SOW Araz-Winterhaven Gate and Erosion Control (Ver. 1.0).pdf

PDF 322 KB Posted

Attached to
SEEKING SOURCES FOR INSTALLATION OF NEW GATE AND EROSION CONTROL FOR TACTICAL COMMUNICATIONS TOWER (TACCOM) NEAR ARAZ-WINTERGATE, AZ
Solicitation number
AC-22-01323
Issued by

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION STATEMENT OF WORK

For

Araz-Winterhaven Gate and Erosion Control

1.0 Scope of Work

The purpose of this statement of work includes the installation of a gate and erosion control at the Tactical Communications (TACCOM) tower in Araz-Winterhaven (Latitude 32.7476, Longitude -114.7050). The proposed installation would incorporate a 16-foot drive gate in the north fence line and erosion control along the north, east and south fence lines. The gate installation will require the removal of a section of the existing chain-link fence and installing two posts and a hinged, 2-part 16-foot drive gate that swings inward to the compound. The erosion control would require the leveling of the eroded topography along the afore mentioned fence lines and installing erosion fabric, and 4-6 inch rock. A water diversion channel will also be installed to divert water runoff diagonally in a southeastern direction from the north fence line to the south fence line. The contractor must prepare a construction plan that shows the proposed site layout and any recommendations based upon information gathered to install the gate and erosion control at the site. A sketch of the proposed construction plan is provided in Appendix D of this document.

The contractor will provide labor, travel, permits/application fees, mobilization costs and tools for technicians to travel to Araz-Winterhaven (Latitude 32.7476, Longitude -114.7050) to install a 16-foot drive gate and erosion control along with any other incidentals as noted in this statement of work. Locations and site-specific information can be referenced from the construction drawings and sections below. The government will furnish no materials and all materials are to be procured by the contractor for installation. Upon successful installation of all proposed tasks, the contractor will be responsible for restoring the site to a natural state. All work items denoted in Section 3.0 may require additional effort to complete work items as described. Work items such as additional site investigations or additional site work, which are not listed herein but are expected to complete the work, must be identified in the contractor’s work plan.

1.1 Objectives

This SOW shall achieve the following specific objectives:

Complete all activities as outlined in this statement of work.

Complete installation of new 16-foot drive gate.

Complete installation of erosion control along fence lines.

Complete installation of water diversion channel

Ensure proper fence installation after gate installation

Ensure the Earth Electrode System (EES) is properly installed in accordance with FAA-STD-019f after gate installation

Complete project close-out

1.2 References

All applicable documents referenced in this SOW are listed below.

Government Furnished Information

Applicable Federal, State, and Local Requirements.

Applicable Standard Industry Quality and Safety Requirements

DHS-CBP Design Guides

TIA/EIA-222H

FAA STD-019f

ASCE 7 (current revision)

International Building Code (IBC)

National Electric Code (NEC)

National Fire Protection Association (NFPA)

ANSI/ASTM

AWS D1.1

American Concrete Society

American Institute of Steel Construction

Occupational Safety and Health Administration (OSHA)

2.0 Requirements

Contractor will:

Provide all necessary labor (or sub-contract labor) of appropriate skill to accomplish all tasks with this

SOW

Submit Project Completion Report as Described in Section 3.0

Travel as necessary to accomplish all tasks in the SOW.

Provide specialized services to accomplish all tasks specified in the SOW.

Provide procurement services as required for materials and equipment.

Must submit and clear a law enforcement clearance through the local CBP sector office for all personnel including sub-contractor personnel, see Appendix C for the required form.

Complete all tasks as required in Section 3.0

Provide deliverables as required in Section 3.1

Schedule and coordinate as required by Section 4.0

Provide progress/compliance as required in section 4.0.

Provide information and service in conformance with requirements in Appendix A

Government will:

Provide necessary funding for the successful accomplishment of this service order agreement.

Identify known constraints and/or limitations associated with the accomplishment of tasks identified with this service order agreement.

