This statement of work outlines requirements for replacing the transmitter in the Airport Surveillance Radar Model 8 (ASR-8) system. Vendors are requested to provide capabilities documentation within 90 days demonstrating a transmitter meeting specifications, including operating between 2700-2900 MHz, 750KW to 1.4 MW peak power, MTBF of 25,000 hours, and monitoring/fault detection capabilities. The documentation should also address dimensions, weight, maintenance requirements, and production timelines. The Federal Aviation Administration requires the capabilities statement and reserves the right to inspect and require changes to submitted documentation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of Transportation Federal Aviation Administration
ASR-8 Transmitter Replacement
Statement of Work
Prepared by Terminal Surveillance Engineering
(AJW-1433)
Date 11/14/2023
Table of Contents
1.0 INTRODUCTION ...................................................... ERROR! BOOKMARK NOT DEFINED.
2.0 SCOPE OF WORK
2.1 OVERVIEW .......................................................................... ERROR! BOOKMARK NOT DEFINED.
2.2 OBJECTIVES ........................................................................ ERROR! BOOKMARK NOT DEFINED.
3.0 SPECIFICATIONS .................................................... ERROR! BOOKMARK NOT DEFINED.
4.0 DESCRIPTION OF TASKS
5.0 DOCUMENTATION DELIVERABLES
5.1 DOCUMENTATION TABLE
5.2 DOCUMENTATION REQUIREMENTS
APPENDIX A - ACRONYMS
1.0 Introduction
The Federal Aviation Administration Airport Surveillance Radar Model 8 (ASR-8) Has been in service since 1975. The system is a dual channel system operating between 2700 and 2900 MHz the transmitters operate through a diplexer allowing both channels to operate in cooperation with each other. The ASR-8 system is deployed to 54 locations around the world.
2.0 Scope of Work
2.1 Overview
The ASR-8 has been in service since 1975 and is starting to become unsupportable due to obsolescence of components. The aging systems are experiencing wiring issues with the length of service they have endured. The FAA has a requirement to replace the transmitter in the ASR-8. The transmitter is a fully self-contained enclosure that accepts incoming low power RF for amplification, and timing control signals to trigger the RF amplification in the transmitter. The incoming low power for amplification is 7.5 W. This is a request for capabilities to meet the specific requirements in section 3 of this announcement. All technologies for transmitter construction are being evaluated.
2.2 Objectives
The objective of this acquisition is:
a. Provide a response outlining the capabilities of a transmitter to meet the requirements of Section 3.
3.0 Specifications
a. -Frequency= 2700-2900 MHz adjustable in minimum of 1 MHz increments
b. -Spectrum= Balanced sidelobes and -40DBm minimum at 7MHz above and below center -frequency. Will accept higher levels up to 10MHz maximum based on performance.
c. -PRF= 800-1300 Hz
d. -Pulse width = 0.6usec (Adjustable range 0.55 minimum to 1.1 maximum)
e. -Output power = 750KW to 1.4 MW peak power or equivalent.
f. -Stability = -60dB or lower
g. -Input power 3phase 208V 70A maximum circuit breaker rating
h. -MTBF of 25,000 Hours
i. -Fault monitoring of the transmitter to allow for ease of troubleshooting.
j. -Monitoring/Display of all critical voltage and current parameters
k. -Ability to use external test equipment for maintenance procedures and operational verification of standard.
l. -LRU replacement should be less than 1 hour per part.
m. -Preventative maintenance procedures to maintain system
n. -WR284 rectangular waveguide connection for output RF
o. -Existing COTS equipment with minor modifications allowed.
p. -Complete data rights for government use and future modifications
4.0 Description of Tasks
1. Develop documentation to describe transmitter that can meet the requirements in Section 3.
This description should include:
a. Dimensions of transmitter
b. Weight
c. Fault monitoring
d. Performance monitoring
e. Preventative Maintenance requirements.
f. Mean Time Between Failure
g. Production timelines
5.0 Documentation Deliverables
5.1 Documentation Table
Contractor must provide the documentation deliverables shown in the following Documentation Table. Contractor must submit each deliverable on or before the due date given in this table. The COR under special circumstances may extend a due date.
Documentation Table
SOW # Deliverable Deliverable Description Due Date
4.0 Capabilities
Documentation
Capabilities of Vendor transmitter to meet requirements of Section 3.0 90 days from release
5.2 Documentation Requirements
FAA has the right to inspect, determine acceptance and require changes prior to final acceptance for all documentation deliverables developed under this contract. FAA actions in this regard will be consistent with SOW requirements, the contract and industry best practice. All documentation deliverables provided by the Contractor become the exclusive property of the FAA and for FAA to use without limits, unless existing intellectual property rights or other parts of this contract supersede that.
Contractor must submit documentation deliverables to the COR. Contractor must use Microsoft Office 2010 applications or Adobe PDF for documentation deliverables developed under this SOW.
Appendix A - Acronyms
AML Federal Aviation Administration Logistics Center CO Contracting Officer (refers only to a FAA position) COR Contracting Officer’s Representative (refers only to a FAA position) ENG Engineer FAA Federal Aviation Administration FAALC Federal Aviation Administration Logistics Center FOB Freight on Board IAW In Accordance With IM Item Manager LMS Logistics Management Specialist MDR Multi-Mode Digital Radio (CAVU-2100) MDR PS CAVU-2100 Power Supplies Rev 1 MMAC Mike Monroney Aeronautical Center NAS National Airspace System NSN National Stock Number OKCET Oklahoma Communications Engineering Team AJW-173 PDF Portable Document Format PPP&M Preservation, Packaging, Packing and Marking PV Provisioner QTY Quantity SOW Statement of Work TDR Technical Data for Requirements US United States
| Date 11/14/2023 |
| Table of Contents |
| 1.0 Introduction |
| 2.0 Scope of Work |
| 2.1 Overview |
| 2.2 Objectives |
| 3.0 Specifications |
| 4.0 Description of Tasks |
| 5.0 Documentation Deliverables |
| 5.1 Documentation Table |
| 5.2 Documentation Requirements |
| Documentation Table |
| Due Date |
| Deliverable Description |
| Deliverable |
| Appendix A - Acronyms |