SOW_Clauses_Wage_Determination.pdf

PDF 3 MB Posted

Attached to
WV-OHIO RIVER ISLAND-SHOP PAINTING
Solicitation number
140FC226Q0025
Issued by

About this file

This is a Statement of Work (SOW) and solicitation package for exterior and interior painting of the Middle Island Shop Building located in St. Mary's, West Virginia. The Fish and Wildlife Service (FWS) is seeking quotes for repainting a 54-foot by 100-foot building with 15.5-foot eave height. The project scope includes surface preparation (cleaning, filling cracks with 50-year paintable caulk, drying), replacement of deteriorated materials, removal of worked-out staples replaced with exterior-rated screws, and application of primer and two finish coats of high-quality name-brand paint (Valspar, Behr, Olympic, or approved equivalent). Color samples must be pre-approved by the Contracting Officer's Representative (COR) prior to purchase. The contractor shall supply all materials, labor, equipment (including boom lifts, ladders, scaffolding, brushes, rollers, spray equipment, drop sheets, and sandpaper), and complete cleanup upon project completion.

This small business set-aside solicitation (140FC226Q0025) has a firm fixed-price structure with quotes due by May 15, 2026 at 3:00 PM EDT, submitted electronically to William_Koski@ios.doi.gov. A mandatory site visit is scheduled for May 6, 2026 at 9:00 AM EDT, with questions due by May 7, 2026 at 3:00 PM EDT. The period of performance runs from June 2, 2026 to October 30, 2026 (60 days from Notice to Proceed, whichever is first), with work limited to daylight-to-dark hours. The COR is Vic Elam (Victor_Elam@fws.gov, 304-375-2923x125). The contract is subject to Davis-Bacon prevailing wage requirements, Buy American construction materials requirements, OSHA compliance, environmental and safety regulations, and standard federal contract clauses. Award will be made to the responsible respondent offering the lowest evaluated price determined fair and reasonable, without discussions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Middle Island Shop Building Painting Solicitation Number: 140FC226Q0025

FWS

STATEMENT OF WORK

Facility improvements by repainting the exterior (and interior of Lean-to) of the following facility:

Middle Island Shop building (RPI #10021849)

Location: Middle Island, George Street, St. Mary’s, WV, 39°24’24.02” N, 81°12’11.78” W

The requirements in this statement of work (SOW) are the basis for the refurbishment. The contractor shall use only high-quality materials for this refurbishment.

This will enable the contractor to assess the building and the site conditions for the project.

The building to be painted is shown in the Appendix of this document. The building measures 54 feet wide by 100 feet long, with an eave height of 15.5 feet.

Site Visit: 5/6/2026 @ 9:00 AM EDT. Please notify POC of intention to attend by COB 5/5/2026

POC: Vic Elam, Victor_Elam@fws.gov , 304 375 2923x125

Questions: Due 5/7/2026 by 3:00 PM EDT. E-mail questions to Contract Specialist: Bill Koski, at

William_koski@ios.doi.gov

Quotes Due: 5/15/2026 by 3:00 PM EDT, E-Mail quotes to Contract Specialist: Bill Koski, at

William_koski@ios.doi.gov

Period of Performance: 6/2/2026 to 10/30/2026, to be coordinated with COR, Victor Elam, Victor_Elam@fws.gov , 304 375 2923x125

Project Safety:

The Contractor shall be responsible for compliance with all Federal, State and Local Safety and

Environmental regulations to include provisions of Occupational Safety and Health Administration

(OSHA) requirements.

1. CODE OF FEDERAL REGULATIONS (CFR)

a. 29 CFR 1910 Occupational Safety and Health Standards (OSHA)

b. 29 CFR 1926 Safety and Health Regulations for Construction

Project Specifics:

1. Preparation:

Follow manufacturer’s recommendations regarding preparation of surfaces to receive paint and application of paint itself. Procedures shall include, but not necessarily be limited to, the following:

a. Cleaning – Pressure wash, compressed air, scrape, or brush to remove loose foreign matter, including; mold, mildew, and dirt in a manner which causes no undue damage to the substrate.

b. Filling – fill cracks and holes with name brand 50-year paintable caulk. Include all supplies and sundries into submittal.

mailto:Victor_Elam@fws.gov mailto:William_koski@ios.doi.gov mailto:William_koski@ios.doi.gov mailto:Victor_Elam@fws.gov

c. Drying – unless otherwise specified, ensure that surfaces are cured and dry before applying additional coats of paint as per manufacturer instructions.