Provide all necessary design documents, manuals and other guidance that govern the submission and quality of tasks identified with this service order agreement.

Provide all project development documents, as developed in environmental, planning and reality processes, that identify project commitments or constraints that must be met by project scope

3.0 Tasks

The tasks to be performed under this SOW are described below in several categories:

Phase I: Planning and Coordination o Work Plan Submission/Approval o Kickoff Meeting.

o Contractor Work Plan, Weekly Progress Meeting and other Items of Appendix A o Contractor will be required to submit site access form with PPI prior to work completion and for site access approval.

Phase II: Construction o Contractor will install gate and erosion control as outlined in this statement of work

Phase III: Project Completion Report o Contractor will produce a close out report to support project acceptance.

3.1 End Results/Deliverables

The deliverables to be completed and submitted under this statement of work are to install a new gate and erosion control at Araz-Winterhaven.

3.2 List of Deliverables by Task

The deliverables to be completed and submitted for each task under this SOW are described below. Acceptance of the work will be based on conformance with construction plan and other government furnished information provided by FAALC/AJW-L500.

1) Project Work Plan

2) Install 16-foot gate

3) Install erosion control along fence line

4) Install water diversion channel

5) Project Closeout Report

4.0 Schedules/Milestones

Project scheduling and milestones for the site will be submitted within 5 days of award and include no less than the following milestones:

Security Clearance

Work Plan and Work Schedule

Stakeholder Approval (Property owner, CBP, and/or FAA)

Pre-work Meeting, (via telecon)

Mobilization

Construction

Final Inspection and Acceptance

Demobilization

Project Close-Out

5.0 Other Considerations

All personnel shall be required to submit and clear a law enforcement clearance through the local CBP sector office.

Before and after photos of all tasks scheduled for completion will be submitted within 5 days of completing the activity- not at the end of the project.

6.0 Progress/Compliance

The following will be coordinated with FAA/AML-L500 in order to monitor progress and ensure compliance (identify action):

Pre-work Meeting (via telecon)

Final Inspection and Acceptance

Submission Documents in Sections 3.2 & 4.0

7.0 Period of performance

After the notice to proceed is issued, the contractor should be prepared to complete the project through close out within 6-months. Prior to construction, it will be required to perform a construction kick-off meeting 14- days prior to construction, and mobilization. Submission of personnel site access forms will be required NLT 21-days prior to construction mobilization. Mobilization will not be scheduled until a Construction Work Plan has been submitted and approved. From mobilization, onsite work should be completed within 60 calendar days. Final inspection to be completed within 7-calendar day window for work completion. Punch list items must be completed with 30-calendar days of final inspection unless otherwise approved and all construction closeout documentation must be submitted within 60 calendar days of final inspection for initial review by the government. Construction close out documentation will not be accepted until all punch list items have been completed and reflected in construction closeout documentation as necessary. All necessary work activities and schedule adjustments that may extend the total duration of the project are the responsibility of the contractor to identify in advance of project implementation. This doesn’t preclude extensions for unforeseen conditions and circumstances, differing site conditions or other bona fide reasons that require active management to unnecessarily extend period of performance.

8.0 Place of performance

The place of performance is Araz-Winterhaven (Latitude 32.7476, Longitude -114.7050) This site has controlled access and requires onsite escort, which will be provided by the Government.

Appendix A – Construction Requirements

CONTRACTOR SITE VISIT

When required by the Contractor to adequately prepare a Work Plan or as identified in the Scope of Work Requirements, the project location identified in the scope of work will be visited to perform a site survey. The site survey shall provide the basis of the Contractor’s Work Plan and no formal site survey report submission shall be necessary when the site survey is conducted to produce a Work Plan.

