SOW - B205 Boiler Vent Piping Replacement- CONS revised (1 Apr).pdf
PDF 1 MB Posted
- Attached to
- Buckley SFB - Replace Boiler Vent Piping
- Solicitation number
- FA2543BoilerExhaustVentReplacement
About this file
Statement of Work Summary
This is a Statement of Work (SOW) for replacing boiler vent piping at Building 205, located at 606 S. Aspen St., Buckley Space Force Base, Colorado. The work scope covers replacement of both exhaust and air intake vent piping for four Lochinvar boilers: two Model FBN1001 domestic hot water boilers and two Model AWN 1000 heating boilers. The contractor must provide all supplies, materials, tools, equipment, and qualified labor necessary to complete the project. All work must comply with manufacturer specifications and multiple governing standards including UFC 3-410-01 and UFC 3-420-01, the National Fuel Gas Code (ANSI Z223.1), NFPA 101, the International Mechanical Code, OSHA 1926.55, and applicable state and local codes. The contractor is required to review all equipment manufacturer installation and operation manuals before beginning work.
The period of performance is 60 calendar days after date of award, with utilities to remain functioning throughout the project. The contractor must provide a certified inspector to conduct inspections at various points and upon completion must perform multiple leak checks (both static and operational), draft analysis, and combustion analysis on all boilers. All vent piping material must be CPVC as specified in the Lochinvar installation manuals. Final deliverables include a comprehensive report containing photographs, inspection dates and times, leak check results, operational and safety check summaries, draft analysis reports, combustion analysis reports, and any identified unit deficiencies. The contractor is responsible for removing and disposing of all removed materials off-site, and a pre-bid site visit can be scheduled with a designated staging area and government-provided utilities available.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B205 Boiler Venting Sources Sought.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF
WORK
FOR
B205 Replace Boiler Vent Piping
606 S. Aspen St.
Buckley SFB, Colorado
80011
CAO: 1 Apr 2026
1.0 Scope of Work
1.1 Primary Objective
The Contractor shall provide all supplies, materials, tools, equipment, and qualified labor necessary for replacing all boiler venting (exhaust & inlet) at Bldg. 205. The existing boiler venting is deteriorating due to ongoing condensate leaks creating a risk of failure that could release hazardous flue gases into the facility. Replacing boiler venting will ensure proper system operation and the continued safety of the facility and its occupants.
1.2 Vent Piping Replacement
The contractor is responsible for providing all material and qualified labor necessary to replace both the exhaust and air intake vent piping for all four boilers in building 205:
• (2) Lochinvar domestic hot water boilers Model #: FBN1001
• (2) Lochinvar heating boilers Model #: AWN 1000
• Prior to beginning any work, the contractor shall thoroughly review all equipment manufacturer Installation and Operation manuals in their entirety. After reviewing all manuals, the contractor will replace all boiler venting in accordance with UFC 3-410-01: Heating, Ventilating, and Air Conditioning Systems; UFC 3-420-01: Plumbing Systems; National Fuel Gas Code, ANSI Z223.1; OSHA 1926.55; NFPA 101, Life Safety Code; International Mechanical Code (IMC); National Mechanical Code, Section 305, Table 305.4; National Building Code, Section 305, Table 305.4; all applicable state/local codes, and the manufacturer's specifications.
1.3 Inspecting / System Analysis
The contractor will provide a certified inspector to conduct inspections at various points throughout the project. The contractor’s inspector will work closely with 460th CES project managers and inspectors to communicate and identify any issues in a timely manner.
Upon completion of the vent piping replacement, the contractor shall:
• Perform inspections of the newly installed vent piping to ensure the following:
• All vent connections to the appliances are safely made using the proper fittings and materials in strict accordance with manufacturer’s specifications and section 1.6.
• All vent piping is properly secured and supported according to standards in section 1.6.
• All vent piping is airtight and properly sealed according to standards in section 1.6.
• All vent piping meets proper clearances according to standards in section 1.6
• All vent piping is properly pitched per manufacturer’s specifications & standards in section 1.6 to allow condensate drainage.
• All vent piping is properly exhausting combustion gases according to standards in section 1.6.
• Conduct multiple comprehensive leak checks on all newly installed piping, both while the units are static and again under full operational load.
• Perform draft analysis to ensure combustion gases are properly venting out of the facility.
• Perform a combustion analysis on all boilers to ensure safe and efficient operation.
• Coordinate with the 460th CES project manager for a final inspection by the Fire Department following project completion.
1.4 Recommissioning Systems
After testing and completing system analysis, the contractor will perform an operational check of all systems and ensure units are operating safely IAW standards in section 1.6.
Upon completion, the contractor will deliver a deficiency report detailing any compromised components or units requiring further attention. If any additional work or replacement of any system components is recommended, the contractor must provide a separate, detailed report with clear justification for the recommendation.
1.5 Contractor-Furnished Items
All vent piping material must be compliant with the options listed in the Lochinvar installation and operation manual for the specified boiler models.
The contractor is responsible for providing all necessary materials and equipment, including but not limited to:
• All vent Piping material (CPVC as listed in Operations Manual).
• Any starter sections or adapters needed to safely connect venting to the appliances in strict accordance with manufacturer’s specifications.
• All specialized tools required to re-commission units, perform draft analysis, conduct combustion analysis, and complete operational tests of all gas-fired equipment.
1.6 Governing Standards
All work shall be performed in strict accordance with the manufacturer's specifications and the latest editions of the following:
• UFC 3-410-01: Heating, Ventilating, and Air Conditioning Systems
• UFC 3-420-01: Plumbing Systems
• NFPA 101, Life Safety Code
• International Mechanical Code (IMC)
• National Fuel Gas Code, ANSI Z223.1
• OSHA 1926.55
• Applicable ASME Boiler and Pressure Vessel Codes
• National Mechanical Code, Section 305, Table 305.4
• National Building Code, Section 305, Table 305.4
• All applicable state and local laws/codes
UFC criteria can be accessed via the Whole Building Design Guide at https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc
2.0 Project Logistics & Scheduling
• Period of Performance: 60 calendar days after date of award.
• Utilities will be required to remain functioning to the facility during this scope of work.
https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc
• Site Access & Coordination:
• A pre-bid site visit can be scheduled.
• A designated staging area for materials and equipment will be provided.
• The contractor will have access to Government-provided utilities. A restroom is available on the first floor for contractor use.
3.0 Technical & Compliance Requirements
3.1 Definition of Qualified Labor
The contractor must ensure all technicians are certified and licensed to service, repair, and install the following Lochinvar commercial boilers in accordance with the standards listed in Section 1.6.
• (2) Lochinvar domestic hot water boilers Model #: FBN1001
• (2) Lochinvar heating boilers Model #: AWN 1000
3.2 Reporting & Deliverables
Upon project completion, the contractor shall submit a final report of work containing the following detailed information:
• Photographs of the completed work.
• Inspection times and dates.
• Results of all leak checks(for both static and operational states).
• A summary of all operational and safety checks performed.
• A complete draft analysis report for all equipment.
• A complete combustion analysis report for all equipment.
• A detailed summary of any unit deficiencies discovered during re-commissioning.
3.4 Disposal of Materials
The contractor shall remove and dispose of all removed parts and materials after the project is complete. Materials shall not be disposed of anywhere on Buckley SFB.
4.0 ATTACHMENTS:
Attachment 1: Manufacture’s data plates
- Attachment 2: Photos of pipping
Attachment 3: FD Life Safety Hazard MFR
File details come from the government source that posted it. Updated .