SOW - AB Controls Upgrades.pdf
PDF 468 KB Posted
- Attached to
- JB-Charleston A/C Controller upgrades
- Solicitation number
- A039943
About this file
This document is a Statement of Work for an Air Base Controls Upgrades project at Joint Base Charleston. The work consists of upgrading the existing building automation system controllers to Tracer SC+ controllers and integrating them into the base-wide Energy Management Control System (EMCS) to be compatible with the existing Trane Ensemble system. The project will replace approximately 38 Trane BCUs, 6 Trane SCs, 7 Trane ILONs, and 11 JCI Network Attached Engines/Field Servers as building level controllers. It will also upgrade obsolete software and firmware to use secure communication protocols. Upon completion, the EMCS will be consolidated into one system and fully migrated to BACnet over IP protocol.
The related Federal Contract Opportunity is a Notice of Intent to Award a sole source contract to Trane USA for the upgrades. The work to be performed is summarized in the Statement of Work. The contract will be awarded under the statutory authority of 10 U.S.C. 3204(a)(1) or 41 U.S.C. 3304(a)(1) due to Trane being the sole authorized provider of the A/C systems at Joint Base Charleston. Responsible sources may submit capability statements, proposals, or quotations by 1:00PM EST on 12 August 2024 for the Government's consideration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HVAC Chiller Justification and Approval - Signed.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Air Base Controls Upgrades
Statement of Work
Air Base Controls Upgrades
Joint Base Charleston
20 June 2024
MISSION IMPACT: The existing equipment designated in this Statement of Work (SOW) are largely in legacy status and prevent migration from the legacy-status Tracer Summit control system. Repair materials are increasingly unavailable for the building controllers and associated equipment, and the Tracer Summit system traffic is blocked by the firewall across the COINv2 domain. The Tracer Summit operating system currently remains off the COIN domain while residing on the COIN VLAN, introducing a significant vulnerability and preventing compliance with the current cybersecurity policies, particularly DAFGM 2023-3201 CE Control Systems Cybersecurity memorandum. Once building controllers are converted to SC+'s, the remaining Tracer Summit workstations can be joined to COINv2 and full Energy Management Control System (EMCS) functionality will be capable at the associated buildings through the Trane Ensemble Platform.
A. GENERAL: The work to be performed consists of providing all designs, labor, material parts, and equipment necessary to replace all remaining outdated building automation system front end controllers to Tracer SC+ controllers and integrate to the existing base-wide EMCS such that they are fully compatible with the existing Tracer
Ensemble system. There are roughly 38 Trane BCUs, 6 Trane SCs, 7 Trane ILONs, and 11 JCI Network Attached
Engines/Field Servers that are acting as building level controllers. The project will also remove critical obsoleted unit controllers, like chilled water plant controllers, but integrate remaining unit controllers, like VAV box controllers. This will allow for the remaining devices to continue to run and be replaced at failure. All beyond-end-of-life software and firmware that communicate on the base's network will be removed or upgraded within the
EMCS network and insecure protocols (NTLM v2, Telnet, HTTP, N2, and Metasys Private Message) will be replaced with secure and DISA approved communication protocols (BacNet, Secured Fox, HTTPS, Kerberos, SMTP, and SSL Platform Daemon). The majority of remaining unit controllers that communicate directly with corresponding building controllers, but not on the base's network, will remain. Upon completion, the JBC AB
EMCS will be entirely consolidated into one system and fully migrated to BACnet over IP protocol. The existing
Trane Summit system that communicates with most of these controllers will be able to be decommissioned. All project components and materials shall be installed in accordance with the manufacturer’s technical installation instructions and specifications. Contractor shall provide all tools, qualified labor, materials, equipment, supplies and supervision necessary to engineer, install, and warranty all items in accordance with the following Statement of
Work. All work shall be accomplished in accordance with all Federal, State, Local Regulations and applicable guidelines & requirements to include but not limited to the following codes and standards:
1. International Building Code
2. International Mechanical Code
3. National Electrical Code (NFPA 70)
4. National Fire Code (NFPA 1)
5. Unified Federal Criteria (UFC)
B. LOCATIONS: All Air Base facilities listed in the following table.
49 219 466 673
51 221 468 705
54 469 707
60 247 473 721
72 302 479 729
74 322 503 731
112 325 544 798
129 346 548 1950
169 366 578 1951
176 407 581 1990
201 412 610 1993
214 461 652 16000
215 464 669 Substation
C. SCOPE OF WORK: The project requirements include, but are not limited to the following:
1. Integrate new Tracer SC+ building controllers into the existing base wide Trane Ensemble Server in AB building 721.
2. Provide necessary programming, startup, and checkout.
3. Recreate all demand limiting programming that was in Summit to be in Ensemble.
GENERAL:
1. All concealed low voltage control wiring to be plenum cable, all other to be in conduit.
2. All necessary custom programming for control and supervision of equipment as specified.
3. All work to be performed between 7:00 AM and 5:00 PM Monday through Friday.
4. Provide complete sets of submittals.
5. Provide as-built documentation and complete system manuals.
6. Warranty first year parts and labor for control work listed.
BUILDING 49
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing SC.
• Provide control as-built drawings and submittals.
• Integrate the following existing equipment:
• (1) power meter
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
BUILDING 51
Building Automation System, Tracer SC+ System: (Qty. 2)
• Provide, mount and wire (1) Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Existing Field Server to remain
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (1) SYMBIO500 to replace water pressure controller MP580.
• Reuse existing enclosure
• Integrate the following existing equipment:
• (2) CRUs
• (35) VAV boxes
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Water Pressure Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire (1) SYMBIO500 controller to replace existing MP580
• Reuse existing enclosure and transformer.
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
CRU Integrations (Qty: 2)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 35)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
BUILDING 54
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing SC.
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (2) SYMBIO500s to replace mechanical room controller and separate pumps and air handlers.
• Reuse existing enclosure
• Integrate the following existing equipment:
• (18) VAV boxes
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Mechanical Room Controllers (Qty: 2)
• Label and disconnect all inputs and outputs
• Provide, mount and wire (2) SYMBIO500 controller to replace existing MP580
• Reuse existing enclosure and transformer.
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
VAV Integrations (Qty: 18)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 60
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing SC.
• Provide control as-built drawings and submittals.
• Integrate the existing equipment:
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
BUILDING 72
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following new pieces of equipment:
• (1) Air Cooled Chiller
• Integrate the following existing pieces of equipment:
• (4) AHUs
• (38) VAV Boxes
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Chiller Integration (Qty: 1)
• Wire new BACnet/MSTP link from SC+ system controller to chiller’s BACnet controller
• Program all available BACnet points in SC+
• Set up system graphic
AHU Integrations (Qty: 4)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 38)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 74
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following existing pieces of equipment:
• (1) Air Cooled Chiller
• (4) AHUs
• (38) VAV Boxes
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Chiller Integration (Qty: 1)
• Discover device integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
AHU Integrations (Qty: 4)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 38)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 112
Building Automation System, Tracer SC+ with Bridge System: (Qty. 1)
• Provide, mount and wire Tracer SC+ with Bridge and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following existing pieces of equipment:
• (2) AHUs
• (26) VAV Boxes
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
AHU Integrations (Qty: 2)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 26)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 129
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following existing pieces of equipment:
• (8) Split Units
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Split Unit Integrations (Qty: 8)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 169
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing SC.
• Provide control as-built drawings and submittals.
• Integrate the existing equipment:
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
BUILDING 176
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing ILON adapter.
• Provide control as-built drawings and submittals.
• Integrate the following existing equipment:
• (4) Air Handler Units
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
AHU Integrations (Qty: 4)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 201
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire (1) Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (1) SYMBIO500 and enclosure to replace condenser water plant MP580.
• Integrate the following existing equipment:
• (8) Florida Heat Pump units.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Mechanical Room Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP580
• Provide new enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
Heat Pump Unit Integrations (Qty: 8)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 214
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire (1) Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following existing equipment:
• (4) Florida Heat Pump.
• Integrate the following new equipment:
• (1) SYMBIO500 and enclosure to replace mechanical room plant MP580.
• (1) XM70 IO Expansion module to replace CO2 controller
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Mechanical Room Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP503
• Provide new enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
CO2 Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire XM70 controller to replace existing MP503
• Provide new enclosure and transformer
• Wire communications from SYMBIO500 plant controller to XM70 IO module
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
Heat Pump Unit Integrations (Qty: 4)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 215
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire (1) Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following existing equipment:
• (2) Florida Heat Pump.
