This is a Statement of Work (SOW) for design-build construction services at Mountain Home Air Force Base (MHAFB) in Idaho, with a 90-calendar-day performance period from Notice to Proceed. The project (17505902, FA489726Q0003) involves upgrading Direct Digital Controls (DDC) and associated HVAC equipment in Building 1501, replacing existing Johnson Controls International (JCI) systems with new Automated Logic equipment.
The contractor must provide all labor, materials, services, oversight, and direction to replace controls for 2 air handling units (AHUs), 20 variable air volume (VAV) units with reheat, 4 VAVs with reheat and CO2 capability, 2 fan coil units, and install 1 HVAC emergency shutdown switch, 1 hot water system control, 1 hot water loop pump, 1 outside air sensor, and 1 BACnet router. The current system contains 134 control points. Key deliverables include an environmental protection plan, as-built drawings, recycled material weight tickets, equipment cut sheets, and operation and maintenance manuals with sequence of operations. All work must comply with UFC, IBC, IMC, IPC, IECC, NEC, NFPA, ICC, AFETL, and AFI standards. The contractor shall pre-configure all new devices, conduct all digital work through maintenance laptops connected to the Energy Management Control System (EMCS) network, sanitize IP addresses, provide BACnet router integration with boilers, map new points to the existing Automated Logic front-end server in Building 1300, and ensure system startup and functional operation. Project closeout requires two copies of operation and maintenance manuals, on-site system training with end users, and a final acceptance meeting with a punch list for any deficiencies. The government provides a one-year warranty period from final acceptance, with the contractor responsible for remedying all defects at contractor expense. Points of contact include Contracting Officer Ryan J Rubenstein, Contract Specialist Caleb Ferch, and Project Manager Mr. Jeff Jackson.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Presolicitation -SS-26Q0003-B1501 HVAC Controls Upgrade.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
For Construction
February 2026
Project: 17505902
FA489726Q0003
Direct Digital Controls Upgrade, Building 1501
Mountain Home AFB, Idaho
1.0 INTRODUCTION
1.1. The United States Government (USG) has a requirement for design-build construction services to replace the existing Direct Digital Control (DDC), and associated equipment with new equipment in Building 1501 located on Mountain Home Air Force Base (MHAFB).
2.0 BACKGROUND INFORMATION
2.1. Building 1501 is located off Gunfighter Ave and Desert St., 360 Mountain Home AFB, 83648 Idaho. The base is transitioning to Automated Logic which will replace all the current JCI controls within the building. A portion of the building has a secure area which will require advance notice to gain entry, schedule with the facility manager. Contractor will be furnished with the equipment room key which will be returned upon completion of the project.
3.0 PRIOD OF PERFORMANCE
3.1. The period of performance for the following Statement of Work (SOW) shall be 90 calendar days from the Notice to Proceed (NTP).
4.0 GENERAL REQUIREMENTS
4.1. Contractor is to provide all labor, materials, services, oversight, and direction to complete the construction/installation of the requirements identified in this Statement of Work (SOW) to replace all controls for 2 AHU’s, 20 VAV’s with reheat, 4 VAV’s with reheat and CO2, 2 Fan coil units (AC- 1&2), install 1 HVAC Emergency Shutdown switch, 1 hot water system control, 1 Hot water loop pump, 1 Outside Air sensor, and 1 BACnet Router. Current system has a total of one hundred and thirty-four points. Detailed requirements are listed below but in general this project will replace the current DDC controls with updated equipment for the existing HVAC equipment. All construction will be required to adhere to the current standards set forth by UFC, IBC, IMC, IPC, IECC, NEC, NFPA, ICC, AFETL, AFI, and other applicable standards as referenced in this Statement of Work. This SOW only provides explanation of the basic desired facility/s and any requirements that are in addition to the afore-mentioned standards. Since this SOW does not reference specific applicable standards, the
Contractor shall present a proposal that reflects a thorough review of all standards, codes, and regulations that apply to the requirements within this SOW.
4.2. The Contractor shall verify site conditions and any site dimensions needed for design and construction.
4.3. The Contractor shall identify and obtain all required permits from Mountain Home AFB, federal, state, and local agencies
4.4. The Contractor shall fill out DAF Form 4394, Department of the Air Force User Agreement (Attachment 1) and DD Form 2875, System Authorization Access Request (SAAR) (Attachment 2) to access EMCS network. After assigning devices EMCS network IP addresses, maintenance laptops will be required. To use maintenance laptops, contractors will sign in at EMCS shop and sign out daily.
