This is a Statement of Work (SOW) for the installation of an air conditioning system at Fire Station #8, Building #1058 in the Vogelweh Housing Area at Ramstein Air Base, Germany. The project, designated YANB 21-1566, is managed by the 435th Construction and Training Squadron with a target completion date of September 2025. The contractor must manufacture, deliver, and assemble a complete REMKO MVV 2003 DC inverter multi-split VRF air conditioning system consisting of one outdoor unit, one floor console, one condensate collection tray with oil separator, nine indoor wall-mounted units (REMKO MVW 222), and nine wired remote controls. The scope includes installation of a complete refrigerant pipe network using seamless copper pipes with thermal insulation, connection of condensation pumps and hoses, job site mobilization, system commissioning, and provision of operating materials including R 410A refrigerant.
All work must comply with applicable German regulations (DIN EN standards, VDI standards) and U.S. Air Force standards, including cybersecurity requirements per UFC 4-010-06 for all electronic components. The contractor must obtain a risk assessment per German Labor Protection Law two weeks prior to installation start and coordinate with the Health & Safety Coordinator. An independent expert hired by the contractor must conduct a comprehensive technical handover inspection including pressure testing, evacuation, system calibration, and user instruction. Deliverables include as-built documentation in English and German within 20 days of turnover, consisting of CAD files in DWG format compatible with AutoCAD 2024 or lower, technical specifications, installation and maintenance manuals, electrical diagrams, and training protocols. The contractor bears all costs for site entry passes, police clearance certificates, waste disposal, and storage area maintenance. An AF Form 679 waiver for air conditioning installation was approved on 23 August 2022, and coordination with HVAC-Shop confirms that only REMKO manufacturer components may be installed.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
YANB 21-1566 – Install Air Conditioning
Statement of Work
Install Air Conditioning
Construction Project Number: YANB 21-1566
Add/Alter Fire Station #8, Building #1058
Installation and Location/UIC: Germany- Vogelweh Housing Area
435th Construction and Training Squadron
Ramstein Air Base
September 2025
COR:
Mr. Felix MAYER | Tel: 06371-47-6368 | Email: felix.mayer.de@us.af.mil
SOW prepared by:
Mrs. Slava MIRKOVA | Tel: 06371-47-7420 | Email: slava.mirkova.bg@us.af.mil mailto:felix.mayer.de@us.af.mil
Title I – General
435 CTS will remodel building #1058 in Vogelweh Family Housing, Germany, to house
Satellite Fire Station #8. The requested work includes the renovation and remodeling of
Building 1058 and the addition of a vehicle bay.
The remodel/construction work is necessary to provide an adequate and functional satellite fire station to provide efficient and effective fire and rescue services to the Vogelweh Family
Housing Area. This new fire station will ensure that the DoDl6055.06 required emergency response time to all military facilities within 7 minutes.
1. Location:
The new Fire Station #8 will be located on Vogelweh Housing Area, Alabama Street – next to building #1058 and can be reached by paved roads. A location map is attached under Title
III. The area can only be entered with valid US entry passes. Costs for entry passes and police clearance certificates are at the contractor's expense.
2. Applicable Publications / Norms:
All work shall be planned and carried out in compliance with relevant German regulations regarding installation, commissioning and final turn over of air conditioning systems with cooling fluids (i.e. DIN EN 16798-1, DIN EN 16798-3, DIN EN 378, DIN 8960, DIN EN
1736, DIN 8901, VDI 2078, VDI 2081). In addition, traffic rules and the safety regulations of the Bauberufsgenossenschaft (builders association) shall be adhered to, as well as the
Base Appearance Standards for KMC construction projects.
Important: For the installation of the air conditioning the user has provided CTS with a AF FORM 679, an approved waiver, dated 23 Aug 2022.
3. Additional Information:
Cooling load calculations for the rooms and a floor plan are available. The pipe dimensions must be checked by the contractor and adjusted if necessary. If changes to the pipe routing are necessary compared to the plan already supplied, these must be entered into an execution plan early on and coordinated with the client so that the necessary installation plans can be harmonized with the other trades. Air coolers must be installed in such a way that proper condensate drainage is possible.
It has already been coordinated with HVAC-Shop, RAB, and due to repair and maintenance work, only components from the manufacturer REMKO are to be installed – see attached email correspondence with Mr. Denis Müller, 86 CES/CENMP.
