SOW AWNING MAYO.pdf

PDF 118 KB Posted

Attached to
USCGC Issac Mayo Awning Replacement Federal contract opportunity
Solicitation number
13912PR260000020
Issued by
Department of Homeland Security US Coast Guard

About this file

Summary

This is a Scope of Work (SOW) for canvas awning replacement and aluminum frame coating work on the Coast Guard Cutter Isaac Mayo. The Contractor is required to renew canvas awnings on the 01 Deck and Fantail, and inspect, clean, and coat the installed aluminum frame. No government-furnished property is provided. The work must be performed during the vessel's scheduled inport period from 27 June to 18 July at USCG Sector Key West, 100 Trumbo Point Road, Key West, Florida 33040, with ENS Genevieve Brewer identified as the point of contact.

The Contractor's specific responsibilities include furnishing and installing all protective coverings to prevent contamination of non-affected vessel components; handling all interferences including GPS/Radio antennas and screen panels per Surface Forces Logistics Center Standard Specification 0000; providing all necessary equipment (ladders, scaffolding, man lifts) for access; removing existing canvas covers and lacing for disposal; conducting visual inspection of awning support structures and mounting hardware with documented discrepancies and repair plans; cleaning all visible corrosion from the aluminum frame using chemical and/or mechanical methods and applying outdoor protectant with current Safety Data Sheets provided; and installing new color-matched canvas, lacing, and mounting hardware with proper tensioning. The work references Coast Guard Drawing 154 WPC-613-201, Revision C, and applicable SFLC Standard Specifications for general requirements, welding processes, and ship structure preservation.

View the file

Other files for this federal contract opportunity

Other files attached to USCGC Issac Mayo Awning Replacement, newest first.
File Type Posted
Issac Mayo SOW.docx DOCX document
15-4543.txt TXT text file
Ship Drawing Canvas 154-WPC_613_201_1_-_C (003).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work

Canvas Awning Replacement Clean, Inspect, and Coat Aluminum Frame

On CGC ISAAC MAYO

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew the canvas awnings on the 01 Deck and the Fantail. In addition, to inspect, clean and coat the installed aluminum frame. This work is to be performed on the Coast Guard Cutter Isaac Mayo during their scheduled inport period.

1.2 Government-furnished property.

None

2. REFERENCES

2.1 Coast Guard Drawings.

Coast Guard Drawing 154 WPC-613-201, Rev C, Rigging & Covers A&D

2.2 Coast Guard Publications.

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

2.3 Other References.

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. None.

3.1.2 Tech Rep. Not applicable

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Any disturbed mounting hardware shall be replaced with new. Known interferences include, but are not limited to the following:

GPS/Radio Antennas

Screen Panels

3.1.5 Ladders, Scaffolding, Man Lift. The contractor shall provide all required equipment for access to the awnings for removal and installation.

3.1.6 Canvas Removal. The contractor shall remove existing canvas covers and lacing and remove from property for disposal.

3.1.7 Awning Frame Inspection. The contractor shall conduct a visual inspection of all awning support structures and mounting hardware. Any discrepancies shall be documented and a proposed repair plan provided via CFR to KO. Any disturbed mounting hardware shall be replaced with new.

3.1.8 Awning Piping Cleaning and Protectant Application. The contractor shall remove all visible corrosion from existing awning frame using chemical and/or mechanical methods and coat the exposed aluminum with an outdoor protectant. Any chemical applied shall have current SDS provided for ships records.

3.1.9 Awning Installation. The contractor shall install new color matched to existing awning, lacing and any required mounting hardware. Canvas shall be tensioned to ensure a tight application.

4. NOTES

4.1 This Scope of Work was generated by:

USCGC ISAAC MAYO

100 Trumbo Pt. Rd.

Key West, FL, 33040

(305) 432-7419

4.2 The following are the U.S. Coast Guard vessels that the work is to be performed on and the availability for installation:

4.2.1

USCGC ISAAC MAYO

100 Trumbo Pt. Rd.

Key West, FL, 33040

(305) 432-7419

Expected installation dates are during the vessel’s inport availability, 27JUN-18JUL.

POC: ENS Genevieve Brewer

Work Location: USCG Sector Key West, 100 Trumbo Pt. Road, Key West, FL 33040.

File details come from the government source that posted it. Updated .