CRANE RENTAL SERVICES FOR INSTALLATION OF ANTENNA, RADOME, AND OTHER EQUIPMENT NEAR BATTLE MOUNTAIN, NV.
Solicitation number
6973GH-MS-23-00002
Issued by

About this file

This document includes a Statement of Work and related federal contract opportunity notice. The Statement of Work outlines requirements for crane rental services to lift and install an antenna beacon, equipment, and radome structure at the Battle Mountain, NV CARSR antenna site for the Federal Aviation Administration. Services will include lifting estimated 1,500 and 500 pound items as well as a 13,600 pound radome from the ground to the 75 foot tower over one to seven days in June 2023. Interested vendors are requested to respond to the federal contract opportunity with their capability statement, equipment, availability in June, experience, business history, programmatic approach, and rough order of magnitude cost estimate by May 31st, 2023 for budgeting purposes. The Federal Aviation Administration will evaluate responses for a potential small business set-aside of a single award contract.

Text of this file

5/22/20234/3/2023

Statement of Work (SOW)

SERVICES

Battle Mountain, NV CARSR Antenna & Radome Installation

Introduction and Overview This is an urgent and compelling requirement to support FAA Mission of Battle Mountain, NV ARSR-2 radar site. An antenna system and radome must be installed as soon as possible to restore FAA mission requirements.

The purpose of this requirement is for crane services to lift a beacon antenna, equipment, and radome structure onto the antenna deck.

Background On December 27th, 2022, the Battle Mountain (BAM), NV, CARSR system experienced an unscheduled outage, resulting in the loss of both Radar and Beacon Data Services (RDAT & BDAT). The Common Air Route Surveillance Radar (CARSR) is a long-range L-band radar with a range of 200 nautical miles. The CARSR has as its purpose the detection and tracking of aircraft that are Enroute from one airport to another.

BAM CARSR is located on the 9,600ft peak of Mt Lewis in Nevada and routinely experiences high winds, snow and ice during the winter season. The Airway Transportation Systems Specialist (ATSS) access the facility via snow-cat located at the Saddle snow-cat shelter, approximately 1.2 miles from the site. FAA Field Maintenance Program (FMP) crews only plow the roads to provide access the snow-cat shelter.

The Remote Maintenance and Monitoring (RMM) status for the CARSR system indicated an open antenna interlock. While attempting to access the facility, Wednesday, January 11th, 2023, the snow drifts exceeded the 20ft marker poles used to guide the snow-cat driver safely to and from the facility, preventing the ATSS from site access. Prior to returning, the visibility at the Saddle was sufficient to observe a catastrophic radome failure that encloses the Radar, Beacon and communication antennas.

On March 16th 2023, all radio communication links were lost, FAA, DOD and AT&T, from the Battle Mountain, NV location, causing Air Traffic to declare an Air Traffic Control (ATC) Alert for sectors 42 and 44. This alert requires that all commercial and civilian air traffic to be re-routed around the affected sectors. Airway Transportation Systems Specialist (ATSS) observed via helicopter that the CARSR/BI-6 antenna collapsed onto the communication equipment that provides the radio service to Air Traffic and other customers.

Scope of Work The vendor must provide crane, crane operator(s), and incidentals to lift antenna beacon, equipment, and radome structure from ground and or trailers to antenna tower deck (75ft) that is located on Battle Mountain, NV.

Crane lifts would be for the following:

Antenna Beacon: estimated at 1500lbs / dimensions of 28’x4’x8’ lifted from the ground/trailer and placed on 75’ tower

Spanko Gantry Crane: 4 pieces each under 500lbs / largest dimension would be a 10’ beam lifted from the ground/trailer and place on 75’ tower

Radome Structure: estimated at 13,600lbs / 45’ tall / Outside diameter is 59’ lifted from the ground and placed on 75’ tower

Note: Radome will have 80’ long lifting straps to assist the lift

Contractor must notify the FAA Contracting Officer (CO) immediately if change of schedule or delay is intended to utilize or incur any cost against the contingency contract line item which addresses delays.

Any changes to contract Firm Fixed Price must be coordinated prior to costs incurred. Only the FAA CO has the authorization on behalf of the FAA to agree to such changes. Any other agreements made between the contractor and other FAA personnel is at the contractor’s risk.

Period of Performance The FAA requires services for 1 day; Weather permitting the crane may be on site best case one day for the lift and drive time up and down. Worst case scenario one week.

The period of performance is June 17th- 21sts Crane Mobilization on June 17th

Crane set up on June 18th Crane Lift Attempt #1 June 19th Crane Lift Attempt #2 June 20th Crane Lift Attempt #3 June 21st

Any delays or changes to this start date or schedule prior to the start of work may be approved by the designated Contracting Officer’s Representative (COR), so long as there is no impact to contract price.

Any delays or changes to this start date or schedule after the start of work, or any changes that could result in future claim for additional payment must be coordinated with and approved by the Contracting Officer (CO).

Place of Performance Battle Mountain, NV: (Latitude: 40.403194, Longitude: - 116.867778).

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .