This Procedure 5 Work Plan outlines the scope of work for an asbestos abatement project. The federal contractor will remove approximately 2,500 square feet of asbestos-containing cementitious pipes and contaminated soil located at an illegal dump site in Thermal, California. Notifications will be provided to the South Coast Air Quality Management District and OSHA ten days prior to commencement of removal work. The contractor will establish decontamination areas, properly dispose of asbestos-containing materials, and conduct personal air monitoring during abatement activities in accordance with Cal/OSHA regulations. Upon completion, a final visual inspection will be performed to ensure the work area is free of debris and suitable for redevelopment.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROCEDURE 5

WORK PLAN FOR ABATEMENT WORK

COACHELLA VALLEY SITE #2

NEC AIRPORT BOULEVARD & BUCHANAN STREET

THERMAL, CALIFORNIA 92274

PREPARED FOR:

C&C CONTRACTING

25 STANFORD PLACE

MONTCLAIR, NEW JERSEY 07042

PREPARED BY:

ATC GROUP SERVICES LLC DBA ATLAS TECHNICAL

1180 DURFEE AVENUE, SUITE 125

SOUTH EL MONTE, CALIFORNIA 91733

ATLAS PROJECT NO. 1011601991

DATE OF ISSUE: JULY 21, 2021

Max Quezada Stephen Drengson Certified Asbestos Consultant No. 14-5205 Certified Asbestos Consultant No. 06-3975

PROCEDURE 5 – ASBESTOS ABATEMENT WORK PLAN

COACHELLA VALLEY SITE #2

ATLAS Project No. 1011601991 Page | 1

ABATEMENT WORK PLAN

PART 1 – SCOPE OF WORK

1.1 INFORMATION / OBSERVATIONS

A. This work plan is being prepared per the requirements of South Coast Air Quality Management District (SCAQMD).

B. Impacted Area – NEC Airport Boulevard & Buchanan Street, Thermal, California

ATC Group Services LLC dba Atlas Technical (Atlas) was retained by C&C Contracting to review and utilize an asbestos inspection report prepared by Masters Environmental for the debris piles found on the lot located at the Northeastern corner (NEC) of Airport Boulevard and Buchanan Street in Thermal, California. The scope of the project was to create a SCAQMD Procedure 5 Work Plan to properly remove the illegally dumped asbestos-containing cementitious pipes. This work was authorized by C&C Contracting on July 19, 2021. The asbestos inspection report was conducted by Masters Environmental in general accordance with all Federal, State and local guidelines, dated and provided to the Client on July 15, 2021.

During the inspection activities, Masters Environmental observed three types of pipe and collected nine samples. Six of the nine samples were positive for asbestos and most of the pipe was observed damaged and therefore friable.

Masters Environmental further stated that almost everything in the pile contains 35% Chrysotile and Crocidolite asbestos that come in assorted widths, lengths and densities. The asbestos inspection report is attached to this work plan.

The following is the scope of work to cleanup and remove the identified asbestos-containing friable cementitious pipe, and any debris on soil:

1.2 DESCRIPTION OF WORK

A. The work will include the following:

1. The Asbestos Abatement Contractor (Abatement Contractor) shall post appropriate signs and barrier tape to demarcate the area to keep others out of the work area.

2. The Abatement Contractor shall use wet methods.

3. All asbestos-contaminated debris shall be double-bagged or double wrapped in transparent, leak-tight bags and/or poly with appropriate labels, then placed in the asbestos waste bin.

ATLAS Project No. 1011601991 Page | 2

4. The Abatement Contractor shall clean up, remove, and dispose of as friable the asbestos-containing cementitious pipe identified as a 2,500 square feet area.

5. The ACM debris observed on the property appears to contaminate approximately 2,500 square feet of the soil under the cementitious pipe. The debris should all be able to be removed by hand and only impact the top layer of soil.

B. Personal air monitoring shall be conducted during the work area as required by

Title 8 of the California Code of Regulations (Cal/OSHA).

C. Work included: Abatement Contractor shall furnish all labor, materials, services, permits, insurance (specifically covering the handling and transportation of the asbestos-containing waste material), and equipment which is specified, shown, or reasonably implied for the abatement activities.

D. Abatement Contractor must ensure that all equipment is properly secured before leaving the site at night (note that lots of trespassing/dumping activities have been observed on this site).

1.3 OBSERVATIONS

A. A final visual inspection will be conducted after the completion of the abatement work by the owner’s representative.

PART 2 – GENERAL

2.1 DESCRIPTON

A. Work included: Abatement Contractor shall furnish all labor, materials, services, permits, insurance (specifically covering the handling and transportation of ACM and asbestos-containing waste material), and equipment which is specified, show or reasonably implied for the abatement activities.

B. Applicable regulations: Abatement Contractor shall comply with all applicable

Federal, State and local regulations governing asbestos work, especially:

1. South Coast Air Quality Management District (SCAQMD ), Rule 1403

2. California Code of Regulations (CCR), Title 8, Section 1529, Asbestos

3. Code of Federal Regulations (CFR), Title 29, Part 1926.1101, Asbestos

2.2 SUBMITTALS AND NOTIFICATIONS

A. All Submittals and copies of all notifications and correspondence shall be submitted to C&C Contracting and/or the Owner’s representative.

ATLAS Project No. 1011601991 Page | 3

B. Personnel Training: Prior to beginning work, the Abatement Contractor will provide a photocopy of training certificates for each employee from their respective California Department of Occupational Safety and Health (DOSH) accredited training provider or organization.

C. Respirators: Submit manufacturer's certification that the respirators to be used for this project comply with government agency requirements. Abatement Contractor's certifications for each employee must clearly state that each employee has been fit tested and properly trained for the respirator they will be wearing.

D. Medical Examinations: Submit proof that all personnel providing labor and/or professional services who will be entering contaminated areas have had current medical examinations.

E. Permits: Submit proof satisfactory to the Owner's Representative that all required permits have been obtained.

F. Equipment Certification: Submit certification that vacuums, negative air pressure equipment filters, and other local exhaust ventilation equipment are properly permitted form SCAQMD, if required, and conform to ANSI Z9.2-1979.

G. Notifications: Contact the required government agencies electronically 10 working days prior to Project commencement:

1. South Coast Air Quality Management District 21865 E. Copley Drive Diamond Bar, CA 91765

2. Occupational Safety and Health Administration:

Cal OSHA Local District Office

H. Provide copy of Abatement Contractor's License and Asbestos Certification from the Contractor Licensing Board, and copy of registration with the Division of Occupational Safety and Health in accordance with California Labor Code, Section 6501.

ATLAS Project No. 1011601991 Page | 4

PART 3 – EXECUTION

3.1 WORK AREA PREPARATION

A. Preparation Procedures for Removal of the identified ACM piles:

1. The asbestos abatement activities of ACM, asbestos-containing waste and debris shall be executed using wet methods, as described in SCAQMD, Rule 1403, Procedure 3. Double bag or “burrito” wrap (2-layers) removed materials for disposal (if possible).

2. Abatement Contractor shall demarcate the Work area for the duration of the known asbestos materials removal to keep other non-trained and non-protected personnel out of the work area.

3. Abatement Contractor shall establish a 3-stage decontamination unit at the perimeter of the demarcated area since the material abated was observed damaged and is considered friable by the SCAQMD.

4. Provide temporary power and lighting when necessary, and ensure safe installation of temporary sources and equipment per applicable electrical code requirements, including appropriate ground-fault protection. Abatement Contractor shall take all precautions necessary, including inspections and testing, to insure the safety of his employees and other project personnel from electrical hazards during the course of the Project.

5. Provide and maintain appropriate "ABC" type fire extinguishers in the work areas. The size and number of extinguishers shall be as required by local fire officials, but shall not be less than one (1) fire extinguisher inside and outside each work Area.

6. The Abatement Contractor shall not commence with the asbestos abatement work until all preparation requirements have been completed; all tools, equipment, and materials are on hand; all required submittals, notices and permits have been approved.

3.2 ASBESTOS REMOVAL

A. Before removal, ACM and asbestos-containing waste and debris shall be sprayed with Amended Water. Spray materials repeatedly during the work process to maintain a wet condition. All vacuuming shall use approved HEPA vacuums.

Equipment shall have the necessary SCAQMD permits. All affected areas are to be kept adequately wet during asbestos abatement and cleanup activities.

B. Remove ACM using wet methods and in a manner that will not create dust and debris or leave visible residue. Place asbestos containing wastes and asbestos contaminated building contents into properly labeled double six (6) mil bags or “burrito” wrap in a minimum of two (2) layers of six (6) mil plastic and place in

ATLAS Project No. 1011601991 Page | 5 properly labeled and lockable containers lined with two (2) layers of six (6) mil plastic, or in accordance with the disposal facilities requirements.

C. The work areas shall be kept orderly, clean and clear of work materials, polyethylene sheeting, tape, cleaning material, PPE and all other disposable materials or items used in the work areas shall be packed into properly labeled protective packaging and removed from the work areas.

D. Powered equipment can be used to move properly burrito-wrapped asbestos-containing materials that are too heavy for humans to move unassisted, but the abatement (cutting, wrapping, etc.) must be done by hand first.

E. Protective packages containing ACM and asbestos-containing and asbestos-contaminated waste and debris shall be cleaned and placed in the Asbestos Waste Dumpster until hauled to the Asbestos Waste Disposal Facility for disposal.

3.3 DECONTAMINATION PROCEDURES

A. Decontaminated procedures for Contained Work Area:

1. Remove all visible accumulations of ACM, asbestos-containing and asbestos-contaminated waste and debris from both the pile and the top layer of soil beneath the pile. HEPA-vacuum and/or wet-clean all surfaces within the Work Area to remove asbestos residue and dust.

2. After cleaning, the Abatement Contractor shall perform a complete visual inspection of the work areas to ensure that the work areas are free of any visible debris or residue including the top layer of soil under the debris pile.

3. Upon completion of their visual inspection, the Abatement Contractor shall notify the Owner and/or Owners Representative in advance that the work area is ready for Initial Review.

4. Worker decontamination procedures must be carried out whenever a person leaves the asbestos demarcated area, or when removal work is finished.

Workers shall remove gross debris from protective clothing using wet methods and/or a HEPA filtered vacuum, remove the disposable suits, and place them into a labeled, two layered, 6-mil poly bag. The worker shall thoroughly wash hands, respirator, and face with clean water at the designated wash station (inside 3-stage decontamination unit) prior to leaving the demarcated area.

This procedure is known as ‘personal decontamination’.

3.4 ASBESTOS DISPOSAL

A. Asbestos-Containing Waste Materials and asbestos-contaminated waste and debris shall be packed into approved and labeled protective packaging. All waste shall be properly labeled and disposed of in two layers of 6-mil transparent poly bags or wrapped with two layers of 6-mil transparent poly sheets.

ATLAS Project No. 1011601991 Page | 6

B. Abatement Contractor shall deliver asbestos-containing waste materials to the pre-designated Asbestos Waste Disposal Facility in accordance with the guidelines of the EPA.

C. At the conclusion of Work, the Abatement Contractor shall provide evidence (such as a "Bill of Lading", "Hazardous Waste Manifest", or “non-Hazardous Waste Manifest”) that the Asbestos-Containing Waste Material was disposed of at the approved EPA Hazardous Waste Disposal Facility. The evidence shall be submitted with the final request for payment, The Abatement Contractor shall indicate the weight, in tons, of the Hazardous Asbestos-Containing Waste Material generated from the Project.

D. The Abatement Contractor shall be responsible for the safe handling and transportation of all Waste generated by the Project of this Contract, to the designated Waste Disposal Facility. The Abatement Contractor shall bear all costs for all claims, damages, losses, and clean up expenses against the Owner or Atlas, including but not limited to attorney's fees rising out of, or resulting from, Asbestos spills on the site or spills en route to the Waste Disposal Facility.