CONTRACTOR WORK PLAN

The Contractor shall be required to produce a Work Plan and the Work Plan will follow the guidance provided below. When the requirement for a site visit is waived by the Contractor in order to develop a Work Plan, the Work Plan will include no less than a summary of work to be completed (with limitations, exclusion and assumptions) and schedule to complete the work. Work Plan will also include the following items (unless waived or documentation provided with base contract). List of Quality Control Activities, Definable Features of Work, Materials, Verification and Testing Activities, Submittal Register, Non-compliance/Deficiency Process, Change Management Process, Construction Reporting and Inspection, Construction Tolerances, Workmanship and Warranty Requirements. Each of these items will be defined as described below:

FEATURES OF WORK: Include a list of defined features of work (DFOW) with descriptions of work requiring any preparatory inspections and descriptions of the verification, inspection, testing, acceptance, and quality control requirements for each element of work to be reviewed (such as photographs, measurements, and tests).

MATERIALS: All equipment and materials to be incorporated into the design and construction drawings are to be identified and appropriate documentation to be provided to government to assure the proper materials are being utilized and will not affect the service, capacity or operation of the constructed tactical infrastructure. The equipment and materials incorporated into require a certification. Certifications will be provide as one of the following types of certifications:

Type A: Manufacturer prepared certification consisting of a certified report detailing tests conducted by a laboratory certified on samples obtained from the lot of material in shipment.

Type B: Manufacturer prepared certification showing the limits of test values as determined by a laboratory certified, qualified commercial laboratory or another approved laboratory.

Type C: Manufacturer certification certifying that the material in the shipment conforms to the same formula or is essentially the same as the material previously approved for construction.

Type D: Manufacturers prepared certification stating that the material meets the contract requirements, listed by specification reference number, section reference or other appropriate identification approved by the Resident Engineer/Government Inspector.

Type E: Fabricator prepared certification covering a composite item incorporating two or more materials previously approved on an individual basis, but that lose their identities when incorporated into the composite item.

Type F: Resident Engineer’s acceptance based on confirmation that supplier delivery invoices materially matches contract required materials, all contract requirements have been met and visual inspection at the point of incorporation shows satisfactory workmanship and condition of the material.

Type F Certifications will not be accepted for equipment or materials specified in the design and construction drawings where the source or supplier of the equipment is known in advance of construction. When equipment or materials are specified by brand and model name the equipment or material or equal must provide a Type A

– Type E Certification as a part of the final design submission package. All other materials where the source, supplier or model and brand name are unknown until the date of delivery by the contractor a Type A – Type F Certification may be accepted. All equipment and/or material certifications collected after the beginning of construction will be supplied with the as-built submission package.

Certifications will be required for all equipment and materials incorporated into the design and construction of the project. Material certifications will not be required for any of the following reasons;

Equipment and/or Material provided as Government Furnished Equipment or Materials

Equipment and/or Material salvaged or produced from local sources adjacent to project permanent and/or temporary easements. This does not alleviate necessary documentation to validate material meets sampling and testing requirements.

Equipment and/or Material is on approved State Department of Transportation (SDOT) Material List.

Materials meeting this condition must still be documented as approved SDOT Material and furnished to the Resident Engineer during construction.

HEALTH AND SAFETY PLAN: The HSP will identify the local emergency services and provide a local emergency preparedness plan. The HSP shall conform to the requirement of the United Facilities Guide Specifications, division 01, Section 01 35 26 (Government Safety Requirements), Parts 1.7 and 1.8.

Government will not be held responsible for wellbeing of Contractor Personnel. The Contractor shall conform to all applicable safety standards published in the Federal Register, OSHA or applicable life safety code. The Contractor shall ensure employees observe all safety, security, traffic control, and fire prevention requirements in effect at the site. Government safety personnel may observe Contractor operations/processes at any time on Government premises. Imminent danger situations shall be corrected on the spot; other safety issues shall be processed through the COR/TOPOC. The HSP shall be specific to the project site and identify emergency contact information, communication and reporting procedures.

QUALITY CONTROL ACTIVITIES: Include a description of the quality control activities that will be performed (e.g., the steps that will be taken to successfully review the specific elements of the construction, including visual inspection (periodic or continuous), measurement, frequency and other checks designed to verify compliance with stated requirements) to include Contractor acceptance of the construction elements such as construction tolerances and other criteria used to approve craftsmanship and work.