2. General Requirements:

a. Replace any rotted or otherwise deteriorated boards or other materials that need to be replaced.

b. Remove staples that have worked their way out and replace with an exterior rated screw (pre-drill holes if necessary to prevent wood splitting).

c. Paint to be used – needs to be included in a submittal with the name brand (i.e., Valspar, Behr, Olympic) or approved equal for approval by the contracting officer representative (COR).

d. Primers, sealers, undercoats – ensure that primers, sealers, and undercoats are suitable for the substrate and compatible with the finish coat and each other.

3. Paint Application:

a. Apply primer coat if needed and/or two coats of the selected finish color paint or with the number of coats specified in accordance with the manufacturer’s recommendations. Allow each coat to harden for the drying time (or time between coats) recommended by the manufacturer.

b. Finish – ensure each coat of paint is uniform in color, gloss, thickness, and texture and free of runs, sags, blisters, or other discontinuities.

c. Over head doors, man doors, electrical panels, windows, and any other objects that are not currently painted the primary color of the building will not be required to be painted.

d. Any building part that is not to be painted shall be protected from overspray.

e. Do not apply paint when the surrounding temperature or humidity are outside of the manufacturer’s recommendations.

4. Colors:

a. Color samples must be pre-approved by the COR prior to purchase by the contractor.

b. Use only unadulterated paint except as per manufacturer's directions.

c. Do not combine paints from different manufacturers.

d. Use only the type and quantity of thinners recommended by the paint manufacturer.

Upon completion of the work all paint cans, other materials, containers, debris, and protective coverings shall be cleaned up and removed from the site and the contractor shall leave the area in a clean, neat, and orderly condition satisfactory to the COR.

General

1. All work is to comply with the local building regulations.

2. The contractor will rectify any damage to all areas on completion of the work.

3. The contractor shall supply all materials and labor to complete the work.

4. All waste material will be taken from the site and disposed of properly by the contractor.

5. Site is always to remain tidy and cleaned up on completion of work.

6. All work is to be carried out in a workmanship like manner.

7. All documentation regarding warranties, guaranties, and instructional literature are to be handed over to the COR.

8. All care must always be taken to protect the property/area and drop sheets to be used where necessary.

9. Any variations are to be priced and approved in writing by COR before proceeding with the work.

10. All measurements are to be confirmed by the contractor on site.

Note: Any damage caused by the contractor or his contractors is to be made good at the contractor’s expense.

CONTRACTOR PROVISIONS

The contractor shall supply everything necessary for the execution and completion of the work, including paint, brushes, rollers, spray equipment, drop sheets, sandpaper, fillers, sealants, scrapers, thinners, color charts, masking tape, lumber and other materials, boom lifts, ladders, and scaffolding.

WORKING HOURS

Working hours will be daylight to dark. No work is to take place outside of these hours unless the COR has approved.

PROJECT SCHEDULE

The contract time for this project is 60 days from the Contractor’s Notice to Proceed or by October 31, whichever comes first.

COR

The COR for this project is:

Vic Elam, Refuge Manager

Ohio River Islands National Wildlife Refuge

3982 Waverly Road

Williamstown, WV 26187

620-203-8514

Victor_elam@fws.gov

Note, this is not the location of this project – See location near the beginning of this SOW.

APPENDIX: Photo of the building to be painted.

mailto:Victor_elam@fws.gov

Shop building to be painted.

Section Title

Part I—The Schedule

A Solicitation/Contract Form

B Prices

C Description/Specifications/Statement of Work

D Packaging and Marking

E Inspection and Acceptance

F Project Delivery

G Contract Administration Data

H Special Contract Requirements

Part II—Contract Clauses

I Contract Clauses

Part III—List of Documents, Exhibits, and Other Attachments

J List of Attachments

Part IV—Representations and Instructions

K Representations, Certifications, and other Statements of Offerors

L Instructions, Conditions, and Notices to Offerors

M Evaluation Factors for Award

SECTION B – PRICES (QUOTE SCHEDULE)

N/A

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

See Attached SOW

(End of Section C)

SECTION D – PACKAGING AND MARKING

D.1.0 PAYMENT OF POSTAGE FEES

All postage and fees related to submitting information forms, reports, etc., to the CO or the COR shall be paid by the contractor.

D.2.0 MARKING

All information submitted to the Contracting Officer or the Contracting Officer's Representative shall clearly indicate the Contract Number of the contract for which the information is being submitted.

(End of Section D)

SECTION E – INSPECTION AND ACCEPTANCE

The following clauses are incorporated by reference:

52.246-12 INSPECTION OF CONSTRUCTION AUG 1996

(End of Section E)

SECTION F – PROJECT DELIVERY

F.1.0 PERIOD OF PERFORMANCE

See clause 52.211-10 in this section.

52.242-14 SUSPENSION OF WORK APR 1984

(End of Section F)

SECTION G – CONTRACT ADMINISTRATION DATA

Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP)

(February 2021)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform

System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

1. Invoice billed according to contract line items and rates.

2. Certified payrolls and Statement of Compliance in accordance with clause 52.222-8.

3. If the partial payment is billed and the invoice states a lump sum, the invoice shall include an itemized breakdown and narrative progress summary of the work performed during this invoice period.

4. If final payment is billed, the last invoice shall state “FINAL”.

5. Contractor’s Release of Claims shall be submitted with the final invoice.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor

Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve

Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-

3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

(End of Section G)

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1.0 WORK HOURS

https://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov

Unless otherwise specified in Section C, work hours under this contract shall be limited to the time between one-half hour before sunrise to one-half hour after sunset each day. No work will be performed on Saturday, Sunday, or Federal holidays unless authorized by the COR.

H.2.0 ENVIRONMENTAL INTERRUPTION OF WORK

H.2.1 Environmental - The Contracting Officer, by issuance of a suspend work order, may direct the Contractor to shut down any work that may be subject to damage due to weather conditions, fire danger, or because it is impracticable to work during the winter season. The Contractor will be given a resume work order which will document the date the work suspension ends. The Contractor will not be entitled to additional monetary compensation for such suspensions regardless of duration. An allowance has been included in the contract time for environmental delays. The count of contract time will therefore continue during all periods of suspension due to normal weather conditions, including fire danger. The Contractor will not be entitled to additional contract time for any suspensions except to the extent that they are due to unusually severe weather conditions.

H.2.2 Endangered Species - The Government may direct the Contractor to discontinue all operations in the event that listed or proposed threatened or endangered plants or animals protected under the Endangered Species Act of 1973, as amended, are discovered to be present in or adjacent to the project area.

H.3.0 DRAWINGS

H.3.1 Reduced Size Drawings. Drawings appearing in this package may be photographically reduced in size. Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. The Contractor may request full-size drawings from the COR.

H.4.0 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA

H.4.1 Public Law 93-291, May 24, 1974, provides for the preservation of scientific, prehistorical, and archeological data

(including relics and specimens) which might otherwise be lost due to alteration of the terrain as a result of any Federal construction project.

H.4.2 The Contractor agrees that should any contractor employee, in the performance of this contract, discover evidence of possible scientific, prehistorical, historical, or archeological data the contractor will notify the Contracting Officer immediately in writing giving the location and nature of the findings.

H.4.3 Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the applicable clauses in Section I of this contract.

H.4.4 The Contractor agrees to insert this requirement in all subcontracts which involve the performance of work on the terrain of the site.

H.5.0 SUBSTITUTION – PROCESSION OF WORK

Any proposed key personnel, minimum qualifications for incoming or replacement key personnel, subcontractors, processes, procedures or materials included in the quotation are hereby incorporated into the contract. Performance shall be limited to the personnel, qualifications, firms, procedures, and materials that were specifically identified in the

RFQ response. The Contractor shall obtain the Contracting Officer’s written consent before making any substitutions or changes. All substitutions or replacements shall comply with the terms and conditions of the contract.

H.6.0 ENVIRONMENTAL IMPACT

All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13 October 1978, Federal Compliance with

Pollution Control Standards; the Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 ET SEQ); the

Clean Air Act as amended (42 U.S.C. Sec 7401 ET SEQ); the Endangered Species Act, as amended (16 U.S.C. Sec

1531, ET SEQ); the Toxic Substances Control Act, as amended (15 U.S.C. Sec 2601, ET SEQ); the National Historic

Preservation Act, as amended (16 U.S.C. Sec 470, ET SEQ); the Solid Waste Disposal Act, as amended (42 U.S.C.

6901 ET SEQ); and the Archaeological and Historic Preservation Act, as amended (16 U.S.C. Sec 469, ET SEQ).

Should the United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.