4.5. Contractors shall follow the base Environmental Protection Plan Section 01 57 19, Change 2 (Attachment 3) for hazardous materials. A copy of the Environmental Protection Plan will be provided with this SOW.
4.6. The Contractor shall remove and dispose of all components of the existing HVAC system that is replaced by the new system.
4.6.1. Recyclable materials may be taken to the base recycle center otherwise such materials will need to be disposed of off base.
4.6.2. All recycled material weight tickets shall be submitted to the Contracting Officer for Government records.
4.7. Material storage and contractor staging areas (laydown yard) will be selected during the pre-construction site visit.
4.8. During the progress of the work, the Contractor shall keep a careful record at the job site of all changes and corrections from the layouts shown on the drawings, if applicable, regardless of whether they are a part of the construction effort or not. This shall include any hidden or subsurface data discovered during construction. The Contractor shall enter such changes and corrections on a copy of the deliverable Final Construction Drawings and provide the Contracting Officer (CO) with a copy of the updated drawings
5.0 SUBMITTALS:
5.1. Environmental Protection Plan
5.2. As-Built Drawings
5.3. Recycled material weight tickets,
5.4. Controllers cut sheets, and O&Ms for all equipment installed.
5.4.1. All submittals shall be provided to the CO for review.
6.0 DESCRIPTION OF WORK
6.1. The Contractor shall verify site conditions and any site dimensions needed for design and construction.
6.2. The current HVAC system mechanical schedule can be provided upon request. The drawing should only be used as a guide since some components may have subsequently been removed, replaced, or added. The Contractor shall verify, gather, and/or generate all data required to produce a complete design to include a controls sequence of operations as it relates to the current systems.
6.3. Contractors shall minimize any interruption with building operations. Any required lengthy downtime needs to be scheduled 1 week in advance with the project manager.
6.4. All work shall be in accordance with current Department of Defense Unified Facility Criteria (UFC) 1-200-01 DoD Building Code (Attachment 4, Change 4), UFC Series 3-400 Mechanical (Attachment 5, Change 1), UFC Series 3-500 Electrical Engineering (Attachment 6, 2024), UFC 3-600- 01 Fire Protection Engineering for Facilities (Attachment 7, Change 6), and NFPA 1 , ASHRAE 135, and UFC 3-410-02 DDC for HVAC (Attachment 8, Change 2).
6.5. The Contractor shall produce and submit a complete HVAC Controls drawing submittal that adheres to current standards set forth by UFC 1-200-01 DoD Building Code, UFC Series 3-400 Mechanical, UFC Series 3-500 Electrical, UFC 3-600-01, and NFPA 1, ASHRAE 135, and UFC 3-410- 02 DDC for HVAC. The Government shall have 10 Calendar days to review the design submittal before providing comments. Job requirements and considerations include:
6.5.1. Demo existing JCI cabinets, controllers and thermostats.
6.5.2. Replace existing DDC control modules, wiring, and terminations. Replace existing DDC control modules, wiring, and terminations.
6.5.3. Provide and install a new, open protocol, web based, direct digital automatic control system to serve the entire project.
6.5.4. Install new cabinets for hardware, do not install them in existing cabinets.
6.5.5. Pre-configured all new devices prior to connecting to the Energy Management Control System (EMCS) network.
6.5.6. All digital work while/after connected to EMCS network must be conducted through maintenance laptops.
6.5.7. All software upgrades required to complete work on EMCS network connected devices must be transferred in CD format.
6.5.8. Replace existing JCI controls with new DDC equipment.
6.5.9. Sanitize all Internet Protocol (IP) Addresses on equipment replaced.
6.5.10. In the event of a control valve needing to be replaced, draining of the system must be conducted by United Staes Government (USG) base personnel if isolation valves are not working or available.
6.5.11. Provide and install the required control valves, actuators and ancillary DDC material.
6.5.12. Run, install, and program in a New HVAC Emergency Shutdown button. Project manager will clarify location of button installation.