Please be advised that all electronic components will be subject to a Cybersecurity check and only components that are compliant with UFC 4-010-06 Cybersecurity of Facility-
Related Control Systems may be installed. The contractor is obliged to deliver all relevant documents for this check with the quote. Please be advised that quotes with missing
Cybersecurity information cannot be reviewed!
4. Acceptance / Commissioning / Handover:
An inspection must be carried out by an independent expert, hired by the contractor.
The technical handover of equipment includes checking and documenting the delivered equipment components and the entire pipe network, including pressure testing and evacuation. In addition, a comprehensive refrigeration equipment inspection is carried out.
This includes checking the system pressures and all relevant values to ensure fault-free operation, as well as instructing the system technician. The technical handover of the system to the user is carried out by qualified personnel.
Furthermore, the following services are part of the technical equipment handover: Visual inspection of the indoor and outdoor modules for assembly errors and damage, visual inspection of refrigerant lines, inspection of electrical connection lines, leak test with dried nitrogen, evacuation and filling of the system, calibration of indoor and outdoor parts, instruction of the user, creation of a report, and technical equipment handover to the user.
5. As-Built Documentation / Manuals
Provision of 3 CD-ROMs with all relevant electronic files (dwg. and pdf-format), manuals, maintenance schedule, circuit schemes, electrical engineering conformity:
- Technical specifications, dimensioning of entire complete and sufficient system in accordance with U.S. and host nation regulations.
- AC installation/assembly and maintenance manuals
- Electrical installation, conformity of proper installation and connection to provided main power distribution panel
- All manuals & files will have to be provided in English and German language.
Title II – Description of work:
Manufacturing, delivery and assembly of entire air conditioning system, consisting of:
1. Job Site Mobilization
- Construction site setup
- Work platform, scaffolding, and/or ladders. Installation height: max. 3.50 m above floor.
2. Air conditioning system, consisting of:
Description: REMKO MVV 2003 DC
Quantity: 1 each
Manufacturer: Remko
Model: MVV 2003 DC
Item number: 1623680
Description: Floor console BK-1000 Plus S
Manufacturer: Remko
Model: BK-1000 Plus S
Item number: 1613273
Description: Condensate collection tray incl. oil separator MVV 2000/Duo
Manufacturer: Remko
Model: MVV 2000/Duo
Item number: 260128
Description: REMKO MVW 222
Quantity: 9 each
Manufacturer: Remko
Model: MVW 222
Item number: 1623504
Description: KFB-4 wired remote control
Manufacturer: Remko
Model: MVD 222-1002/MVW 222-562
Item number: 1613269
- Fixed price for the refrigeration connection of indoor air conditioning units in connection with the technical handover of equipment by REMKO (also for A2L refrigerants in accordance with
DIN EN 60335-2).
- The contractor must announce all necessary power requirements for CTS pre-installation.
3. Pipe network:
Refrigerant pipes made of seamless drawn copper from Cu-DHP, strength R220 soft according to
EN 12735-1, cleaned inside, pipe ends sealed, with factory-fitted thermal insulation made of modified polyethylene according to DIN EN 14313 with structured white protective film. Building material class flame retardant CL s1 d0 according to DIN EN 13501-1, does not drip when burning, minimal smoke development. Permissible operating pressure 169 bar with 3-fold safety up to 100 °C according to EN 14276.
Installation of pipes in accordance with DIN EN 378-2 and DKI i.164, copper pipes in refrigeration and air conditioning technology. Brazing using silver or phosphorus solders in a protective gas atmosphere. Pressing with special press fittings for refrigerant-carrying pipes in accordance with
DIN EN ISO 14903.
Brazing is carried out using brazing alloys in accordance with DIN EN ISO 17672, recommended brazing alloys CuP 179 or CuP 279, if necessary, fluxes in accordance with DIN EN 1045 type
FH10 must be used. For solders AG 134, AG 145, and AG 244, use flux in accordance with DIN
EN 1045. Type: FH 10. Brazed joints may only be made by qualified personnel. Before and during the joining process by brazing or welding, the pipes must be flushed with dry protective gases, e.g., inert gases (noble gases, nitrogen, and mixtures thereof) or forming gases (e.g., nitrogen-hydrogen, nitrogen-argon, etc., max. hydrogen content 4 vol.%). When using capillary solder and press fittings, consult the respective fitting manufacturer regarding the possible areas of application, particularly the maximum permissible operating pressures.
