SOW - Bldg. 1025 Roof Repair.pdf

PDF 114 KB Posted

Attached to
VGLZ182019 Repair Roof Building 1025
Solicitation number
W50S85-20-R-0008
Issued by

View the file

Other files

File Type Posted
Amdendment 1 20R0008.pdf PDF
site vist minutes 1025 roof.pdf PDF
30 July Site vist Sign in Sheet.jpg JPG image
SELFRIDGE Design Standards 10Nov2017.pdf PDF
W50S85-20-R-0008.pdf PDF
02_General Contract Spec.pdf PDF
SANGB Base Access List.xlsx XLSX spreadsheet
01b_General Specification - EPDM Roofing.pdf PDF
1025 roof inspection.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Project Number, Title: VGLZ182019 Repair Roof B1025 Civil Air Patrol 29 Jan 2020

The EPDM Specifications and Selfridge Design Standards apply to this Statement of Work (SOW). The work shall be in strict compliance with those specifications and the requirements identified in this SOW and its attachments.

Sections of this SOW may supersede the requirements of the specifications, in which case the more stringent/higher quality requirements shall apply. The number of pages in this SOW, including attachments, is 3.

1. This SOW provides for repair to B/1025 Star Base Roof, but is not limited to:

A. Contractor shall repair the following roof areas (refer to attached drawing)

52' x 27' Mod-Bit Roof – approximately 1,404 sf

B. Contractor shall remove existing ballast, curb build up, insulation and associated roofing material back to structural deck.

C. Contractor shall install new gravel stop, tapered insulation and cover-board over existing structural deck, see attached drawing. Insulation shall have a minimum slope of 1/4" per foot.

D. Contractor shall install 90-mil EDPM single ply roofing membrane over the newly installed tapered insulation and cover-board. EPDM to turn down vertical face of building envelope. EPDM shall extend 6” down face of building. New fascia to be installed over EPDM and gravel stop. Transitions between materials shall be flashed and sealed as applicable.

E. Contractor shall inspect, clean, repair and test roof drainage system components, as required.

F. Following repair contractor shall complete a water test, and provide a report as proof that the roofing assembly is preventing water from infiltrating the building.

G. Contractor shall provide a warranty for the repair. Warranty period shall be in line with the manufactures warranty guidelines. Repair methods shall target a 30 year warranty period.

2. Additional specifications for materials or requirements not included in the specifications:

A. See Selfridge Design Standards.

3. The following attachments are included in this SOW:

1. Roof Sketch dated September 2019

2. B/1025 Architectural Roofing Sketch

File details come from the government source that posted it. Updated .