SOW 903 IPR FY25_Roof Repair updated.doc

DOC document 2 MB Posted

Attached to
San Francisco National Cemetery Repair roof tiles
Solicitation number
36C78625Q0125
Issued by

About this file

This is a Statement of Work (SOW) for roof repair at the San Francisco National Cemetery. The project involves repairing approximately 300 square feet on the east side of the Administrative Office Building, including removing and reinstalling roof tiles, replacing damaged sheathing, and installing new underlayment. The contract requires a 30-calendar day completion timeline from the Notice to Proceed, with work to be performed between 8:00 AM and 4:30 PM, Monday through Friday.

Key requirements include submitting material specifications for approval, protecting existing structures and vegetation, maintaining cemetery operations, and adhering to strict employee conduct standards appropriate for a national shrine. The contractor must coordinate with the Cemetery Director and Contracting Officer's Representative (COR), ensure minimal disruption to burial activities, and provide a one-year warranty on all work. The solicitation is issued by the Department of Veterans Affairs National Cemetery Administration under solicitation number 36C78625Q0125, with contact points including Cemetery Director James Columbia and COR Ronnie Campbell.

View the file

Other files

File Type Posted
36C78625Q0125 - RFQ-ROOF TILES REPAIR SAN FRAN.docx DOCX document
Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

San Francisco National Cemeterry 903-IPR Tile Roof Repair

Scope of Work

San Francisco National Cemetery 1 Lincoln Blvd.

San Francisco, CA 94129

SCHEDULE OF SERVICES:

Contract Line Item
Description
Quantity
Unit
Unit Price
Total Price
0001
Contractor shall Repair an area of approximately

300sq. ft. east side of Administrative Office Bldg.

1. Remove tile from the edge of the gutter up to the hip & ridge.

2. Before the tile is reinstalled, contractor will inspect the area carefully. Any dry rotted or damaged sheathing will be replaced.

3. Install new underlayment (Smooth

Modified Bitumen Membrane).

4. Reinstall the roof tile in the area.

$________
$________

TOTAL PRICE

1. GENERAL SCOPE OF WORK:

The Contractor shall furnish all materials, equipment, labor and supervision necessary to repair east sided of Administrative Office at SFNC. Pictures, contract drawings, and per applicable standards and requirements.

Project Location: San Francisco National Cemetery, 1 Lincoln Blvd, San Francisco, CA 94129.

Completion Time: Thirty (30) calendar days from date of issuance of Notice to Proceed (NTP).

Cemetery Director, James Columbia

TEL: (650) 589-7737

james.columbia2@va.gov COR, Ronnie Campbell

TEL: (650)-589-7737

ronnie.campbell@va.gov

Work in this project includes but is not limited to:

Repair East Side Roof Administrative Office:

1. Contractor shall remove roof tiles intact.

2. Contractor shall install new underlayment membrane replacing damaged sheathing as needed.

3. Contractor shall correctly reinstall tiles and test for any leaks.

4. Parking and staging area: Coordinate with COR.

Dispose of Shipping Containers:

1. Contractor shall remove and dispose of all debris and have area clear of all equipment once completed.

2. Contractor shall not dispose any debris in cemetery trash containers or dumpsters, Contractor shall take all debris off site at their expense.

2. GENERAL REQUIREMENTS

1. The Contractor shall submit sample and technical specifications on all materials being used in this project and shall not proceed with any work prior to approval by the Project Manager/Director and COR.

2. Before beginning any work, the Contractor shall survey the site and examine the drawings and review the scope of work to determine the extent of the work. The Contractor shall take the necessary precautions to avoid damages to existing items to remain in place, to be reused or to remain the property of the Cemetery. Any damaged items shall be repaired or replaced at the Contractors expense as directed by the COR.

3. Establish construction limits, install safety controls, and install construction fencing as approved by the COR.

4. Thoroughly clean up the work area at the end of each day’s work and at completion of the project. Leave premises clean and free of waste, scrap, used equipment or other material intentionally or incidentally delivered to the site by Contractor or Contractor’s personnel.

5. The Contractor shall protect from damage all existing improvements, equipment, structures, facilities, grounds and utilities at or near the work site or adjacent property. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuse to repair the damage promptly.

6. Upon completion of contact, deliver work complete and undamaged. Existing materials, equipment, structures, facilities, grounds and disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in good condition as existed before commencing work.

7. At Contractor’s own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor’s workmen to existing piping and consults, wires, cables, etc., of utility services or of fire protection systems, communication systems (including telephone) which are not scheduled for discontinuance or abandonment.

8. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

9. Thoroughly clean up the work area at the end of each day’s work and at the completion of the project. Leave premises clean and free of waste, scraps, used equipment or other material intentionally or accidentally delivered to the site by the Contractor or Contractor’s personnel.

10. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs and grass) on or adjacent to the work site not to be removed and do not reasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

11. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be made known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in the performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

12. All utilities required for the continuous operation of all existing facilities shall be maintained in service at all times except when disruptions are needed. The contractor shall inform the Cemetery Director and the Contracting Officer (CO) in writing 2 weeks prior to the need shutdown. When the option exists, implement options to minimize interruption of services to the facilities.

13. The Contractor shall coordinate with the Project Manager or COR for parking, material storage, temporary portable restroom facilities and any other needs for the work. Public access to the National Cemetery shall not be impaired.