3.5 AIR MONITORING AND TESTING

A. Air Visual Monitoring

1. A final visual inspection of the work area will be conducted once all identified

ACM have been completely abated.

B. Air Monitoring

1. The Abatement Contractor will be required to conduct personal air monitoring during the work as required by Title 8 of the California Code of Regulations (Cal/OSHA).

END OF WORK PLAN

Work Plan for Abatement Work Coachella Valley Site #2 – Cementitious Pipes

NEC Airport Boulevard & Buchanan Street Thermal, California 92274

PROJECT NO. 1011601991

Photograph No. 1: Asbestos-containing cementitious pipes – close-up.

Photograph No. 2: Asbestos-containing cementitious pipes.

Work Plan for Abatement Work Coachella Valley Site #2 – Cementitious Pipes

NEC Airport Boulevard & Buchanan Street Thermal, California 92274

PROJECT NO. 1011601991

Photograph No. 3: Asbestos-containing cementitious pipes

D

C

B lo

A

�5 oB 5-'I

Site 1 Approx.

Illegal Dump Site Cleanup Area. i�.

New Security Pipe Gate (See Drawing 1163-303-714) ·------

N

A Date: 6/26/2020

YAOGIS2019-0008

Coachella Illegal Dump Sites - - Site 1

Site 1: Avenue 70 @ Coachella Canal SW ¼ SW ¼ , 523, T75, Rl0E, SBM on Reclamation Acquired Land.

width r±

10'Min.

6' Minimum from existing grade

Onsite material to be used to build berms Approx. 2: 1 slope (See Note 4)

Existing ground .ff··111_ -ill,,,III

III I ll � �-'-

DETAIL A - TYPICAL BERM

(NOT TO SCALE)

4 5

Coachella Illegal Dump Sites - - Site 2

Site 2 Berm Approx. 1,050' long

New Security Pipe Gate llll , , (See Drawing

Date: 612612020

YAOGIS2019-0008

1163-303-714)

Site 2: Avenue 56@ Coachella Canal SW¼ SW¼ , 518, T6S R9E, SBM on Reclamation Withdrawn Land.

Notes:

1. Drawing is not to scale, field verify all dimensions and elevations.

2. Dial "811" DigAlert at least two full working days prior to digging.

3. Government will stakeout berm locations, and security pipe gate locations.

4. Contractor shall use water and equipment while placing material for compaction when building berms.

4 5 ite

RECLAMATION

Managi.ng Water in the West z <I'.

w

� U Vl UJ z w f--w <I'.� vi

D

LL z ,_. a_ " I:; w _J ::;:

<( � '"zf-0 => IC(/) wzao z<I'.

���§ � LL _J ::c :I: z C: c::( <C ::.:: :;:soc ::E<i:

C.9 Z o��� W W >-" 1l _J c::: _J

5: ffi� [cl <( � f- hffioz<I'.

::5 ��Clct <(W

Ul �ffi:58 uu u:1 � <n al :'.:S > J:=> c::: u:S:

_Jw c3 <i! �

Vl U u <I'.

u

JEFF L, SANDERSON C,E,T,

DESIGNED

JEFF L. SANDERSON C.E.T.

DRAWN

X

CHECKED

Garcia Samuel (Sam) P.E.

TECH. APPR.

Scott, Carrie M P.E.

APPROVED

ADM IN APPROVAL - Chi�f of T�dmical Support Offlc�

YUMA, AZ 2020-07-24

CLEAN UP SITE 1 AND

SITE 2

SITE PLANS AND

TYPICAL BERM

212-303-60002

SHEET 1

B

A

Area of asbestos

1180 Durfee Avenue, Suite 125, South El Monte, CA 91733

323.517.9780 | oneatlas.com

1180 Durfee Avenue, Suite 125, South El Monte, CA 91733

323.517.9780 | oneatlas.com