H.7.0 HAZARDOUS MATERIALS

Any material suspected of being hazardous that is unexpectedly encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating.

Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR 1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.

H.8.0 GREEN PROCUREMENT REQUIREMENTS

In the performance of this construction contract, the Contractor shall make maximum use of products identified on the mandatory environmental purchasing list at the following links, as applicable:

U.S. EPA Comprehensive Procurement Guidelines published at www.epa.gov/cpg/products.htm.

USDA Biobased product listings published at www.biopreferred.gov.

Energy Star® product listings published at www.energystar.gov/products.

FEMP Low Standby Power product listings published at http://energy.gov/eere/femp/covered-product-categories

Contractor shall comply with all reporting requirements of the following clauses when applicable (See Clause and

Provision sections):

52.223-1 Biobased Product Certification

52.223-2 Reporting of Biobased Products Under Service and Construction Contracts.

52.223-4 Recovered Material Certification

52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items

H.9.0 UNAUTHORIZED PERSONNEL

The contractor shall inform all personnel working under their jurisdiction (including subcontractor and visiting supplier personnel) that access to restricted areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.

H.10.0 CONSTRUCTION WAGE RATES APPLICABLE TO TRUCK DRIVERS

29 CFR 5.2(j) limits coverage of construction contractor or subcontractor employees performing as truck drivers under the Davis-Bacon Act (FAR 52.222-6) to only their time spent directly upon the "site of the work" or when hauling between the site of the work and a facility which is dedicated to and located in the proximity of the actual construction location. Other transportation of materials or supplies to or from the site of work by employees of the construction contractor or subcontractor is not “construction” at the site of work and accordingly is not subject to the Davis-Bacon

Act.

H.11.0 FIRE DANGER SEASON

http://www.epa.gov/cpg/products.htm http://www.bioprefferd.gov/ http://www.energystar.gov/products http://energy.gov/eere/femp/covered-product-categories

If the COR allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.

(End of Section H)

SECTION I – CONTRACT CLAUSES

Clause Title Date

52.201-1 DEFINITIONS JUN 2020

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements JAN 2017

52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE OCT 2018

52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND

CERTIFICATIONS

DEC 2014

52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC

CORPORATIONS

NOV 2015

52.213-4 TERMS AND CONDITIONS-SIMPLIFIED ACQUISITIONS (OTHER THAN

COMMERCIAL ITEMS)

NOV 2024

52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE NOV 2020

52.222-3 CONVICT LABOR JUN 2003

52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS AUG 2018

52.222-7 WITHHOLDING OF FUNDS MAY 2014

52.222-8 PAYROLLS AND BASIC RECORDS JUL 2021

52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS FEB 1988

52.222-11 SUBCONTRACTS (LABOR STANDARDS) MAY 2014

52.222-12 CONTRACT TERMINATION – DEBARMENT MAY 2014

52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND

RELATED REGULATIONS

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988

52.222-15 Certification of Eligibility MAY 2014

52.222-30 CONSTRUCTION WAGE RATE REQUIREMENTS – PRICE ADJUSTMENT

(NONE OR SEPARATELY SPECIFIED PRICING METHOD

AUG 2018

52.222-31 CONSTRUCTION WAGE RATE REQUIREMENTS – PRICE ADJUSTMENT

(PERCENTAGE METHOD)

AUG 2018

52.222-32 Construction Wage Rate Requirements - - Price Adjustment (Actual Method) AUG 2018

52.222-50 COMBATING TRAFFICKING IN PERSONS OCT 2020

52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026 JAN 2022

52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022

52.222-90 Addressing DEI Discrimination by Federal Contractors (APR 2026)

(DEVIATION

APR 2026)

52.223-2 Reporting of Biobased Products Under Service and Construction Contracts MAY 2024

52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY FEB 2021

52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION. MAY 2011

52.223-11 Ozone-Depleting Substances and High Global Warming Potential

Hydrofluorocarbons

MAY 2024

52.223-12 Maintenance, Service, Repair, or Disposal of Regrigeration Equipment and Air

Conditioners

MAY 2024

52.223-23 Sustainable Products and Services (DEVIATION FEB 2025) MAY 2024

52.225-9

Buy American—Construction Materials OCT 2022

52.226-8 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING

WHILE DRIVING

MAY 2024

52.227-1 Authorization and Consent JUN 2020

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement JUN 2020

52.227-4 PATENT INDEMNITY-CONSTRUCTION CONTRACTS DEC 2007

52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS MAY 2014

52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS JAN 2017

52.232-33 Payment by Electronic Funds Transfer—System for Award Management OCT 2018

