SOW.docx
DOCX document 15 KB Posted
- Attached to
- Installation of Corning multimode (MM) OM3 Fiber and red shielded Cat6 cables to floor boxes
- Solicitation number
- N6893622Q0162
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 22Q0162 Amendment 2.docx | DOCX document | |
| POSTING PM3008 R216 Layout.pdf | ||
| Commercial Solicitation N6893622Q0162.docx | DOCX document | |
| POSTING Room 1310.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Building 3008 Room 214, 215, & 216 Installation of Corning multimode (MM) OM3 Fiber and red shielded Cat6 cables to floor boxes. PM3008 R216 Layout drawing.
· Vendor must supply the parts as described in the SOW and install them.
· Require a quote that shows what parts the vendor is providing.
1) Provide and install (1) 2” conduit stub up into the drop ceiling from the customer supplied CPI two-bay cabinet and secure the new cabinet to the floor. (PM3008 R216 Layout.pdf Page 3)
2) Provide and install (1) CPI 11” brush grommet, Part #13671-001, in the floor tile under the new cabinet. (PM3008 R216 Layout.pdf Page 3)
3) Provide and install (3) CPI floor boxes, Part #A0802-RF-D1 (1) in the center of room 214, 215 & 216. (PM3008 R216 Layout.pdf Page 3)
4) Provide & install (48) Berk-Tek red Cat6 Shielded network cables to each of the floor boxes under the floor in rooms 214, 215 & 216. Cables will be fed from the bottom bay of the new CPI two-bay cabinet. Leave a 20’ service coil at each box, so boxes can be relocated in the future. (PM3008 R216 Layout.pdf Page 3)
5) Cables runs will travel through the raised floor, between the cabinet and the floor boxes.
6) Provide and install (288) red Leviton shielded Cat6 Jacks, Part #61SJKRC6 to terminate cables on each end.
7) Provide and install (6) Leviton shielded modular patch panel, Part #4S255-S48.
8) Terminate, certify & label all new cables installed.
9) Ground/bond each patch panel. Bond each patch panel to the main ground system to be determined on site.
10) Provide and install (1) 12F MM OM3 TB aqua cable form the new cabinet in room #216 up to room #356 (use the existing conduit in place). (PM3008 R216 Layout.pdf Page 4)
11) Provide and install (1) Corning CCH-O2U fiber patch panel in the existing rack in room #356. (1) 12F MM OM3 LC adaptor panel. (PM3008 R216 Layout.pdf Page 4)
12) Provide and install (1) Corning O1U fiber patch panel in the new CPI cabinet bottom bay. (1) 12F MM OM3 LC adaptor panel. (PM3008 R216 Layout.pdf Page 4)
13) Provide and install (1) 2” fire sleeve penetration under the floor from room #216 to room #215. (PM3008 R216 Layout.pdf Page 4)
14) Relocate the existing DITAC fiber cables from the existing small cabinet to the new CPI cabinet, and land in the top bay. (3) 6F SM TB cables and (3) 12F MM OM3 TB cables.
15) Re-use the existing DITAC fiber patch panel in the new cabinet.
16) Provide and install (1) SmartUPS 1500VA Uninterruptible Power Supply w/network card, Part #SMX1500RM2UCNC.
17) One 6F singlemode and one 12F multimode OM3 cables shall be re-pulled from room 218 to the new cabinet in room 216, approximately 100’.
18) Installation of 110V power to the new cabinet along with a ground bar.
Building 36 Room 1316 & 1310 Installation of Fiber Optic AEA 6F MM TO (28) Locations. PM36 R1310 AEA Drops Drawing.
1) Provide and install (1) AEA 6F MM OM3 cable to each of the (28) workstations located in rooms 1316 & 1310 (4 strands) terminated LC/LC. Cable will be suspended above the drop ceiling with 2” J-hooks.
2) Provide and install Leviton MOS at each fiber cable drop location with the LC insert for each labeling to identify specific network and drop ID per standard labeling scheme. (1) MOS/box at each of the (28) workstations.
3) Provide and install 1” white ICC SMR and fittings on the walls down to the MOS box at the workstations.
4) Provide and install the necessary Corning CCH-CP24-E4 adapters LC adaptor panels at the IDF in the existing 4U patch panel.
5) Provide and install metal backing plate to span from side to side of the furniture panels for the MOS box to mount at all (28) workstations.
6) Provide labor and hardware for mounting metal plating.
7) Demo & removal of any existing unused copper network cabling to the space. Cover the empty wall boxes with blank faceplates.
8) Provide red line drawings for final workstation layout with labeling for all fiber optic drops.
File details come from the government source that posted it. Updated .