6.5.13. Provide and install 24V transformers for DDC controllers.
6.5.14. Provide BACnet integration with system boilers. (Boiler interface card provided with equipment)
6.5.15. Provide and install new controllers in place of existing JCI.
6.5.16. Label all controllers, wiring, and cabinets with proper tag ID.
6.5.17. Provide BACnet Router/Global Controller with program memory.
6.5.18. Map all new points to existing Mountain Home AFB Automated Logic front-end server located in Building 1300.
6.5.19. Provide all programming, graphics, and download/commissioning.
6.5.20. New units should be installed according to the manufacturer’s instructions and recommendations.
6.5.21. Startup and ensure functional system operation.
7.0 PROJECT CLOSEOUT:
7.1. The Contractor shall furnish two (2) copies of operation and maintenance manuals for any product installed in the construction project as well as a Sequence of Operations. The manuals shall contain complete instructions for operation, inspection, testing, and maintenance of the system and shall include part breakdown diagrams. If applicable, the manuals shall also contain complete wiring schematics and diagrams. Organize operation and maintenance data into suitable sets of manageable size as indicated in the Mountain Home Base Design Standards, “Operations and Maintenance Manuals”. The Contractor shall provide the CO all paperwork that was shipped with or attached to the product or material.
7.1.1. Provide on-site system training/walk-through with end users.
7.1.2. Contractor shall request from the CO a final acceptance meeting. The request shall be in writing (email is sufficient) at least three (3) working days prior to the meeting.
7.1.3. Meeting will be chaired by the CO and attended by appropriate Government and Contractor personnel. It is mandatory the Contractors Project Superintendent be in attendance.
7.1.4. If during the final acceptance meeting it becomes obvious to the CO that the TO is not ready for final acceptance, the CO will immediately cancel the final acceptance meeting and direct the Contractor to reschedule when the work is complete.
7.1.5. The Government will generate a punch list of deficiencies that the Contractor must complete prior to the Government taking beneficial occupancy of the facility. During the final acceptance meeting, the CO will ask the Contractor how much time he/she requires to correct the deficiencies and both parties will come to an agreement on the number of days to correct the deficiencies. The Government will schedule a meeting to verify the deficiencies are corrected.
8.0 WARRANTY:
8.1. In addition to any other warranties in this contract, the Contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, workmanship or contractor furnished design or that furnished by any subcontractor or supplier at any tier. This warranty shall not limit the Government’s rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes and/or fraud.
8.1.1. This warranty shall continue for a period of one (1) year from the date of final acceptance of the work.
8.1.2. If the Government takes beneficial occupancy of a portion of the project, prior to final acceptance of the entire project, the warranty for the portion occupied will commence on the date of its occupancy.
8.1.3. For all other portions not beneficially occupied, the warranty shall begin on the date of their beneficial occupancy, or final acceptance of the entire project, whichever occurs first.
8.1.4. The Contractor shall remedy, at the Contractor’s expense, any failure to conform or any defect. In addition, the Contractor shall remedy, at the Contractor’s expense, any damage to Government-owned or controlled real or personal property when that damage is the result of:
8.1.5. The failure by the Contractor, subcontractor, or supplier at any tier, to conform to contract requirements or, any defect of equipment, material, workmanship, or design furnished.
8.1.6. The Contractor’s warranty with respect to work repaired or replaced will run for one year from the date of repair or replacement.
8.1.7. The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
8.1.8. If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.
8.1.9. With respect to all warranties, express or implied, from subcontractors, manufacturers or suppliers for work performed and materials furnished under this contract, the Contractor shall:
8.1.9.1. Obtain all warranties that would be given in normal commercial practice.
8.1.9.2. Require all warranties to be executed, in writing, for the benefit of the Government if directed by the Contracting Officer and enforce all warranties for the benefit of the Government if directed by the Contracting Officer.
9.0 FILE TRANSFERS
9.1. Files may be transferred via email; larger files will be sent electronically via DoD Safe.
10.0 POINTS OF CONTACT
Contracting Officer (KO): Ryan J Rubenstein ryan.rubenstein.1@us.af.mil Contract Specialist (CS): Caleb Ferch caleb.ferch.1@us.af.mil Project Manager (PM): Mr. Jeff Jackson jeffery.jackson.3@us.af.mil Construction Inspector (CI): Mr. Jeff Jackson
11.0 ADDITIONAL INFORMATION
11.1. Authority. Under no circumstances shall anyone other than the Contracting Officer (CO) have authority to make any commitments or changes on behalf of the Government with the contractor that affect price, quality, quantity, delivery, or any other terms and conditions of the contract, nor shall any other Government representative in any way direct the contractor or its subcontractors to operate in conflict with the contract terms and conditions. The Contractor shall immediately notify the CO, in writing, if any written or oral direction, instruction, interpretation, or determination is received from the Contracting Officer that causes or that the Contractor believes will cause a change, or that the Contractor regards as a change order.