52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS JUN 2013

52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS

SUBCONTRACTORS

MAR 2023

52.233-3 PROTEST AFTER AWARD. AUG 1996

52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM. OCT 2004

52.236-2 DIFFERING SITE CONDITIONS APR 1984

52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK APR 1984

52.236-5 MATERIAL AND WORKMANSHIP APR 1984

52.236-6 SUPERINTENDENCE BY THE CONTRACTOR APR 1984

52.236-7 PERMITS AND RESPONSIBILITIES NOV 1991

52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

APR 1984

52.236-11 USE AND POSSESSION PRIOR TO COMPLETION APR 1984

52.236-12 CLEANING UP APR 1984

52.236-13 ACCIDENT PREVENTION NOV 1991

52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES APR 1984

52.236-16 QUANTITY SURVEYS APR 1984

52.236-17 LAYOUT OF WORK APR 1984

52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION FEB 1997

52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION – ALTERNATE I APR 1984

52.240.91 Security Prohibitions and Exclusions

52.243-5 CHANGES AND CHANGED CONDITIONS APR 1984

52.244-6 Subcontracts for Commercial Products and Commercial Services (DEVIATION FEB

2025)

Oct 2025

52.245-1 GOVERNMENT PROPERTY. SEP 1991

52.245-9 USE AND CHARGES APR 2012

52.246-21 WARRANTY OF CONSTRUCTION MAR 1994

52.247-63 Preference for U.S.-Flag Air Carriers JAN 2025

The following clauses are provided in full text:

52.225-9 – BUY AMERICAN–CONSTRUCTION MATERIALS (OCT 2022)

(a) Definitions. As used in this clause—

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at

Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, https://www.acquisition.gov/far/2.101#FAR_2_101 materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the

U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding

COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding

COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

________________________________________________[Contracting Officer to list applicable excepted materials or indicate

"none"]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the

Government determines that-

(i)The cost of domestic construction material would be unreasonable.

https://www.acquisition.gov/far/25.105#FAR_25_105 https://www.acquisition.gov/far/25.105#FAR_25_105 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/12.505#FAR_12_505

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1)The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2)For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3)The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1)The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2)For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3)The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the

Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting

Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the

Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction material description Unit of measure Quantity Price (dollars) *

Item 1

Foreign construction material https://www.acquisition.gov/far/25.105#FAR_25_105

Domestic construction material

Item 2

Foreign construction material

Domestic construction material

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]

[Include other applicable supporting information.]

(End of clause)

52.247-69 REPORTING REQUIREMENT FOR U.S.-FLAG AIR CARRIERS REGARDING TRAINING TO PREVENT

HUMAN TRAFFICKING (JAN 2025)

a) Definitions. As used in this clause—

Human trafficking means “Severe forms of trafficking in persons” or “Sex trafficking.”

Severe forms of trafficking in persons means—

(1) Sex trafficking in which a commercial sex act is induced by force, fraud, or coercion, or in which the person induced to perform such act has not attained 18 years of age; or

(2) The recruitment, harboring, transportation, provision, or obtaining of a person for labor or services, through the use of force, fraud, or coercion for the purpose of subjection to involuntary servitude, peonage, debt bondage, or slavery.

Sex trafficking means the recruitment, harboring, transportation, provision, or obtaining of a person for the purpose of a commercial sex act.

(b) Annual reporting requirement.

(1) In accordance with 49 U.S.C. 40118(g), the Contractor shall provide the annual report described in paragraph (b)(2) of this clause by October 30th, via email, to the following agencies:

(i) General Services Administration: TraffickingPreventionReport@gsa.gov;

(ii) U.S. Department of Transportation: trafficking@dot.gov;

(iii) Department of Labor: AirCarrier-HTreports@dol.gov;

(iv) Transportation Security Administration: ics-cchtfams@tsa.dhs.gov;

(v) U.S. Customs and Border Protection: CLP@cbp.dhs.gov; and

(vi) DHS Center for Countering Human Trafficking: Info@CCHT.dhs.gov.