QUALITY CONTROL PLAN: Include how the Contractor plans to develop and maintain quality, timely and efficient operations. QCP should include a description of the inspection and monitoring of services provided with the process for identifying, reporting and preventing/correcting nonconformities. When material, equipment, or components are unacceptable to the Government, the Contractor shall, at no cost to the Government, remove, replace, and rework material, equipment, and components so that compliance with the Government's requirements are satisfied.

VERIFICATION & TESTING ACTIVITIES: Identify the verification and testing laboratory facilities, qualifications and procedural requirements that complement the quality control activities and definable features of work.

Include in project schedule milestones for verification and testing. All verification and testing should be with the project close out package and include conducted, by whom, the standard to which it is verified / tested, and the documentation to provide evidence of verification / test results.

SUBCONTRACTOR MANAGEMENT PLAN: Identify the list of subcontractor(s)’s employees employed in the execution of the contract, services performed, certifications, licenses, qualifications, and experience. The Contractor shall describe in detail how the subcontractors will be managed to ensure quality, timely performance of contract requirements.

SUBMITTAL REGISTER: Include a submittal register for all anticipated materials certifications, verification/testing/acceptance logs, shop/fabrication drawings, cut sheets, manufacturer installation instructions, and other reports, as necessary, to include when submittals are due to the Government.

NON-COMPLIANCE / DEFICIENCY PROCESS: Describe the non-conformance management and resolution process and how non-conformities are resolved when identified.

CHANGE MANAGEMENT PROCESS: Describe the process for addressing and proposing changes to awarded documentation.

WARRANTIES: Describe the warranty of all craftsmanship and materials incorporated into Customer Assets and/or Facilities.

WEEKLY PROGESS MEETINGS

The Contract Manager shall be required to meet weekly during the implementation of Contractor Work Plans unless waived. Meetings may be held onsite or via a teleconference with government representatives.

HOURS OF OPERATION

Government core duty hours are Monday through Friday, 0600 to 1800. Some emergency situations may require the Contractor to work outside core duty hours. These situations include, but are not limited to, disruption of services, e.g., unscheduled/scheduled outages of facility services, or contingency accidents/incidents, or other emergencies. Late or nighttime work hours may be permitted to avoid the high summer temperatures.

FAA personnel observe the following days as holidays:

New Year's Day, Martin Luther King's Birthday Presidents' Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day.

Any other day designated by Federal statute, by Executive Order or by the President's proclamation or as identified on scope of work.

When any such day falls on a Saturday, the preceding Friday is observed. When any such day falls on a Sunday, the following Monday is observed. Observance of such days by Government personnel shall not be cause for an extension to the delivery schedule or period of performance or adjustment to the price, except as set forth in the contract. Except for designated around-the-clock or emergency operations, Contractor personnel will not be able to perform on site under this contract with FAA on holidays set forth above unless identified on the scope of work or Work Plan. Extreme weather conditions, other emergency situations, and other acts of nature (e.g. floods, earthquake) may warrant an office closure or a delay in normal operating hours.

WORK COORDINATION

The Contractor shall coordinate with the government manager’s or building manager’s office to ensure the work to be performed does not disrupt customer operations. A twenty-one (21) calendar day notice to the government and facility personnel is required for all work that require site access, service interruption, disconnects or cut-off of any utility to or within the facility, or requires the facility to be vacated. This is not intended to include outrages associated with the communication cutover plan. Notices will be identified with the submission of Site Access Forms. Site Access Forms are required to properly conduct a background check. All Contractor Personnel who fail background investigation will be denied access and the cost and impacts associated will be borne by the Contractor. All contractor personnel will be required to provide name, title, company, home address, last four of social security number, date of birth, driver’s license number and state driver’s license is issued. All information will be used to perform at a minimum a criminal records search at local, state and federal levels.