11.2. Commencement. Upon award, the Contractor shall proceed with securing payment and performance surety bonds. No other efforts shall commence until the CO issues a Notice to Proceed (NTP), except for attendance of a predesign conference or preconstruction conference. Upon receipt of an NTP, the Contractor shall proceed with all other efforts required by the contract. Only one NTP will be issued for all project efforts. No on-site construction shall commence prior to Government approval of preconstruction submittals, including all design efforts and deliverables for design-build projects, unless expressly authorized by the CO.
11.3. Progress of Work. The scheduling and reporting of percentage of completion contemplated by FAR Clause 52.232-5 Payments under Fixed-Price Construction Contracts and 52.236-15, Schedules for Construction Contracts, shall be accomplished on or equivalent to an Air Force Form (AF) 3064, Contract Progress Schedule, and AF Form 3065, Contract Progress Report. The project schedule shall incorporate, as applicable, milestone events specified in the contract, including, notice to proceed, substantial completion, milestones related to specified work phases and site restrictions, Contractor-defined milestones to identify target dates for critical events based upon the Contractor's chosen sequence of work, and depict all major activities necessary to complete the work. The Contractor shall also prepare and submit for approval a cost breakdown of the Contract price, to be referred to as the “schedule of values”, assigning values to each major activity necessary to complete the work. Values must include all direct and indirect costs, although a separate value for bond costs may be established.
The schedule of values must contain sufficient detail to enable the Contracting Officer to evaluate applications for payment. If the percentage completed for the monthly reported period is less than the approved scheduled percentage the contractor shall provide the CO with an explanation for falling behind. If progress will not be regained within the next monthly reported period, the contractor shall provide the CO a supplementary schedule for approval demonstrating how progress will be regained.
Progress payments may be made up to substantial completion (95%) and after a pre-final inspection has occurred with the CO. The final progress payment of 5% (Final Invoice) will only be made following completion of any remaining punch-list items and final inspection, submission of the final progress report (100%), any remaining submittals, records, drawings, payrolls, Standard Form 1413s, release of claims, and other closeout documents, and turnover of Government property (materials, equipment, keys, etc.).
11.4. Submittals. All submittals will be coordinated through the Contracting Office using an AF Form 3000 Material Approval (Attachment 9). All equipment, material, and articles incorporated into the work are subject to the approval of the CO. The CO may request submittals that are absent from the submittal register but are incorporated into the work or that the contractor contemplates incorporating into the work. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements. If the submittal is incomplete or otherwise does not provide the Government with sufficient detail, the CO may request additional information to determine compliance.
Each additional submittal request or request for additional information shall not be construed as a change, Government delay, or entitle the contractor to any equitable adjustment.
11.5. The Government shall be allotted 14 calendar days after the date the Government receives a submittal or resubmittal to complete reviews. Upon transmission of the submittal to the Government the contractor shall confirm its receipt. Approval or disapproval of a submittal shall not be construed as a complete check and indicates only that the Government objects or does not otherwise object to the submittal. Approval shall not relieve the contractor of the responsibility to meet contract requirements or for any error. Government review comments may be ‘for-information-only’ and therefore not a basis for approval or disapproval. Government review comments shall not relieve the contractor of their responsibility for quality control. All preconstruction submittals shall be approved prior to commencement of any construction at the work site, unless otherwise authorized by the CO.
11.6. Design-Build: For a project that is design-build in nature, where the construction contractor has overall responsibility for producing the necessary specifications and drawings to fulfil the government requirement, the Government scope of work does not specify project submittal requirements. Submittal requirements are driven by the design. It is the responsibility of the contractor to be aware of standardized and project-specific submittal requirements in the Unified Facilities Guide Specifications (UFGS) that will be applicable to the project when preparing offers and post-award activities such as developing project schedules. Applicable submittal requirements from the project scope of work or specifications may not be removed/waived by the contractor (e.g. SD-01 Preconstruction Submittals, Contractor Quality Control Plan).