Pipe network consisting of following components:
Description: Refrigeration pipe, insulated, installed according to design.
Quantity: according to design
Manufacturer: Remko
Model: 3/8”, 3/4”, 1/4”, 1/2”, Item number: 260128
Description: Y-distributor set for MVV AT/IT fluid and suction line
Quantity: 2 sets
Item number: 1611095
Description: 4-way distributor set for liquid gas and suction line
Quantity: 2 sets
Item number: 1611096
Description: Condensation hose 16/18 mm diameter, per meter
Quantity: 1 each per wall unit
Item number: 1613053
Description: Condensation pump KP-6
Quantity: 1 each per wall unit
Item number: 1613251
- The installation of the distribution sets involves connecting and soldering the refrigerant lines already connected by the installer to the distributors. Since absolute cleanliness must be ensured in this complex pipe system, soldering is carried out under dry nitrogen.
4. Miscellaneous / Additional services, special services:
- The pipe dimensions must be checked by the contractor and adjusted if necessary.
- The contractor must adjust the system components so that the planned functions and performance are achieved and the legal requirements are met. The air volume flows must be adjusted in accordance with the calculated settings. Measured values must be documented.
- The contractor shall provide one-time training for the operating and maintenance personnel for the system. Leading time for coordination: 2 weeks.
- If necessary, the delivery and installation of special fastening structures, e.g., brackets and support frames is also part of this contract.
- Delivery of the operating materials and media required for commissioning and trial operation, particularly the required refrigerant R 410A.
5. As-built documentation
As-built documentation, digital revision documents in German and English language including:
- System diagrams.
- General electrical diagrams and connection diagrams in accordance with DIN EN 61082-1
“Electrotechnical documentation – Part 1: Rules.”
- Compilation of the key technical data.
- Copies of the required test and manufacturer certificates.
- All operating and maintenance documents, required for safe and economical operation.
- Protocol on the training of maintenance and operating personnel.
Title III Attachments:
PDF.files created by 435 CTS / CEP:
- B4229_M9_Air Conditioning_Floor Plan_Phase 1.pdf
- B4229_Cooling Load Calculation VDI2078.pdf
- E-Mail AC Remko Manufacturer.pdf
- Bldg 1058-Fire Station 9-AF Form 679 AC Waiver.pdf
The site location is at Vogelweh Family Housing and can be accessed via 3rd Avenue or Alabama
Street.
Title IV Special conditions
1. Technical Specifications, Manuals, As-Built-Package
20 days prior to turn-over event: All As-built documentation, maintenance manuals, technical specifications and analysis reports must be provided in English and German language to 435 CTS.
Drawings must be submitted as CAD plans/ DWG format, compatible with AutoCad (2024 or lower) and as PDFs.
2. Marking
Delivery and installation of functional, identification, and information signs.
3. Waste/ package and grading materials
All waste materials generated by the contractor must be disposed in accordance with the local and federal waste disposal laws. This is part of the contract.
4. Storage Area
435 CTS will determine and delegate the contractor an area for material and equipment storage. It is the contractor’s responsibility to ensure that no contamination by improperly stored fuels, chemicals or paints occurs. The contractor is responsible for the security of his property.
Bldg. 1058
5. Health and Safety coordinator
The contractor must provide a risk assessment (German Labor Protection Law) for all required and described accomplishments not later than 2 weeks prior to installation start. This assessment has to be provided to the 435 CTS Health & Safety Coordinator Mr. Ralf Schrade, ralf.schrade.de@us.af.mil, 435 CTS/CEP, An der Schwarzbach, Bldg. #667, 66877 Ramstein-
Miesenbach, Phone: 0049-(0)6371-47-7290.
6. Compliance with Environmental Protection Programs
The contractor shall execute all work covered in this project in accordance with regulations in the applicable environmental protection management programs (EMS). The contractor shall carry out the work in a resource-saving manner including water, energy and other resources. The generation of refuse or debris shall be minimized. Whenever possible, materials shall be recycled or reused.
Also, low toxic materials shall always be the first choice, if they meet all requested criteria.
