This Statement of Work (SOW) details a construction project for the Department of Veterans Affairs to renovate Building T 111 at the Boise Veterans Affairs Medical Center. The project involves comprehensive renovation work including new exterior walls, a sloped roof, concrete foundation, concrete ramps/porch, interior updates such as bathroom modifications, new walls, flooring, painting, door updates, and HVAC package unit upgrades. The contract has a 274-calendar day period of performance starting from the Notice to Proceed, with the Contracting Officer's Representative being Patrick Bird from the Facility Management Service located in Boise, Idaho. The project emphasizes that hospital operations take precedence, meaning construction activities may be restricted, curtailed, or rescheduled to minimize disruption to medical center functions, with strict requirements for safety, infection control, and site security.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

CONSTRUCTION

06/02/2025

VA Project Number: 531-24-101

VA Project Name: Renovate Building T 111

FORCE Contracting UID Number: TBD

1. CONTRACTING OFFICER’S REPRESENTATIVE (COR)

Name: Patrick Bird

Section: Facility Management Service (FMS)

Address: 500 W. Fort St., Boise, ID 83702

Phone Number: 208-422-1405

E-Mail Address: patrick.bird@va.gov

2. BACKGROUND

This project will renovate Building T 111 to make it more closely resemble existing campus architecture and provide minor updates to the interior of the building.

3. SCOPE

Contractor shall provide all tools, equipment, materials, labor, supervision, and management to complete the intent of project 531-24-101 in strict accordance with this SOW, contract drawings, and contract specifications. Any and all Work not specifically identified by the contract drawings and/or specifications but necessary for a complete system shall be included as if specifically identified in the Contract Documents.

Work includes, but is not limited to, demolition, site preparation, civil, structural, architectural, mechanical, plumbing, electrical, fire suppression, and fire alarm.

4. SPECIFIC TASKS

The Boise Veterans Affairs Medical Center is a Hospital First. Any and all construction activities shall be secondary to the mission of the Medical Center. This means that some activities shall only be performed outside of normal business hours, may be curtailed if they interfere with normal activities, and may be delayed for other times or conditions. Other potential issues include, but are not limited to noise pollution, noxious fumes, vibrations, parking and roadway restrictions, and limited utility tie-ins. Restrictions on activities may be imposed by the Contracting Officer (CO) even if they are below OSHA allowable limits. The CO or their designated representative shall have the final authority over the needs of the BVAMC.

Additionally, construction safety, infection control, and site security shall be prime requirements of the Work and as such any infraction may be considered a material breach of the Work and cause for termination for cause by the Government.

5. RENOVATE BUILDING T 111

Reference attached design drawings and specifications for project 531-24-101. The renovation of building T 111 will include new exterior walls to enclose the existing building and support a new sloped roof. This will include a new concrete foundation to support the gravity and lateral loads of the new structure. Work includes new concrete ramps/porch. The interior will have minor bathroom updates, new walls, new flooring, new painting, and new skins for existing doors. Work also includes updating existing HVAC package units.

6. TESTING

The Contractor shall be responsible for all testing and laboratory services in connection with this project as stated in the contract drawings and specifications. Testing and laboratory services include, but are not limited to concrete strength, compaction, and HVAC test and balance. The Contractor shall provide both paper and electronic copies of all test reports to the COR in a timely manner.

7. DISPOSAL OF MATERIALS AND EQUIPMENT

The Contractor is responsible for the correct disposal of all materials associated with this project. Details on documenting waste streams as well as a list of local recycling/disposal facilities will be provided to the Contractor at the start of work; compliance with disposal and documentation is required under the base bid contract.

8. COORDINATION OF WORK

If any questions or concerns arise, the Contractor shall contract the CO and/or the COR for direction. Any disruptions to the normal functions of the BVAMC (road closures, utility connections, etc.) shall be brought to the attention of the COR in writing at the earliest possible date. Refer to the contract specifications for allowable time frames of notification.

9. PERFORMANCE MONITORING

The Government is required to monitor contractor performance and certify the work was done in strict accordance with the contract. This monitoring will be done by the COR. At least weekly, the COR will perform Safety and Interim Life Safety inspection and Environmental inspections. In addition, the COR shall perform periodic inspections of the Work as further detailed in the Specifications. It is the Contractor’s responsibility to manage their schedule to allow adequate time for all inspections prior to proceeding with subsequent work.

A. Inspection and Acceptance Criteria

The COR is responsible for certifying that the work done under the contract is performed to time and standard. The COR is also responsible to assure the inspection and acceptance of in place products provided incidental to services. A demonstration period or trial period is not considered inspection of a product.

10. QUALITY CONTROL

The Contractor is responsible for their own quality control. Refer to specification 01 45 00 for expectations and reporting requirements related to quality control. Failure to comply with quality control requirements may result in removal of personnel from the jobsite and/or contract termination for cause by the Government.

11. SECURITY REQUIREMENTS

The Contractor shall only access BVAMC buildings directly associated with the Work. The Contractor shall not enter or attempt to enter any patient care area unless coordinated with the COR. Additionally, the Contractor shall provide construction site security as further identified in the Specifications or on the Drawings.

A. Contractor Parking and Material Laydown Area

Contractor parking and material laydown areas shall be within the dashed boundary “Approximate Limits of Work” as shown on contract drawings.

12. SPECIAL CONSIDERATIONS

Consideration for crane lift for installing roof trusses should be closely coordinated with the VA to minimize impacts to traffic on the entry road to the hospital for both patients and staff.

A. Phasing

There are no special phasing requirements for this contract.

B. Identification of Potential Conflicts of Interest

There are no known potential conflicts of interest.

C. Identification of Non-Disclosure Requirements

The Contractor shall not have access to sensitive and/or proprietary information. No non-disclosure agreements are anticipated for this contract.

D. Packaging, Packing, and Shipping Instructions

All deliveries shall be specifically addressed to the Contractor and not the BVAMC. The BVAMC shall make best efforts to refuse delivery of Contractor goods or materials. Any materials inadvertently received by the BVAMC will be identified to the Contractor for immediate pick-up.

The BVAMC takes no responsibility for the receipt of any goods or materials that are the Contractor’s. Additionally, the Contractor shall be responsible for receipt, offloading at the site, and storage of all delivered goods pertaining to this contract.

13. RISK CONTROL

The Contractor shall refer to division 01 specifications for guidelines on safety, risk, and infection control.

14. PERIOD OF PERFORMANCE

The contract period of performance shall be 274 calendar days from receipt of the Notice to Proceed. Refer to specification section 01 00 00 – 1.42 for detailed information on the contract schedule. Additional contract days may be negotiated during award if any add alternates are selected by the Government.

- End of Section -