SOW DECK COVERING (INTERIOR WET-DRY) RENEW WORK ITEM 15.docx
DOCX document 29 KB Posted
- Attached to
- RENEW Interior Deck Covering Systems
- Solicitation number
- 70Z02920QJM896
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Galveston Current Wage Rates 6 2020.txt | TXT text file | |
| Commercial Supplies Services Clauses Provisions 2020 08.docx | DOCX document | |
| SF18 -JM896- Interior Deck Covering Galveston.pdf | ||
| OFF 336.continuation.sheet JM896Galveston.pdf | ||
| SPEC WI 15.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Period of Performance: Week of Oct 19 2020 – Oct 23 2020
SHORT TITLE: DECK COVERING (INTERIOR WET/DRY) RENEW
1. PLACE(S) OF PERFORMANCE:
a. IPF Galveston ATTN: Mike Amrhine 3000 Fort Point Rd Galveston, TX 77550
2. REFERENCES:
COAST GUARD DRAWINGS
Coast Guard Drawing 75D-WAGL 0103-19, Rev B, Booklet of General Plans (75309) Coast Guard Drawing 75D-WAGL 1101-3, Rev -, Shell Expansion (75309) Coast Guard Drawing 75D-WAGL 4804-5, Rev -, Freshwater & Waste Piping Plan (75309-75310) Coast Guard Drawing 75D-WAGL 4804-6, Rev -, Freshwater & Waste Piping Sections (75309-75310)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install Interior Deck Covering Systems
OTHER REFERENCES
MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric
3. SPECIFICATIONS: USCGC HATCHET (WLIC-75D) Dockside Availability FY 2021 Work Items: 15
4. SECURITY REQUIREMENTS:
All personnel requiring access to classified spaces on Coast Guard units as applicable to the task shall require a current security clearance with a minimum level of secret. Contractor’s request for authorization will be submitted in accordance with DOD 5220.22M (Industrial Security Manual for Safeguarding Classified Information) no later than (1) week before each unit visit. Request will be forwarded via MLCLANT, Norfolk, VA, and ATTN: Security Officer, for certification of need to know by the specified COTR/ACOTR/TA. DD-254 Reference (a) applies.
All contractor personnel requiring routine access to a Coast Guard Computer Information System or requiring Public Key Infrastructure (PKI) authentication to perform their required duties under this task shall require a Common Access Card (CAC).
Contractor employees working on-site at Government facilities shall wear a valid Contractor’s identification card. All Contractor employees shall identify themselves as Contractors when their status is not readily apparent and display the Government issued badge in plain view above the waist at all times.
5. TASK ORDER MANAGEMENT DESIGNATION: N/A
6. DESCRIPTION OF WORK:
6.1 Work Item 15: Deck Covering (Interior Wet /Dry) Renew
6.1.1.1 Intent. This work item describes the requirements for the Contractor to renew deck covering system(s).
6.1.1.2 Government-furnished property.
None.
6.1.2. REQUIREMENTS
6.1.2.1 General.
6.1.2.2 CIR.
The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
· 6.1.2.6 Ultrasonic thickness (UT) measurements.
6.1.2.3 Tech Rep.
Not applicable.
6.1.2.4 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
6.1.2.5 Deck covering installation particulars. The Contractor shall perform all tasks specified in SFLC Std Spec 6341 and herein, to install a new covering system in the location(s) specified in Table 1 below.
NOTES
1. The exposed deck surfaces are prepared and coated in accordance with SFLC Std Spec 6310. Refer to SFLC Std Spec 6341, Para 3.2.1.2 for additional information.
2. Ensure the final surface condition of the deck is made “slip resistant” in accordance with manufacturer's installation procedures. Refer to SFLC Std Spec 6341, Para A2.1.2.2.
| TABLE 1 - DECKING SYSTEM LOCATION |
| AREA (*SQFT) |
| DECK MTL (A/S**) |
| SYSTEM/ APPENDIX (SFLC STD SPEC 6341) |
| COVE BASE |
| SYSTEM COLOR |
| UNDERLAYMENT REQUIREMENT |
Galley 1-32-1-Q
S
Cosmetic Polymeric Epoxy Resin, Type III (One-Step Epoxy System)/Appendix A
Yes: X No:
See paragraph 6.1.2.8 (Deck covering color)
Renew existing underlayment.
Crew Head 1-14-2-L
S
Cosmetic Polymeric Epoxy Resin, Type III (One-Step Epoxy System)/Appendix A
Yes: X No:
See paragraph 6.1.2.8 (Deck covering color)
Renew existing underlayment.
Passageway 1-25-0-L
| 120 |
| S |
| Cosmetic Polymeric Epoxy Resin, Type III (One-Step Epoxy System)/Appendix A |
| Yes: X |
No:
| See paragraph 6.1.2.8 (Deck covering color) |
| Renew existing underlayment. |
**Note: A = Aluminum; S = Steel.
***See SFLC Std Spec 6341 for definition of cove base.
6.1.2.6 Ultrasonic thickness measurement. Upon completion of surface preparation and prior to application of primer coat (see 6.1.2.5 (Surface preservation)), the Contractor shall the Contractor shall take a total of 100 UT measurements of deck plating, in locations designated by the Coast Guard Inspector, in accordance with SFLC Std Spec 0740, Appendix C. Use Coast Guard Drawing 75D-WAGL 1101-3 as guidance. Submit a CIR.
6.1.2.7 In addition to the UT measurements, take a total of 25 pit-depth measurements, using a suitable pit depth gauge
6.1.2.8 Deck covering color. The Contractor shall submit a deck covering color chart to Coast Guard Inspector, for the purpose of color selection.
7. GOVERNMENT FURNISHED INFORMATION (GFI): N/A
8. GOVERNMENT FURNISHED MATERIAL (GFM): N/A
9. GOVERNMENT FURNISHED EQUIPMENT (GFE): N/A
10. CONTRACTOR FURNISHED EQUIPMENT (CFE): N/A
11. CONTRACTOR FURNISHED MATERIAL (CFM): N/A
12. TRAVEL REQUIREMENTS: N/A
13. TRANSPORTATION OF EQUIPMENT/MATERIAL:
Transportation of equipment/material is authorized when timely means by the Government is unavailable.
14. DATA DELIVERABLES:
15. SUB-CONTRACTING REQUIREMENTS: N/A
16. ACCEPTANCE PLAN: N/A
17. OTHER CONDITIONS/REQUIREMENTS: N/A
18. LIST OF ATTACHMENTS: N/A
File Name: SOW_XXXX-0 Contractor Name: Contract Number/Task Order Number Record Number if applicable
File details come from the government source that posted it. Updated .