weather response plan. Refer to the
Safety and Environmental Compliance Section.
• All materials required to be purchased to complete the project require material submittal documents.
• Contractor shall submit a Hurricane Evacuation Plan to COR for park approval.
Emergency Repairs Statement of Work DRTO Page 9 of 8
15. ATTACHMENTS – PHOTOGRAPHS
FIGURE 1. OVERALL SOUTHWEST VIEW OF HS-08
Emergency Repairs Statement of Work DRTO Page 10 of 8
FIGURE 2. DETAIL VIEW OF ROOF AT SOUTH PORCH; UNIT 8A
Emergency Repairs Statement of Work DRTO Page 11 of 8
FIGURE 3. DETAIL VIEW OF WOOD LOUVERED VENT AT GABLE END PARAPET & PORCH; UNIT 8A
Emergency Repairs Statement of Work DRTO Page 12 of 8
FIGURE 4. DETAIL VIEW OF COPPER FLASHING AT PARAPET; UNIT 8A
Emergency Repairs Statement of Work DRTO Page 13 of 8
FIGURE 5. OVERALL NORTHEAST VIEW OF HS-08
Emergency Repairs Statement of Work DRTO Page 14 of 8
FIGURE 6. DETAIL VIEW OF COPPER FLASHING AT CHIMNEY
Emergency Repairs Statement of Work DRTO Page 15 of 8
FIGURE 7. DETAIL VIEW FROM THE EAST OF 8A; SECOND STORY WINDOW