ELETRONIC DATA REQUIREMENTS

The Contractor shall provide all submittals and requested data in electronic format, except when requested in hardcopy by the government. The data and information obtained through the execution of the contract is hereby owned solely by U.S. Government. FAA shall have unlimited and unrestricted use of such data. The associated rights and privileges are assignable only by FAA. The Contractor shall maintain all records and submittals generated electronically for 2 years and hard copy for the remaining duration of the contract..

The Contractor shall provide document source files in Microsoft Office Professional formats; provide each document in Portable Document Format (PDF) which is book-marked and fully text retrievable; and provide a cover sheet containing key cataloging formation and a table of contents.

Appendix B – Environmental Monitor and Business Permit

Cultural Resource Monitoring Services:

To assure the protection of traditional cultural resources, the Tribe requests that its cultural resource monitor be present for all ground-disturbing activity on the site, and that the Tribe be reimbursed for the cost of providing its monitor. I understand that this project involves ground disturbing excavation for geotechnical testing to inform design and during construction for the tower and shelter foundations at the Araz Tower site on the Reservation.

You stated that the geotechnical work would likely occur on 09/23/2019 and with a duration of one day. Please also share with me any other plans or details regarding the proposed testing site(s).

When providing a requestor with cultural resource monitoring services, the Tribe generally assesses a Cultural Resource Monitoring Fee of $200/4-hour block. I rely upon the project designer or contractor, based upon its experience and familiarity with the project, to consider the duration of all ground disturbing activities likely to occur during the project and to provide me with an estimate of how many 4-hour blocks will be needed to monitor such activities. For example, if you anticipate that eight hours of ground disturbing activity will occur on a particular day, the cost would be $400 per 8-hour day, reflecting two 4-hour blocks at $200 for each block. On the other hand, if you request a monitor and the monitor arrives as scheduled, but there is little or no work, your firm will be charged an entire 4-hour block. Similarly, if you request a monitor and the monitor works ten hours, your firm will be charged for three 4-hour blocks. The purpose of the 4-hour block is to encourage service requestors to efficiently manage the project schedule to increase the likelihood that the monitor when called will have four hours of work to do.

Based upon your statement that the survey and geotechnical work will likely occur on a single day, I suppose that one 4-hour block of monitoring time will be sufficient. Otherwise, please provide me with an estimate of the time needed to complete the ground-disturbing portion of the geotechnical work. Once we agree on an estimate of the duration of ground-disturbing activity, I will provide you with an invoice for the Cultural Resource Monitoring Fee, with the fee to be paid in advance of the work.

As for scheduling the cultural monitoring, your firm will need to work closely and effectively with me and the cultural monitor to schedule and manage the monitor’s time. On days in which ground disturbing activities will occur, you or your designee will need to so inform me not less than 24 hours in advance so that I can ensure that a monitor is available to perform the work. I will track the monitoring fees, with each day’s work deducted from the initial balance of monitoring time. Once I confirm which monitor will be assigned to the project, I will share his/her contact information with you or your designee.

Given the Tribe’s reliance upon the requestor to estimate the monitoring time, based upon its experience and familiarity with the project, the Tribe typically does not refund fees. If a requestor makes a good faith estimate and timely pays the Tribe’s invoice in advance of the work, but the estimate turns out to be several hours short such that the requestor needs some additional monitoring time to complete the project, I’m willing to provide such additional monitoring time and would bill the requestor without requiring advance payment. Please contact me with any questions at (760) 572-5270 or b.golding@quechantribe.com.

Business Permits:

Any person, firm, or organization that desires to engage in business activity within the exterior boundaries of the Fort Yuma Indian Reservation must first obtain a Business Permit from the EDA. The Business Permit requirement applies to subcontractors, vendors, and service providers---such as land surveyors and geotechnical testing firms---working on a project and whose business activities occur on the Reservation. We encourage you to do business with persons, firms, or organizations already possessing Tribal Business Permits, and upon request, we will provide you a list of permitted companies in business categories matching your needs. The Business Permit Fee varies depending upon the type of business activity. I believe that the Permit Fee for the provision of architectural and engineering (A/E) design services is $150.00 for a twelve-month period that typically runs from the date of application. I also note that the Permit Fee for herbicide/pesticide application is $200.00 per year. I further note that construction services and services pertaining to each of the related trades (electrical, HVAC, plumbing, etc.) would involve a Permit Fee of $500.00 per year. Please find attached a *.pdf of the Business Permit Application. Please have the A/E firm complete it and return it to the EDA along with a copy of the current driver’s license or state issued I.D. for the firm’s project manager who will be on-site, and fee payment of $150.00 in a check or money order made payable to Quechan Indian Tribe. Please contact me or Brandi Mattias, EDA Assistant Planner, at (760) 572-5270 or edaasstplanner@quechantribe.com with any questions.