11.7. Coordination: All work shall be conducted under the general direction of the CO and subject to daily inspection by the Government. References to “Contracting Officer” in the scope of work, specifications, drawings, etc. may be interchangeable with Contracting Officer’s Representative (COR), Contracting Officer’s Technical Representative (COTR), Project Manager (PM), Inspector, Subject Matter Expert (SME), “shop”-specific personnel, or other Government representative(s) that are assisting the CO with technical monitoring or administration of contract requirements, identified, appointed, or delegated certain responsibilities by the CO. Generally, this will be the PM or Inspector.
11.8. The Contractor shall confirm with the CO who is/are the responsible Government representative(s) for the Contractor to successfully coordinate all construction activities. When a work task specifically requires the presence/witness of a responsible Government representative, the Contractor shall ensure the presence/witness is coordinated not later than one week before the work task is scheduled to be completed.
11.9. All construction at the work site shall only be conducted between the hours of 7:00 am and 5:00 pm, Monday through Friday, unless otherwise authorized by the CO. Weekends, Federal holidays, and any associated ‘AF Family Day’, ‘Down Day’ or ‘Goal Day’ are non-workdays and decrease the availability of Government personnel for coordination.
11.10. Federal holidays are:
11.10.1.New Year’s Day (and associated Family Day); Birthday of Martin Luther King Jr;
Inauguration Day; Washington’s Birthday/President’s Day (associated Family Day);
Memorial Day (associated Family Day); Juneteenth National Independence Day;
Independence Day (associated Family Day); Labor Day (associated Family Day); Columbus Day; Veterans Day; Thanksgiving Day (associated Family Day); and Christmas Day (associated Family Day).
11.10.2.Further decreased availability of Government personnel shall be anticipated during the workweeks of the Thanksgiving, Christmas and New Year’s holidays. It is the responsibility of the Contractor to adequately plan for and schedule all coordination necessary (i.e. base/site access, submittals, construction) in advance of known non-workdays.
11.11. Base Access. The Visitor Control Center (VCC) must receive a Security Forces Squadron (SFS) Form 30 (Attachment 10) for each contractor and subcontractor employee that needs access to the base not later than two weeks prior to construction start or otherwise before a valid need for base access. The Contractor shall submit all project SFS Form 30s to the CO (Sponsor) for processing to the VCC prior to the two-week lead time. No consideration shall be given to the Contractor for delays or cost increases experienced due to failing to request base access in a timely manner, nor due to the denial of base access to a contractor or subcontractor employee following the Government-performed background check.
11.12. The contractor shall be responsible to track all contract employees and pass expirations for the duration of the projects, and retrieval/turn-in of passes to the VCC when the project is complete.
11.13. Base access under this contract shall adhere to the most current entry protocols found at https://www.mountainhome.af.mil/Base-Resources-Helping-Agencies/Visitors-Control-Center/
11.14. Being granted base access does not grant access to the restricted or controlled area.
Restricted or controlled area access is contingent upon base access.
11.15. Contractors needing a temporary or long-term pass for base access will need to present a Real ID compliant drivers license or two (2) forms of identification at the VCC to receive a pass.
Failure to do so may access delays that will not be construed as excusable or government-caused.
Below is a list of approved forms the member may use as a second form of ID:
State-issued Enhanced Driver’s License U.S. passport U.S. passport card DHS trusted traveler cards (Global Entry, NEXUS, SENTRI, FAST) U.S. Department of Defense ID, including IDs issued to dependents Permanent resident card Border crossing card An acceptable photo ID issued by a federally recognized Tribal Nation/Indian Tribe, including Enhanced Tribal Cards (ETCs).
HSPD-12 PIV card Foreign government-issued passport Canadian provincial driver's license or Indian and Northern Affairs Canada card Transportation worker identification credential U.S. Citizenship and Immigration Services Employment Authorization Card (I-766) U.S. Merchant Mariner Credential Veteran Health Identification Card (VHIC)
11.15.1.Individuals holding more than one acceptable credential must use the credential most accurately depicting the capacity in which the individual is acting for the specific visit to the installation. Plainly, contractors shall not use military retiree ID to enter the base if the purpose for entering the base is to perform contract work. Use the pass issued by the VCC.
11.16. Contractors are prohibited from possessing weapons, firearms, and ammunition, on themselves or within their contractor-owned or privately-owned vehicles while on Mountain Home Air Force Base.
