SOW_901CM3043A RNC Site Improvement at Pump Stations.pdf

PDF 3 MB Posted

Attached to
Y1PZ--Site Improvement at Pump Stations Proj # 901CM3043A Riverside Nat'l Cemetery
Solicitation number
36C78624B0002
Issued by

About this file

This document outlines the scope of work for a construction project at Riverside National Cemetery in California. The project involves site improvements at existing pump station sites, including minor demolition, construction of a new retaining wall, and regrading areas. The scope of work calls for providing all labor, materials, tools, equipment, and services to complete the project per the attached construction documents and specifications. Work must be done during the cemetery's normal operating hours and cannot interfere with burial services or events. Environmental and historic compliance requirements are specified. The construction performance schedule sets a deadline of 90 calendar days from notice to proceed. The related federal contract opportunity is a solicitation issued by the Department of Veterans Affairs National Cemetery Administration seeking proposals for the project numbered 901CM3043A at Riverside National Cemetery.

View the file

Other files

File Type Posted
36C78624B0002 0001.docx DOCX document
IFB Lump Sum Division Spreadsheet_RNC Site Improvements.xlsx XLSX spreadsheet
Wage Determination.txt TXT text file
Drawings 901CM3043A RNC Site Improvement at Pump Stations.pdf PDF
36C78624B0002.docx DOCX document
Specs 901CM3043A RNC Site Improvement at Pump Stations.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Invitation For Bid Scope of Work

Riverside National Cemetery, California

Site Improvement at Pump Stations

Project #901CM3043A

Project Scope For Construction

Date: September 2023

Department of Veterans Affairs

National Cemetery Administration

Design and Construction Service

TABLE OF CONTENTS

1. GENERAL

2. PROJECT GOAL

3. STATEMENT OF BID ITEM

4. BACKGROUND

5. OPERATIONAL CONSIDERATIONS

6. ENVIRONMENTAL COMPLIANCE

7. HISTORIC COMPLIANCE

8. PROJECT SCOPE - VA NCA

9. GOVERNMENT PROVIDED CONSTRUCTION DOCUMENT PACKAGE

10. ACCESSIBILITY

11. CONSTRUCTION CRITERIA

12. CONSTRUCTION PERFORMANCE SCHEDULE

1. GENERAL

1.1. This Scope of work (SOW) identifies the goal and objectives of this construction project.

1.2. The construction contractor shall provide all labor, materials, tools and equipment, and services necessary to construct this project per the construction documents and specifications.

1.3. The construction contractor shall be responsible for the quality and completeness of the construction project. Complete and accurate coordination between the trades and quality control of all sub-contractor’s work shall be required.

2. PROJECT GOAL

2.1. RIVERSIDE NATIONAL CEMETERY, Site Improvement at Pump Stations per the construction documents and specifications attached herewith.

3. STATEMENT OF BID ITEM

3.1. The purpose of this project is to improve site condition and provide proper drainage of existing

Pump Station Sites.

3.2. Minor Demolition: Site cleaning and excavation as shown on the Bid Document.

3.3. Construction: Install new retaining wall and regrade area as shown on the Bid Document.

4. BACKGROUND

4.1. Riverside National Cemetery is a cemetery located in Riverside, California, dedicated to the interment of United States military personnel. The cemetery covers 1,250 acres (510 ha), making it the largest cemetery managed by the National Cemetery Administration. It has been the most active cemetery in the system since 2000, based on the number of interments.

5. OPERATIONAL CONSIDERATIONS

5.1. Each national cemetery is managed by VA National Cemetery Administration (NCA) personnel in conformance with national and regional (Pacific District) policies, priorities, goals, and objectives. The functions of a national cemetery include the operation and maintenance of all aspects of the cemetery. Typically, this includes burial of veterans and eligible family members, the interment of cremated remains, and the placement and maintenance of a headstone or grave marker. Cemetery operations include the conduct of Memorial Day and other special ceremonies, as well as the care of graves, structures and grounds. Riverside National Cemetery is operated and maintained by Cemetery staff and operating hours are Monday through Friday, 8:00 am – 4:30 pm. Closed federal holidays except Memorial Day and Veterans Day.

5.2. All work must take place during normal operating hours. Any request to work over these hours must be requested in writing and approved by Cemetery Director in conjunction with COR a minimum of 72 hrs. in advance. Also, the Cemetery hosts numerous ceremonies and events. Work that interferes with these ceremonies will cease during ceremonies. Notice will be provided by the Cemetery staff 5 days in advance of scheduled ceremonies whenever possible. Occasionally events are scheduled with less than 5 days’ notice in which case the Cemetery will provide as much notice as is possible.

5.3. Parking is limited. Construction staff vehicle parking areas are to be coordinated with the

COR and cemetery director. Offsite parking will be required, VA NCA will not reimburse for such parking.

5.4. No smoking inside cemetery grounds.

5.5. Proper attire and professional conduct are required at all times.

5.6. All work must cease during the time an internment is taking place near the construction site. Special care must be taken to accommodate visitors and to ensure work does not interfere with their visit and ensure that there are no safety hazards present.

6. ENVIRONMENTAL COMPLIANCE

6.1. Based upon Department of Veterans Affairs “Environmental Effects of VA Actions,” 38

CFR Part 26, this project is “categorically excluded” from the need for environmental documentation, specifically Section 26.6 of said code paragraph (b)(2).

7. HISTORIC COMPLIANCE

7.1. This project is located at the Riverside National Cemetery, which is listed in the National

Register of Historic Places (NRHP). The proposed scope of work for this project is subject to compliance with Section 106 of the National Historic Preservation Act (P.L. 89-665, as amended). Accurate documentation of the work is required for this project to indicate the protection of cultural landscapes and be compatible with contributing elements within the Cemetery. Work on historic resources must meet the Secretary of the Interiors Standards for the Treatment of Historic Resources.

8. PROJECT SCOPE ‐ VA NCA requires the offeror to submit a detailed price breakdown/cost schedule in the proposal which includes cost detail for each scope of work item, cost schedule line items shall match project performance schedule line items.

9. Government Provided Construction Document Package

9.1. The following construction documents are attached for your use.

Drawings

Specification.

10. Construction Criteria‐ See government provided construction document package, section 9 above.

11. Construction Performance Schedule:

11.1. 90 calendar days from notice to proceed.

Signed by Homayoun Kazemipour, COR -----------------------------------------------------