• (1) power meter
• Integrate the following new equipment:
• (1) SYMBIO500 to replace mechanical room plant MP580.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Mechanical Room Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP503
• Provide new enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
Heat Pump Unit Integrations (Qty: 2)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
Power Meter Integrations (Qty: 1)
• Discover devices integrated through LON converter
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 219
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing ILON adapter.
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (1) SYMBIO500 and ENC to replace pump controller.
• Integrate the following existing equipment:
• (3) Air Handler Units
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Mechanical Room Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP503
• Provide new enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
AHU Integrations (Qty: 3)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 221
Building Automation System, Tracer SC+ with Bridge System: (Qty. 1)
• Provide, mount and wire Tracer SC+ with Bridge and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (1) SYMBIO500 and ENC to replace condenser water plant MP580.
• Integrate the following existing pieces of equipment:
• (19) Florida Heat Pumps.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Mechanical Room Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP503
• Provide new enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
Heat Pump Unit Integrations (Qty: 19)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 247
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following existing equipment:
• (3) CHW Air Handler Units.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
AHU Integrations (Qty: 3)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 302
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (1) SYMBIO500 to replace CHW plant controller.
• Integrate the following existing equipment:
• (5) Air Handler Units.
• (45) VAV Boxes.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Chilled Water Plant Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP580
• Reuse existing enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
AHU Integrations (Qty: 5)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 45)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 322
Building Automation System, Tracer SC+ with Bridge System: (Qty. 1)
• Provide, mount and wire Tracer SC+ with Bridge and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following existing pieces of equipment:
• (3) Air Handler Units.
• (47) VAV Boxes.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
AHU Integrations (Qty: 3)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 47)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 325
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following existing equipment:
• (1) Boiler controller
• (1) Chilled water pump controller
• (2) Air Cooled Chillers.
• (17) Air Handler Units.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Chiller Integrations (Qty: 2)
• Discover device integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
AHU Integrations (Qty: 17)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 346
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing ILON adapter.
• Provide control as-built drawings and submittals.
• Integrate the following existing equipment:
• (1) Morganizer.
• (1) Valent Unit.
• (1) Heat Pump.
• (2) misc controllers
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
BUILDING 366
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (2) SYMBIO500 to replace CHW plant controller and AHU controller.
• Integrate the following existing equipment:
• (1) Chiller.
• (16) VAV Boxes.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Chilled Water Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP580
• Reuse existing enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
Air Handler Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP580
• Resue existing enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
Chiller Integration (Qty: 1)
• Discover device integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 16)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 407
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing SC and BCU.
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (1) SYMBIO500 to replace MP503 in back room
• Integrate the following existing equipment:
• (4) unit controllers
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Mechanical Room Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP503
• Reuse existing enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
BUILDING 412
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing JCI controller.
• Provide control as-built drawings and submittals.
• Integrate the following existing equipment:
• (3) Heat Pumps.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Heat Pump Integration (Qty: 3)
• Discover device integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 461
Building Automation System, Tracer SC+ System: (Qty. 2)
• Provide, mount and wire (2) Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing JCI controller.
• Provide control as-built drawings and submittals.
• Provide, install, and wire (9) WCIs
• (3) per floor
• Integrate the following new equipment:
• (2) SYMBIO500s to replace CHW plant controllers.
• (1) in attic
• (1) on second floor
• Integrate the following existing equipment:
• (1) Chiller.
• (7) Air Handler Units.
• (40) VAV Boxes.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Mechanical Room Controllers (Qty: 2)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP503
• Reuse existing enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
Chiller Integration (Qty: 1)
• Discover device integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
AHU Integrations (Qty: 7)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 40)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation
NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 464
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide, install, and wire (6) WCIs
• (2) per floor
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (1) SYMBIO500 to replace CHW plant controller.
• Integrate the following existing equipment:
• (1) Chillers.
• (7) Air Handler Units.
• (90) VAV Boxes.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Chilled Water Plant Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP580
• Reuse existing enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recommission system and verify proper reading from all inputs and outputs
Chiller Integration (Qty: 1)
• Discover device integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
AHU Integrations (Qty: 7)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 90)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 466
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing JCI controller.