11.17. Controlled/Restricted Area Access. Security Forces must receive and authenticate an Entry Authorization List (EAL) prior to any entry into a restricted or controlled area. The Contractor shall submit an EAL information table containing each contractor and subcontractor employee that may be required to perform work in the area to the Government PM for processing to SFS not later than 30 days prior to construction start or otherwise before a valid need for area access. The most current version of the Government template will be provided by the PM. No consideration shall be given to the Contractor for delays or cost increases experienced due to failing to request restricted or controlled access in a timely manner.
11.18. The contractor shall ensure that only the contractor and subcontractor employees listed on the authenticated EAL enter the area. Failure to comply with restricted or controlled area access protocols will result in a security violation and may suspend all or part of the work or result in removal of the unauthorized employee(s) from the base. The duration of required Government actions (e.g.
investigations) following security violations caused by a contractor or subcontractor shall not be construed as excusable delay or unreasonable Government delay.
11.19. Approval to access the base is required before approval to access to a controlled/restricted area. EALs will not be processed that list individuals that do not have approved base access. Being listed on an authenticated EAL does not grant base access.
11.20. Personnel. The Contractor shall employ sufficient management and contract administration resources, including personnel responsible for project management, field superintendence, change order administration, estimating, coordination, inspection, and quality control, to ensure proper execution and timely completion of work. The Contractor shall designate a principal of the firm or other senior management official to provide executive oversight and problem resolution resources to projects for the life of the contract. The Contractor shall employ and require its subcontractors to employ only qualified personnel to perform work required for each project.
11.21. The Government reserves the right to exclude, or remove from the worksite, any personnel for reasons of incompetence, carelessness, or insubordination, who violate rules and regulations concerning conduct on federal property, or whose continued employment on the worksite is otherwise deemed by the Government to be contrary to the public interest.
11.22. Unless expressly authorized by the CO, in the solicitation or otherwise before receipt of offers, combining or ‘dual-hatting’ of roles is not authorized. Therefore, the Contractor shall assume for the purposes of preparing their offer, and execution and timely completion of the project, that separate superintendents, quality control managers, site safety and health officers, and environmental managers are required.
11.23. If ‘dual-hatting’ is expressly authorized by the CO, in the solicitation or otherwise before the receipt of offers, the Contractor shall ensure their designee meets or exceeds the required qualifications of each role for which they are designated.
11.24. Prior to construction, the Contractor shall provide the CO with written designation for each role, proof of qualifications for each designee, and work contact information (desk/mobile phone, email). Repeated failure or excessive delay by the Contractor to meet role and qualification requirements of the contract may be deemed default and result in the Government terminating the Contractor’s right to proceed with the work under the Default Clause.
11.25. Quality Control (QC). The Contractor shall document and resolve all quality control problems and accomplish daily quality control inspections. The Contractor shall establish a method to identify poor performance and specify appropriate corrective action. All work is subject to US Army Corps of Engineers (USACE) Construction Quality Management (CQM) practices.
11.26. Request for Information (RFI) Process.
11.26.1.The term RFI is typically used to request formal clarification or variation of a contract requirement, such as when details are ambiguous or absent from the scope of work, construction drawings and specifications. The Government will only respond to RFIs submitted by the prime contractor, therefore all subcontractor or supplier RFIs shall be reviewed and transmitted to the Government only by the prime contractor. RFIs should include information such as references to the construction documents applicable to the issue, affected definable features of work, problem statement, suggested solution, cost and/or schedule impact, and desired response time. The Government shall be allotted a standard response time of 14 calendar days, unless a shorter period is requested in the RFI for valid time-sensitive issues that will or may impact cost or schedule.
11.27. Site Maintenance. The Contractor shall maintain the project site in a clean, safe and orderly condition. Contractor shall secure all supplies and equipment stored on the TO project site to discourage theft or damage. Protection and security for materials and equipment on site is the sole responsibility of the Contractor. The Contractor may be required to install temporary fencing to protect the site.
11.28. Weather. The Contractor will and will cause its subcontractors to protect carefully all work and materials against damage or injury from weather. If any work or materials have been damaged or injured by reason of the failure on the part of the Contractor or its subcontractors to protect such work and materials, such will be removed and replaced at the expense of the Contractor.
