About this file
This statement of work and solicitation outline requirements for the procurement of resistance and impedance calibration standards and equipment by the Department of the Navy Naval Air Systems Command Naval Air Warfare Center. The contractor shall provide 190 P/N 1433-F Decade Resistors with specified accuracy levels, calibration certificates, serialization, manuals, and shipping. Requirements include a one-year warranty, DFARS compliance for technical data rights, and delivery to the location specified. The purpose is to support aviation maintenance and calibration activities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sole Source.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work A. Background The use of NAVAIR METCAL equipment funding is to procure Calibration Standards (CALSTDs) and ancillary equipment for Aviation Fleet Intermediate Calibration Activities, Fleet Training Activities and Aviation Navy Calibration Laboratories (NCLs) to support Aviation Organizational and Intermediate (I) level maintenance assets. All Cal Standards listed for procurement must first go through an approval process. This process includes: initial submission by the fleet; review and prioritization by the Fleet TYCOM’s; laboratory workload justification and standardization review by a NAVAIR METCAL technical review team; overall procurement strategy reviews to assess overall program objectives, priorities and funding.
REQUIREMENTS:
1. Mfr. one-year warranty with a warranty certificate.
2. Calibration Certificate and calibration sticker (as applicable for each unit)
3. Units to be serialized.
4. Include shipping to destination below.
5. Manufacturer’s Standard Operating and servicing manuals (CD version acceptable) to be provided with each unit. The DFARS clause listed below must be referenced in all contracts and the manufacturer made aware that the use/reproduction of tech data/manuals (for government use only) will follow these use guidelines.
DFARS SUBPART 227.71 - Rights in Technical Data 6.
The US government shall have limited technical data rights for all technical manuals and documents furnished with the procured commercial items, for the purpose of Government use only in duplicating or posting technical documentation to limited access web sites for use by US Government Personnel and Contractors engaged in maintenance, calibration or related logistics activities associated with the procured commercial items in accordance with DFARS 252.227-7015 Technical Data--Commercial Items.
B. Tasking:
The contractor shall provide the following equipment:
1) P/N 1433-F Decade Resistor Qty 190 To include the following:
a. Accuracy:
b. ≤1 MΩ decades: ±(0.01% + 2 mΩ)
c. 10 MΩ decades: ±0.03% after subtraction of zero resistance, at 23°C; traceable to SI
b) Zero resistance:
a. ≤1 MΩ decades: <1 mΩ per decade at dc
b. 10 MΩ decade: ≈3 mΩ at dc
c) Max voltage to case: 2000 V peak
d) Terminals:
e) Gold-plated, 5-way, tellurium-copper binding posts with low thermal emf and low resistance.
f) Terminals: 3 binding posts, labeled HI, LO, and GND
g) Switch capacitance: <1 pF between contacts
h) Environmental conditions:
a. Operating: 10°C to 40°C; < 80% RH
b. Storage: -40°C to 70°C
c. Typical Value of Zero Impedance:
d. <0.001 Ω/decade at 1 Hz
e. 0.04 Ω/decade at 1 MHz
Proportional to square root of frequency above 100 kHz
i) Switches: Continuous rotation 11 positions marked "0"-"10" Multiple solid silver-alloy contacts
j) Calibration Certificate
k) Instruction manual
C. Deliverables
Delivery of the equipment to be provided at the following address:
NAVAIR Calibration Standards
Attn: Lou Cerrillo (UIC N48535)
BLDG 612, Bay 9 MCAS
Beaufort, SC 29904
Phone: (843)524-1405 D. Delivery Date
Delivery shall be no later than 80 working days after award of contract, and shall be absolutely no later than 12-01-2020 *****Early delivery accepted****
E. Invoicing
a. All invoicing shall be submitting into Wide Area Workflow for payment after all material is received in the condition as stated in section B.