(2) The annual report shall include information from the preceding Government fiscal year (October 1 through September 30) regarding—

(i) The number of personnel trained in the detection and reporting of potential human trafficking, including the training required under 49 U.S.C. 44734(a)(4);

(ii) The number of notifications of potential human trafficking victims received from staff or other passengers; and

(iii)

(A)Whether the Contractor notified the Global Human Trafficking Hotline, another comparable hotline, or law enforcement at the relevant airport of the potential human trafficking victim for each such notification of potential human trafficking; and

(B) If the Contractor made a notification, the date the notification was made and the method of notification (e.g., text to Hotline, call to law enforcement).

(c) Training. In accordance with 49 U.S.C. 44734 and 44738, personnel trained in the detection and reporting of potential human trafficking should include the following:

(1) Flight attendants;

https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title49-section40118&num=0&edition=prelim mailto:TraffickingPreventionReport@gsa.gov mailto:trafficking@dot.gov mailto:AirCarrier-HTreports@dol.gov mailto:ics-cchtfams@tsa.dhs.gov mailto:CLP@cbp.dhs.gov mailto:Info@CCHT.dhs.gov https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title49-section44734&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title49-section44734&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title49-section44738&num=0&edition=prelim

(2) Ticket counter agents;

(3) Gate agents; and

(4) Other air carrier workers whose jobs require regular interaction with passengers.

52.252-4 ALTERATIONS IN CONTRACT (APR 1984)

Portions of this contract are altered as follows:

52.217-7 – OPTION FOR SEPARATELY PRICED LINE ITEM (MAR 1989) – altered clause in Section I to better fit a construction contract rather than supply contract. [List this clause if altered version if found in Section I]

[Use this section to list provisions or clauses that have been altered by authority of “substantially the same as” language indicated in the prescription]

1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011) [use when a COR will be delegated]

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the

COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the

Contractor's risk.

1452.203-70 Restrictions on Endorsements. Restriction on Endorsements - Department of the interior (JUL 1996)

The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in

FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the

Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting

Officer to make a determination as to the propriety of promotional material.

1452.204-70 RELEASE OF CLAIMS (JUL 1996)

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

1452.215-70 Examination of Records by the Department of the Interior. Examination of Records by the Department of the

Interior (APR 1984)

For purposes of the Examination of Records by the Comptroller General clause of this contract (FAR 52.215-1), the Secretary of the Interior, the Inspector General, and their duly authorized representative(s) from the Department of the Interior shall have the same access and examination rights as the Comptroller General of the United States.

1452.236-70 PROHIBITION AGAINST USE OF LEAD-BASED PAINT—DEPARTMENT OF THE INTERIOR (JUL

1996) [use when construction of residential structures or rehabilitation (including dismantling, demolition, or removal) of residential structures is contemplated]

Paint containing more than .06 percent by weight of lead in paint, or the equivalent measure of lead in the dried film of paint already applied, shall not be used in the construction or rehabilitation of residential structures under this contract or any resulting subcontracts.

1452.204-70 RELEASE OF CLAIMS (JUL 1996)

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

(End of clause)

1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)

As prescribed in section 1401.670-1, insert the following clause:

Authorities and Delegations (SEP 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the

Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

1452.236-70 PROHIBITION AGAINST USE OF LEAD-BASED PAINT—DEPARTMENT OF THE INTERIOR (JUL 1996)

Paint containing more than .06 percent by weight of lead in paint, or the equivalent measure of lead in the dried film of paint already applied, shall not be used in the construction or rehabilitation of residential structures under this contract or any resulting subcontracts.

(End of Section I)

SECTION J – LIST OF ATTACHMENTS

Attachment 1 Wage Determination provided by The Department of Labor, General Decision Number:

(End of Section J)

SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality

Agreements or Statements-Representation

JAN 2017

52.209-2 Prohibition on Contracting with Inverted Domestic Corporations-Representation NOV 2015

52.223-1 Biobased Prodect Certification (DEVIATION FEB 2025) MAY 2024

52.223-4 Recovered Material Certification MAY 2008

NOTE for SAM Representations: System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations including

52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—Representation; paragraphs (d) and (t) of

52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services; and 52.222-25, Affirmative Action Compliance. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

The following provisions are provided in full text:

52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal

Law (FEB 2016) As prescribed in 9.104-7(d), insert the following provision:

(a)As required by sections 744 and 745 of Division E of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub.

L. 113-235), and similar provisions, if contained in subsequent appropriations acts, the Government will not enter into a…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .