This Statement of Work (SOW) details a sewer pipe repair project for the Riverside National Cemetery in Riverside, California. The project involves repairing approximately 2 feet of a broken cast iron sewer pipe located outside the women's restroom, including removal and disposal of the damaged pipe, restoration of a 4'x4' concrete section, and descaling 50 feet of the cast iron sewer line. The work must be completed within 30 calendar days from the contract award, with site work restricted to 8:00 AM to 4:30 PM, Monday through Friday, excluding federal holidays.

The solicitation (36C78625Q0095) is issued by the Department of Veterans Affairs National Cemetery Administration, with a response due date of 6/27. Contractor qualifications include a minimum of 3 years of experience in biohazard or sewage remediation, preferably with IICRC certification. The project requires compliance with OSHA, EPA, and VA environmental and safety standards. Key contacts include Keith Allen (Executive Cemetery Director), Francisco Jimenez (COR), and Glen Kinion (Project Manager). Contractors must adhere to strict conduct standards, maintain a professional appearance, and work with utmost respect for the cemetery's solemn environment.

View the file

Other files

File Type Posted
36C78625Q0095 Riverside Sewer line repair RFQ.docx DOCX document
SOW Admin Sewer line.doc DOC document
WAGE DETERMINATION.pdf PDF
36C78625Q0095 Riverside Sewer line repair RFQ.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Riverside National Cemetery Administrative Bldg 6/6/2025 Sewer Pipe repair

Scope of Work

Riverside National Cemetery 22495 Van Buren Boulevartd Riverside, CA 95128

SCHEDULE OF SERVICES:

Description
Quantity
Unit
Unit Price
Total Price
1. Repair broken sewer pipe of Admin Building, removal and disposal of broken pipe
1
Job
$___
$___
2. Restoration and matching of removed concrete
1
Job
$___
$___
3. Descale cast iron sewer line
1
Job
$___
$___
TOTAL PRICE
$__

1. GENERAL SCOPE OF WORK:

The objective of this Scope of Work (SOW) is to repair an approx. 2’ broken section of cast iron sewer pipe and to restore an approx. 4’x4’ section of concrete which is located outside the womens restroom, within Riverside National Cemetery, to full operational status, in accordance with OSHA environmental, safety, and sanitation standards.

The contractor shall provide all labor, materials, equipment, and services required to assess, and remediate the impacted space in accordance with OSHA regulations, local health and safety codes and applicable environmental standards. The space must be restored to a safe, sanitary, and fully functional condition suitable for public, employee, and ceremonial use.

Work will be accomplished in accordance with VA requirements, Federal, State, and Local Code requirements.

All work will be conducted in such a manner as to minimize the impact on the cemetery operations. Submission of a schedule that minimizes the effect of normal operations on the cemetery shall be approved by the Contracting Officer’s Representative (COR) and Cemetery Director prior to the start of work.

Site work will be accomplished between the hours of 8:00 and 4:30, Monday through Friday; no work will be performed on Federal Holidays.

All work will be coordinated with the COR. Only the Contracting Officer (CO) has the authority to make changes to the contract that affects price and/or time.

Project Location: Riverside National Cemetery, 22495 Van Buren Ave, Riverside, CA 93203.

Completion Time: Ninety (30) calendar days from the date of issuance of Notice to Proceed (NTP).

Executive Cemetery Director, Keith Allen

TEL: (661) 867-2260

Keith.Allen1@va.gov COR, Francisco Jimenez

TEL: (909) 220-2514

francisco.jimenez@va.gov

Project Manager:

Glen Kinion NCA Pacific District

415-518-1064 glen.kinion@va.gov

DESCRIPTION/STATEMENT OF WORK/SPECIFICATIONS

Description:

Work in this project includes but is not limited to:

Item 1:

A. Repair broken sewer pipe, remove and dispose of broken pipe section B. Restoration and matching of removed concrete C. Descale cast iron sewer line Item 2: Tasks and Requirements

2.1 Repair of broken sewer pipe (CLIN 0001)

· 4” cast iron pipe repair: cut out approx. 2’ section of broken cast iron sewer pipe and rebuild with proper fittings necessary to properly tie in to sewer main

· Removal and dispose of cut-out broken pipe section and fittings

· Ensure safe transport and disposal in compliance with federal, state and local regulations

· Provide disposal manifests upon request

2.2 Structural and Aesthetic Restoration (CLIN 0002)

· Backfill over the repair with appropriate fill material and provide adequate compaction (95% compaction)

· Patch the approx. 4’x4' section with concrete to match existing finish to maintain uniformity in compliance

· All work must adhere to National Cemetery Administration construction and finish standards Descale cast iron sewer line (CLIN 0003)

· Descale the cast iron sewer line starting from existing clean out located in utility room behind the effected restrooms, to downstream approx. 50' 3 Exclusions

· Initial concrete and soil removal to expose the suspected broken sewer pipe, will be done by cemetery staff prior to project start date Deliverables

Deliverable
Description
Due Date
Repair Plan
Detailed step-by-step plan
Within 2 business days of contract award
Daily Logs
Summary of work, personnel, findings
Daily during project
Final Report
Full remediation and clearance documentation
Within 5 days of project completion

· Performance Standards

All work must comply with:

· OSHA 29 CFR 1910 and 1926

· EPA Sewage remediation and disposal guidelines

· NCA Operational Standards and Measures

· VA Directive 0051 (Environmental Management)

· Local/state public health requirements

Contractor must complete work within 30 calendar days from contract award.

All materials and equipment must meet federal environmental and procurements guidelines.

· Contractor Qualifications Minimum 3 years of experience in biohazard or sewage remediation

IICRC (Institute of Inspection Cleaning and Restoration Certification) preferred or equivalent

Proof of general liability and pollution/environmental liability insurance

Contractor personnel must adhere to NCA conduct and dress codes while on site.

· Government-Furnished Property and Site Access The government will provide access to the affected area and utilities as needed.

The contractor shall coordinate all work schedules with the COR to avoid disruption to cemetery operations, ceremonies, and public access.

GENERAL REQUIREMENTS

1. The Contractor shall submit sample and technical specifications on all materials being used in this project and shall not proceed with any work before approval by the Project Manager and COR.

2. Before beginning any work, the Contractor shall survey the site examine the drawings, and review the scope of work to determine the extent of the work. The Contractor shall take the necessary precautions to avoid damages to existing items to remain in place, to be reused, or to remain the property of the Cemetery. Any damaged items shall be repaired or replaced at the contractor’s expense as directed by the COR.

3. Establish construction limits, install safety controls, and install construction fencing as approved by the COR.

4. Thoroughly clean up the work area at the end of each day’s work and at the completion of the project. Leave premises clean and free of waste, scrap used equipment, or other material intentionally or incidentally delivered to the site by Contractor or Contractor’s personnel.

5. The Contractor shall protect from damage all existing improvements, equipment, structures, facilities, grounds, and utilities at or near the work site or adjacent property. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly.

6. Upon completion of contact, deliver work complete and undamaged. Existing materials, equipment, structures, facilities, grounds, and disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in good condition as existed before commencing work.

7. At the Contractor’s own expense, the Contractor shall immediately restore to service and repair any damage caused by the Contractor’s workmen to existing piping and consults, wires, cables, etc., of utility services or of fire protection systems, communication systems (including telephone) which are not scheduled for discontinuance or abandonment.

8. Remove, cut, alter, replace, patch, and repair existing work as necessary to install new work. Existing work to be altered or extended and that is found to be defective in any way shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality to that of the original existing construction, except as otherwise shown or specified.

9. Thoroughly clean up the work area at the end of each day’s work and at the completion of the project. Leave premises clean and free of waste, scraps, used equipment or other material intentionally or accidentally delivered to the site by the Contractor or Contractor’s personnel.

10. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site not to be removed and do not reasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

11. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be made known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

12. All utilities required for the continuous operation of all existing facilities shall be maintained in service at all times except when disruptions are needed. The contractor shall inform the Cemetery Director and the Contracting Officer (CO) in writing 2 weeks prior to the need shutdown. When the option exists, implement options to minimize interruption of services to the facilities.

13. The Contractor shall coordinate with the Cemetery Director for parking, material storage, temporary portable restroom facilities and any other needs for the work. Public access to the National Cemetery shall not be impaired.

14. Thoroughly clean up the work area at the end of each day’s work and at the completion of the project. Leave premises clean and free of waste, scrap, used equipment or other material intentionally or incidentally delivered to the site by Contractor or Contractor’s personnel.

15. The Contractor shall protect from damage all existing improvements, equipment, structures, facilities, grounds, and utilities at or near the work site or adjacent property. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

16. Upon completion of contact, deliver work complete and undamaged. Existing materials, equipment, structures, facilities, grounds, and disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in good condition as existed before commencing work.