Should any breaches of these environmental protection regulations occur during the project, the contractor must rectify or avoid these issues. Rectifying measures shall be based on the time schedule prepared by the EMS coordinator. Also, the contractor has to make sure that his staff knows the details of the environmental protection programs applicable on base and for the work in question.
7. Compliance with Environmental Protection Requirements
The contractor shall comply with all German and USAF regulations regarding environmental protection, to include the German FGS. The contractor shall be able to understand and implement all environmental laws and regulations that apply to this project.
8. Security Requirements
Employees from countries listed in Section K 252.209-8001 of “Disclosure of Ownership or
Control by a Foreign Government that Supports Terrorism” are not allowed access to the military installation without special permission. Base passes will be issued only to people for whom clearances have been granted. The contractor shall not assign any employee to perform work on such installation if the Contracting Officer decides that the presence of the employee would not be in the best interest of the US Government. The contractor shall inform all their assigned workers that they may be subject to search when entering or leaving the job site.
Title V Technical information and product specifications
REMKO MVV 2003 DC
Inverter multi-split VRF outdoor unit for direct evaporation for floor or wall mounting. Outdoor unit for cooling or heating for connection of 2 to 11 indoor units as wall or ceiling cassette units. The outdoor units are designed for connection of indoor units with a min/max cooling connection capacity of 50% to 130%.
The units comply with the relevant EU regulations and are CE marked in accordance with the applicable directives.
Technical data:
Manufacturer: REMKO
Model: MVV 2003 DC
Rated cooling capacity [KW]: 20.0 (10.0 – 21.0)
Rated heating capacity [KW]: 22.5 (10.1 – 25.9)
Energy efficiency class K/H: A++ / A
Energy efficiency rating SEER / SCOP: 7.4 / 4.0
Working range, outdoor unit cooling [°C] -5 to +48
Working range, outdoor unit heating [°C] -20 to +24
Cooling fluid / GWP: R410A
Power supply [V/~/Hz]: 400/3/50
Size (H/W/D) [mm]: 1.558/1.120/528
Weight [kg]: 143
Floor console BK-1000 Plus S
Robust floor bracket for the REMKO MVV 2000 DC outdoor unit, made of reinforced rubber and with a high dead weight. Particularly good damping properties. The set consists of 3 floor brackets.
Supplied as standard with screws, nuts, and washers for attaching the outdoor unit.
Technical data:
Size (H/W/D) [mm]: 100/160/1000
Condensate collection tray incl. oil separator MVV 2000/Duo
Condensate collection tray with oil separator: The condensate collection tray with integrated oil separator prevents oil that has run into the oil protector from being washed out when it rains. The oil is retained completely.
Technical data:
Material: Stainless steel
Size (H/W/D) [mm]: 35/1250/590
Refrigeration pipe, insulated, installed according to design
Quantity: The length of the refrigerant line depends on the local conditions and the design.
Installation of needed refrigeration pipes in different diameters and lengths according to design and calculations. All lines must be insulated. The total length of the refrigerant line depends on the local conditions.
The maximum permissible line length, depending on the outdoor unit must be observed.
Refrigerant pipe 3/8”, Item no: 1613056
Refrigerant pipe 3/4”, Item no: 1613059
REMKO MVW 222
Indoor unit for installation in the upper wall area. Can be combined with the VRF outdoor units of the
REMKO MVV series. Designer front in white with concealed display. Standard features: 7-stage DC fan motor, dust filter, restart after power failure, infrared remote control, swing mode, potential-free contact for external on/off and alarm forwarding, connection options for KFB-4 cable remote control and REMKO
SmartControl.
Technical performace data:
Rated cooling capacity [kW] 2,20
Rated heating capacity [kW] 2,40
Area of application (room volume) approx. [m³] 70
Air flow rate per stage [m³/h] 356/380/386/390/402/411/422
Noise level per stage [dB(A)] 29/29/29/30/30/30/31
Power supply [V/~/Hz] 230/1/50
Size H/W/D [mm] 280/835/203
Weight [kg] 8,4
Condensation pump KP-6, including cable duct for surface mounting and condensation hose.
Quantity: 9 each: 1 each per wall unit
KP 6 condensate pump with cable duct and alarm contact as well as condensation hose, d:6mm.
Power supply [V/~/Hz] 230/1/50
Noise level [dB(A)] <22
Maximum flow rate [l/h] 8 max. Pumping height [m] 6
Protection class: IP 54
Cable duct length [mm] 750