mailto:b.golding@quechantribe.com mailto:edaasstplanner@quechantribe.com

Tribal Employment Rights Fees and Compliance Plan:

For construction contracts valued at $100,000.00 or higher, the Tribe assesses a fee of two percent (2%) of the contract value. For contracts involving work within and outside the Fort Yuma Indian Reservation, the fee is based on the contract value attributable to work within the Reservation. Also, to ensure that Tribal members are afforded opportunities to be employed, all employers must file with the Tribal Employment Rights Office (TERO) a Compliance Plan. Please contact Robyn Waco, TERO Officer, at (760) 572-0123 or teroofficer@quechantribe.com for more details.

Water for Dust Control, Compaction:

For details regarding accessing water from the Tribe’s water system in support of construction activities such as dust control and compaction, please contact Jeremy Douglas, Public Works Director, at (760) 572-0667 or publicworksdirector@quechantribe.com

Appendix C – Security Clearance Form

All contractor and sub-contractor personnel must undergo a CBP background check. All personnel entering in or working on Federal Property will be screened and checked for criminal history and proper immigration status.

Personnel who do not meet the minimum standards will not be allowed on the job site. The following items determine whether or not a person has met the minimum standards as it relates to the criminal history requirement:

. Any felony conviction (at any time) . Immigration violation (unless exonerated by a judge) . Active warrant (anywhere)

Be advised that if an individual does not clear vetting, CBP cannot disclose (for privacy reasons) why they failed.

mailto:teroofficer@quechantribe.com mailto:publicworksdirector@quechantribe.com

Date:

MEMORANDUM FOR: Office of Internal Affairs

Security Management Division

FROM (CBP federal employee): Name

Office

Room, Phone Number

SUBJECT: Contract Worker Pre-Clearance Request

Floor and room location where visit will take place Floor Room #

Name of visitor escort (must be DHS/CBP employee) Name

Telephone number of visitor escort Office Mobile

Date(s) and Time of visit

From Date

Time

To Date

Time

Contractor Name & Home Address U.S.

(Last name, first name, middle name) DOB POB Citizen (List in alphabetical order by last name) SSN (MM-DD-YYYY) (City, State) (Y / N)

SUBMISSION: The Office of Internal Affairs requires a mandatory submission of 72 hours prior to arrival of visitor(s) in order for any visitor to be considered for approval. Email request to SMDSECURITYSERVICESBRANCH@dhs.gov or fax to Internal Affairs, ATTN: Security Management Division at 202-344-1075.

NOTICE: All visitors must present a U.S. Government issued Photo Identification Card.

All visitors must check in at the 14TH Street Security Desk upon arrival and check out at the desk upon departure.

Visitor escorts are responsible for constant escort of headquarters visitors. The designated escort must accompany visitors at all times, to include returning visitors back to the front desk upon departure. Any visitors found in U.S. Customs and Border Protection space without an escort will be immediately reported to security.

PRIVACY ACT NOTICE: This information is provided to PL 93-579 (Privacy Act of 1974). The purpose of this document is provide information necessary for a minimum security check prior to limited authorized access to U.S. Customs and Border Protection facility. Failure to provide this information may result in denial of access.

Revised 12/7/2021

U. S. Customs and Border Protection Headquarters

Contract Worker Pre-Clearance Request

Appendix D – Supporting Documents

File details come from the government source that posted it. Updated .