17. At the Contractor’s own expense, the Contractor shall immediately restore to service and repair any damage caused by the Contractor’s workmen to existing piping and consults, wires, cables, etc., of utility services or of fire protection systems, communication systems (including telephone) which are not scheduled for discontinuance or abandonment.

18. All work will be coordinated with the Contracting Officer’s Representative (COR). Only the Contracting Officer (CO) has the authority to make changes to the contract that affect price and/or time. Work will be conducted in such a manner to minimize the impact on the Cemetery operations.

19. Coordination of Construction with the Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction the construction schedule to cause the least possible interference with Cemetery activities in actual burial areas. Construction noise during the committal services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period.

a. The Contractor is required to discontinue his work efficiently in advance of Easter Sunday, Mother’s Day, Father’s Day, Memorial Day, Veteran’s Day, and/or Federal Holidays to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.

b. Cleaning up shall include the removal of all equipment, tools, materials, and debris and leaving the area in a clean, neat condition.

c. Site work will be accomplished between the hours of 8:00 and 4:30, Monday through Friday, except for Federal Holidays. Work outside of the Cemetery’s normal operating hours of 8:00 am to 4:30 pm shall be permitted on by approval of the COR and to only meet the Period of Performance.

STANDARDS OF EMPLOYEE CONDUCT:

1. The National Cemetery Administration honors veterans with a final resting place and lasting memorials that commemorate their service to our Nation. National Cemeteries are national shrines. The standards of work appearance and procedures performed by the Contractor at this cemetery shall reflect this nation’s concern for those interred there. Due to the sensitive mission of the cemetery and exhibit absolute decorum, composure, and stability all times.

2. Contractor personnel shall be required to adhere to the following standards of dress and conduct, as briefly mentioned here while performing work in the National Cemetery. These standards are enforceable under Title 38, USC, Part 1, Chapter 9, and Section 5901.

3. Clothing shall be presentable and suitable to the work while maintaining proper appearance and decorum indicative of a National Shrine. Uniform shirts and hats are preferred. Clothing shall be clean and cleanliness and personal hygiene are imperative. T-shirts and/or tank tops as outer garments are prohibited. Protective/Safety clothing and shoes shall meet or exceed OSHA and state requirements.

4. Behavior and language must be appropriate, reverent, and respectful at all times.

5. Eating and drinking (except water) is prohibited in the work areas and within the sight of a committal shelter during a service.

6. Use of intoxicating beverages, any tobacco products, and illegal drugs in the Cemetery is strictly prohibited.

7. Contractor personnel shall not lean, sit, or stand on or against headstones or monuments. No tools, equipment, or other items will be placed on or leaned on headstones or monuments.

8. The Contractor shall be responsible for maintaining satisfactory standards of personnel conduct and work performance and shall administer disciplinary action as required. The Contractor is expected to remove any employee(s) from the Cemetery for cause, including, but not limited to, safety violations, other misconduct in the performance of duty under these specifications, and/or contrary to the best interest of the Government. If the Contractor fails to act in this regard, or the reason for removal is immediately required to protect the interests of the Government, the COR may direct the removal of an employee from the premises. Contractor objections to any such action will be referred to the Contracting Officer (CO) for final resolution; however, the Contractor will first immediately comply with COR direction pending any CO final resolution at a later date or time. The Contractor will not be due any type of compensation for the costs incurred as a result of an employee being removed for cause; unless the removal is directed by the COR and later found to be invalid or /or unreasonable by the Contracting Officer.

9. All work shall be performed in accordance with National, State, and Local Codes including the International Building Code (IBC), the International Mechanical Code (IMC), the International Plumbing Code (IPC), and the National Electrical Code (NEC).

All work shall be performed in accordance with the drawings and specifications. It shall be the Contractor’s responsibility to comply with all the applicable codes. The Contractor shall apply and obtain all applicable permits to comply with local, State, and Federal regulations.

CONTRACTOR QUALITY CONTROL

1. The Contractor shall guarantee that all work done under this contract shall be free from defaults and no faulty materials or workmanship with one (1) year warranty or extended manufacturer’s warranty. The Contractor hereby agrees to repair or replace deficiencies within the specified time frame by the direction of the Contracting Officer (CO) at the Contractor’s expense. And shall be corrected to the satisfaction of the Government.

2. The Contractor shall provide a Job Site Superintendent who speaks and writes fluent English on site, and at all times when Contractor personnel are on the premises. The Job Superintendent will:

a. Review and Approve submittals

b. Inspect the quality of work performed

c. Certify the completed work for payment and other purposes Attachments