14. Thoroughly clean up the work area at the end of each day’s work and at completion of the project. Leave premises clean and free of waste, scrap, used equipment or other material intentionally or incidentally delivered to the site by Contractor or Contractor’s personnel.

15. The Contractor shall protect form damage all existing improvements, equipment, structures, facilities, grounds and utilities at or near the work site or adjacent property. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

16. Upon completion of contact, deliver work complete and undamaged. Existing materials, equipment, structures, facilities, grounds and disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in good condition as existed before commencing work.

17. At Contractor’s own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor’s workmen to existing piping and consults, wires, cables, etc., of utility services or of fire protection systems, communication systems (including telephone) which are not scheduled for discontinuance or abandonment.

18. All work will be coordinated with the Contracting Officer’s Representative (COR). Only the Contracting Officer (CO) has the authority to make changes to the contract that affects price and/or time. Work will be conducted in such a manner to minimize the impact on the Cemetery operations.

19. Coordination of Construction with the Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction the construction schedule to cause the least possible interference with Cemetery activities in actual burial areas. Construction noise during the committal services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period.

a. The Contractor is required to discontinue his work efficiently in advance of Easter Sunday, Mother’s Day, Father’s Day, Memorial Day, Veteran’s Day and/or Federal Holidays to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.

b. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the area in a clean, neat condition.

c. Site work will be accomplished between the hours of 8:00 and 4:30, Monday through Friday, except Federal Holiday’s. Work outside of the Cemetery’s normal operating hours of 8:00 am to 4:30 pm shall be permitted on by approval of the COR and to only meet the Period of Performance.

3. STANDARDS OF EMPLOYEE CONDUCT:

1. The National Cemetery Administration honors veterans with a final resting place and lasting memorials that commemorate their service to our Nation. National Cemeteries are national shrines. The standards of work appearance and procedures performed by the Contractor at this cemetery shall reflect this nations concern for those interred there. Due to the sensitive mission of the cemetery and exhibit absolute decorum, composure, and stability all times.

2. Contractor personnel shall be required to adhere to the following standards of dress and conduct, as briefly mentioned here while performing work in the National Cemetery. These standards are enforceable under Title 38, USC, Part 1, Chapter 9, and Section 5901.

3. Clothing shall be presentable and suitable to the work while maintaining proper appearance and decorum indicative for a National Shrine. Uniform shirts and hats are preferred. Clothing shall be clean and cleanliness and personal hygiene are imperative. T-shirts and/or tank tops as outer garments are prohibited. Protective/Safety clothing and shoes shall meet or exceed OSHA and state requirements.

4. Behavior and language must be appropriate, reverent and respectful at all times.

5. Eating and drinking (except water) is prohibited in the work areas and within the sight of a committal shelter during a service.

6. Use of intoxicating beverages, any tobacco products, and illegal drugs on the Cemetery is strictly prohibited.

7. Contractor personnel shall not lean, sit, or stand on or against headstones or monuments. No tools, equipment’s or other items will be placed on or leaned on headstones or monuments.

8. The Contractor shall be responsible for maintaining satisfactory standards of personnel conduct and work performance and shall administer disciplinary action as required. The Contractor is expected to remove any employee(s) from the Cemetery for cause, to include, but not limited to, safety violations, other misconduct in performance of duty under these specifications and/or contrary to the best interest of the Government. If the Contractor fails to act in this regard, or the reason for removal is immediately required to protect the interests of the Government, the COR may direct the removal of an employee from the premises. Contractor objections to any such action will be referred to the Contracting Officer (CO) for final resolution; however, the Contractor will first immediately comply with COR direction pending any CO final resolution at a later date or time. The Contractor will not be due any type of compensation for their costs incurred as a result of an employee being removed for cause; unless the removal is directed by the COR and in later found to be invalid or and/or unreasonable by the Contracting Officer.

9. All work shall be performed in accordance with National, State, and Local Codes including the International Building Code (IBC), the International Mechanical Code (IMC), the International Plumbing Code (IPC), and the National Electrical Code (NEC).

All work shall be performed in accordance with the drawings and specifications. It shall be the Contractor’s responsibility to comply with all the applicable codes. The Contractor shall apply and obtain all applicable permits to comply with local, State and Federal regulations.

4. CONTRACTOR QUALITY CONTROL

1. The Contractor shall guarantee that all work done under this contract shall be free form defaults and no faulty materials or workmanship with one (1) year warranty or extended manufacturer’s warranty. The Contractor hereby agrees to repair or replace deficiencies within the specified time frame by the direction of the Contracting Officer (CO) at the Contractor’s expense. And shall be corrected to the satisfaction of the Government.

2. The Contractor shall provide a Job Site Superintendent who speaks and write fluent English on site, and at all times when Contractor personnel are on the premises. The Job Superintendent will:

a. Review and Approve submittals

b. Inspect the quality of work performed

c. Certify the completed work for payment and other purposes

----END---

5. TECHNICAL EXHIBITS:

· Roof Photos

· Tile Photos

1. SFNC Admin Office East Side where work is required (tarp removed)=300sq ft surface.:

Admin Office with tarp covering east side.

Picture of East side roof with improper laid tile to be removed and re-laid.

Picture of Ridge Cap Tile removed and reset with mortar.