• Reuse existing Field Server
• Provide, install, and wire (6) WCIs
• 2 per floor
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (1) SYMBIO500 to replace mech room controller.
• Integrate the existing equipment:
• (1) Chiller.
• (7) Air Handler Units.
• (40) VAV Boxes.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Mechanical Room Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP503
• Reuse existing enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recommission system and verify proper reading from all inputs and outputs
Chiller Integration (Qty: 1)
• Discover device integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
AHU Integrations (Qty: 7)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 40)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 468
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing SC.
• Provide control as-built drawings and submittals.
• Integrate the existing equipment:
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
BUILDING 469
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (1) SYMBIO500 and (2) XM90 expansion modules to replace CHW plant controller.
• Integrate the following existing equipment:
• (2) Chillers.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Chilled Water Plant Controllers (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller and (2) XM90 expansion modules to replace existing MP580 and associated expansion modules
• Reuse existing enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
Chiller Integration (Qty: 2)
• Rewire comm internally to UC800 and remove LON modules
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 473
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing JCI controller.
• Reuse existing Field Server
• Provide, install, and wire (6) WCIs
• 2 per floor
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (1) SYMBIO500 to replace mech room controller.
• Reuse Existing Enclosure
• Integrate the existing equipment:
• (1) Chiller.
• (7) Air Handler Units.
• (40) VAV Boxes.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Mechanical Room Controller (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP503
• Reuse existing enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
Chiller Integration (Qty: 1)
• Discover device integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
AHU Integrations (Qty: 7)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 40)
• Discover devices integrated through communications bridge
• Template device data in SC+
NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 479
Building Automation System, Tracer SC+ System: (Qty. 2)
• Provide, mount and wire (2) Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing JCI controller.
• Provide control as-built drawings and submittals.
• Provide, install, and wire (9) WCIs
• (3) per floor
• Integrate the following new equipment:
• (2) SYMBIO500s to replace CHW plant controllers.
• (1) in attic
• (1) on second floor
• Integrate the following existing equipment:
• (1) Chiller.
• (7) Air Handler Units.
• (40) VAV Boxes.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Mechanical Room Controllers (Qty: 2)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP503
• Reuse existing enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
Chiller Integration (Qty: 1)
• Discover device integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
AHU Integrations (Qty: 7)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 40)
• Discover devices integrated through communications bridge
• Template device data in SC+
NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 503
Building Automation System, Tracer SC+ with Bridge System: (Qty. 1)
• Provide, mount and wire Tracer SC+ with Bridge and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following new equipment:
• (1) SYMBIO500 to replace CHW plant controller.
• Integrate the following existing pieces of equipment:
• (4) Air Handler Units.
• (25) VAV Boxes.
• Provide 3-D graphics of floor plans and each piece of controlled/supervised equipment. All inputs, outputs and setpoints will be displayed on the graphics for ease of operation.
• Provide system programming, startup, and checkout.
• Connect to base wide Trane Ensemble server located in CAFB B 721 for central access. Reuse existing ethernet connections.
Chilled Water Plant Controllers (Qty: 1)
• Label and disconnect all inputs and outputs
• Provide, mount and wire SYMBIO500 controller to replace existing MP580
• Reuse existing enclosure and transformer
• Wire new BACnet/MSTP link from SC+ system controller to SYMBIO500 controller
• Reconnect all inputs and outputs
• Program controller
• Recomission system and verify proper reading from all inputs and outputs
AHU Integrations (Qty: 4)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these will be added to the deficiency list and reported to the base.
VAV Integrations (Qty: 25)
• Discover devices integrated through communications bridge
• Template device data in SC+
• Set up unit programming and graphics
• Confirm proper communication and operation NOTE: If there are devices that are found to have communications issues or sensor level issues, these
BUILDING 544
Building Automation System, Tracer SC+ System: (Qty. 1)
• Provide, mount and wire Tracer SC+ and LON module with licensing for connected equipment.
• Remove existing BCU.
• Provide control as-built drawings and submittals.
• Integrate the following existing equipment:
• (3) Air Handler Units.
• (1) power meter
• (1) bay room…