11.29. Base Closure/Entry and Exit: The 366th Fighter Wing Commander may at any time deny or restrict entry or exit from Mountain Home Air Force Base. Typically, these occurrences are in the interest of heightened security conditions and public safety concerns. Contractors and their subcontractors shall anticipate the potential for minor entry or exit delays due to the nature of performing work on a military installation. Contractors shall further anticipate the potential for base closure or delayed reporting of Government personnel due to expected or occurring poor weather conditions. Public notifications of base closures and delayed reporting of Government personnel due to poor weather conditions are available on the Mountain Home Air Force Base Gunfighters Facebook page.
11.30. Delays in Entering or Leaving the Work Area: If the work site is located in a restricted or controlled area, the Contractor may experience delays due to compliance with entrance/exit requirements of the restricted/controlled areas. The Contractor shall not be compensated for reasonable delays in accessing these restricted/controlled areas. The Contractor may also be requested to leave a restricted or controlled area at any time. The Contractor shall not be compensated for reasonable delays due to these security measures. The CO may extend the completion date when there is a change in security designations that limit or diminish Contractor access to a work site after commencement of work. The CO may also extend the completion date to offset undue delays, singular or cumulative, due to contractor compliance with base and site security restrictions.
11.31. Nuclear Density Gauge (NDG). NDGs require authorization to be brought onto the base.
Authorization shall be requested for each gauge via material submittal 30 days prior to a valid need to be brought onto the base. No consideration shall be given to the Contractor for delays or cost increases experienced due to failing to request authorization in a timely manner. The following documentation is required with each submittal:
U.S. Nuclear Regulatory Commission (NRC) Form 241 Leak test certificate Radiation Safety and NDG training certificates Radiation Safety Officer contact information
11.32. Waste. Disposal of any Mountain Home Air Force Base waste at the Idaho Regional Waste Services Simco Road Regional Landfill, now known as Sawtooth Regional Landfill, is prohibited unless otherwise indicated by the CO.
11.33. Dig Permit. Call DiglIne to initiate the dig permit process. Digline will give a confirmation number and confirmation email. Complete an Air Force Form 103 including sections 1-7 and a description of work in section 18. Input the Digline confirmation number in section 14 under Remarks.
Provide a map of the work site requiring locates. Submit the AF 103, map, and Digline confirmation email to 366CE.CSU@us.af.mil for processing, and Cc the PM and CO. Once approved the dig permit will be emailed back.
11.34. It is the responsibility of the contractor to submit, track, and renew dig permits in a timely manner to allow the Government to process and approve prior to any beginning of work requiring digging or extending of work requiring digging. Processing may take up to 15 days. Failure to do so may result in delays that shall not be construed as Government delay or entitle the contractor to any equitable adjustment.
12.0 ACRONYMS
ACCU: Air Conditioning Climate Unit ALC: Automated Logic Controls BACnet: Building Automation Control network DDC: Direct Digital Controls JCI: Johnson Controls International AHU: Air Handling Unit
ASHRAE: American Society of Heating, Refrigerating and Air-Conditioning
11. ATTACHMENTS/ REFERENCES
1. DAF 4394-User Agreement
2. DD FORM 2875-SAAR_Form
3. UFGS 01 57 19-Environmental Protection Plan Change 2
4. UFC 1-200-01 DoD Building Code Change 4
5. UFC 3-400 Mechanical Change 1
6. UFC 3-501-01 Electrical Engineering 2024
7. UFC 3-600-01 Fire Change 6
8. UFC 3-410-02 DDC For HVAC Change 2
9. AF 3000 MATERIAL APPROVAL SUBMITTAL
10. SFS 30 - NEW 2025
NFPA: https://www.nfpa.org/en
ASHRAE: https://www.ashrae.org/technical-resources/standards-and-guidelines/standards-addenda/standard-135-2016-bacnet-a-data-communication-protocol-for-building-automation-and-control-networks https://www.nfpa.org/en https://www.ashrae.org/technical-resources/standards-and-guidelines/standards-addenda/standard-135-2016-bacnet-a-data-communication-protocol-for-building-automation-and-control-networks https://www.ashrae.org/technical-resources/standards-and-guidelines/standards-addenda/standard-135-2016-bacnet-a-data-communication-protocol-for-building-automation-and-control-networks https://www.ashrae.org/technical-resources/standards-and-guidelines/standards-addenda/standard-135-2016-bacnet-a-data-communication-protocol-for-building-automation-and-control-networks
File details come from the government source that posted it. Updated .