This document is a Statement of Work (SOW) for the repair of a Caterpillar Model 430F Backhoe Loader at the Dallas Fort Worth National Cemetery. The SOW requires the contractor to provide all management, labor, tools, materials, and equipment necessary to replace the engine on the backhoe loader and return it to operational condition. The scope includes removing the old engine, installing a new complete engine replacement with warranty, and servicing the unit with new fluids. The contractor is responsible for engine core return. The contract will be managed by a Contracting Officer's Representative (COR) who will provide technical oversight and coordination with the cemetery's daily operations. The contractor must obtain all necessary licenses and permits and is responsible for any injury or damage during performance.
The related federal contract opportunity is Solicitation Number QSE--36C78624Q50384, issued by the Department of Veterans Affairs National Cemetery Administration, for the repair of the Caterpillar Model 430F Backhoe Loader with Serial Number 0RDF00741 at the Dallas Fort Worth National Cemetery. The solicitation is seeking offers for the engine replacement work described in the SOW.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
CATERPILLAR BACKHOE LOADER MODEL 430F
1. INTRODUCTION
Dallas Fort Worth National Cemetery, 2000 Mountain Creek Pkwy, Dallas, TX 75211 is looking for interested party who wishes to submit an offer to repair Caterpillar, Model 430F Backhoe Loader.
2. SCOPE
The contractor shall provide all management, supervision, labor, tools, materials, supplies, equipment, and any other items necessary to perform repairs, services, and installation of engine. All repairs and servicing shall return the backhoe loader to operational condition. Current know conditions of the equipment are listed:
Caterpillar, Model 430F Backhoe Loader, Serial Number 0RDF00741 - This unit is not currently operative.
The equipment requires a new engine due to metal in the engine oil system.
3. REQUIRED MAINTENANCE
The engine shall be replaced with a new complete engine replacement. The engine shall have a manufacture warranty and all parts and services. The repair station shall remove old engine, install new engine, remove, and reinstall all engine accessories (including pumps, A/C, etc.), service with new fluids (oil, radiator, etc.). All repairs and servicing shall return the backhoe loader to operational condition.
Since all repairs will be conducted at the repair shop facility, the government is not responsible for any engine core charge. The repair shop is responsible for returning the engine core in a timely manner.
All quotes shall include any travel, freight, miscellaneous supplies, labor fees, and disposal fees included.
4. CLIN STRUCTURE
0001 Caterpillar, Model 430F Backhoe Loader - Engine Replacement
5. CONTRACT MANAGEMENT
A. REPRESENTATIVES OF THE CONTRACTING OFFICER
1. The Contracting Officer reserves the right to designate representatives to act for him/her in furnishing technical guidance and advice or generally supervises the work to be performed under this contract. Such designation will be in writing and will define the scope and limitations of the designee's authority. A copy of the designation(s) shall be furnished to the Contractor at time of award.
2. The VA Contracting Officer will delegate one (or more) representatives to serve as the Contracting Officer’s Representative (COR). The COR may direct and arrange the Contractor’s work schedule in specific areas of the cemetery to coordinate with daily cemetery activities and operations.
Duties and responsibilities of the COR include, but are not limited to, the following:
(i) Provides contract oversight and technical guidance to the Contractor.
(ii) Acts as technical liaison between the National Cemetery and the Contractor and between the cemetery and the Contracting Officer.
(iii) Placing orders for services.
(iv) Determining whether contract deliverables meet functional, technical and performance specifications.
(v) Verification / certification of payments to the Contractor for services rendered.
(vi) Assuring that any changes effecting work involved, price, terms and/or conditions under the contract are not implemented before written authorization is issued by the Contracting Officer.
(vii) The COR may not modify the intent or the terms and conditions of the contract.
3. Contracting Officer: All administrative functions remain with the VA Contracting Officer. Any modifications to the contract, including those involving no-cost changes, increases and decreases in cost or level of services provided, termination or extension of the contract (in part or in whole) and decisions concerning claims or disputes, must be authorized in writing by the Government Contracting Officer.
B. Communication & Coordination of Work with COR: Communication with the COR (or designee) is strongly encouraged. Burial activities at NCA shall take precedence over contract work activities.
Work activity and noise cannot disturb Burial Services. Trucks and workmen are prohibited from passing through the service area during this period.
C. Notwithstanding the Contractors responsibility for total management during the performance of this contract, the administration of the contract will require maximum coordination between the Government and the Contractor. The Government shall provide, at the time of contract award, a list of Government personnel authorized to act as Contracting Officer's Representatives.
6. RESPONSIBILITIES
INSURANCE, LICENSES & PERMITS
The Contractor shall obtain all necessary licenses and permits necessary to perform the work involved and will take all precautions necessary to protect persons and property from injury or damage during the performance of this contract. Contractor is responsible for any injury or damage during the performance of this contract including injury to himself/herself, his/her employees, or others.
The Contractor shall be responsible for maintaining satisfactory standards of personnel conduct and work performance.
(End of Work Statement)