SOW-63321_ICCPRfcCllRnwDv_751.pdf
PDF 137 KB Posted
- Attached to
- USCGC WAESCHE ELECTRODE REPLACEMENT
- Solicitation number
- 70Z085Q1996
About this file
This Statement of Work (SOW) details a contract for renewing a reference electrode in the Impressed Current Cathodic Protection (ICCP) system for the USCGC WAESCHE at the 10th Ave Marine Terminal in San Diego, CA. The work involves removing and replacing a specific reference electrode (part number 50910-001) located in the Shaft Alley, with precise requirements for removal, installation, cable connection, and operational testing. The contractor must follow specific procedures from the NAVSEA Underwater Ship Husbandry Manual, including measuring electrical potential, assembling components, and verifying system functionality in the presence of a Coast Guard Inspector.
The contract period of performance is 30 JUN 25-03 JUL 25, with an estimated cost of $6,670 for the reference electrode. Key requirements include de-energizing the ICCP system, carefully removing and installing the reference cell, connecting cables to the junction box, and conducting comprehensive operational tests to demonstrate the system's satisfactory condition. The contractor must submit Contractor Furnished Reports (CFRs) at various stages and turn over the removed Reference Electrode Assembly to Coast Guard personnel. The useful life span of each reference cell is expected to be 10 years, with instructions to investigate any premature failures.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
63321_BEC_1024_751
WORK ITEM 1: Impressed Current Cathodic Protection System, Reference Cells, Renew
APM: Do not edit any part of the Work Item Title.
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew the designated impressed current, cathodic protection (ICCP) system reference cells.
APM: Validate all GFP data. If the Spec Package's Consolidated List of GFP is changed, ensure it is changed in the source WI and GFP style is applied.
Edit the table to show the actual components to be renewed. Ensure that referenced work item is also in the availability package. If this is an optional
(contingency) work item, be sure that instructions to offerors are such that two prices are submitted: one for renewing a single reference cell; the other for renewing all of them.
GFP table shows the total number of installed components. Quantities should be reduced to realistic values for most uses of this work item.
1.2 Government-furnished property.
APM: Validate all GFP data. If the Spec Package's Consolidated List of GFP is changed, ensure it is changed in the source WI and GFP style is applied.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
Y Reference Electrode
(US Filter Electrocatalytic
50910-001)
NSN: 6140-01-118-4721 1 ea. 6,670.00
2. REFERENCES
APM: Ensure all references are latest version in CG-LIMS. If editing a WI's
References, change the same ref. in the Spec's Consolidated List of References and contact the SES section chief to change the source WI. Ensure any MS
Word “Comments” and Tracked Changes are removed before uploading the
Spec package or delivering to CPD.
COAST GUARD DRAWINGS
Coast Guard Drawing 750-WMSL-085-019 (ASC085007B), Rev A, Docking Drawing (NSC 2
SRD)
Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements
Coast Guard Drawing 750-WMSL-320-025 (ASC320014), Rev D, Cathodic Protection System
Deck Plan and Elementary Wiring Diagram
Coast Guard Drawing 750-WMSL-633-500 (ASC633001), Rev H, Installation of Cathodic
Protection
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 7140, MAR 2022, REV -, SWBS Group 633, Cathodic
Protection
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Naval Sea Systems Command (NAVSEA) Publication S0600-AA-PRO-190, Underwater Ship
Husbandry Manual, 0910-LP-984-3221, Chapter 19, Cathodic Protection Systems
Naval Sea Systems Command (NAVSEA) Publication S0600-AA-PRO-190, Underwater Ship
Husbandry Manual, 0910-LP-0105-8022, Chapter 20, Painting and Fairing Compounds
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
None.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.1.5 Electrical Isolation. With support from the ship’s crew, ensure ICCP system is de-energized and tagged out until post-repair operational testing is ready to be performed.
3.1.6 At the arrival conference, the Contractor must review with ship’s force (SF) representative the procedure required by UWSH manual, Chapter 19, and clarify the status of preliminary or disassembly procedure steps that ship’s force may already have completed. Then agreement must be documented on whether any uncompleted tasks designated as SF in the procedure will be completed by the Contractor or ship’s force. Submit a CFR.
3.2 Reference cell renewal. The Contractor must renew the reference cells shown in Table 1 in accordance with manufacturer’s guidance found in TP 7140, and procedural requirements of the
NAVSEA Underwater Ship Husbandry Manual (UWSH) Chapter 19, Section 9.
TABLE 1 – REFERENCE CELL RENEWAL LIST
ID FRAME SIDE COMPARTMENT
AFT ZONE RE2 65 Stbd Shaft Alley (5-64-1-Q)
3.2.1 Review and execute preliminary procedures as applicable in accordance with UWSH Manual, Section 19-9.2.1.
3.2.2 Reference Electrode Removal. The Contractor must conduct the procedure for removal of the reference cell in accordance with UWSH Manual, Section 19-9.2.2.
3.2.2.1 Due to ship’s force and SFLC previous troubleshooting efforts, the reference cell components internal to the high-hat cofferdam may already be in a disassembled state. In this case, procedural steps relevant to the internal disassembly of the RE gland assembly in this section may be skipped, but the state of the internal components prior to further disassembly must be documented. Submit a CFR.
3.2.2.2 The cable for the existing cell, if disconnected from the rubber connector which interfaces with the electrode pin, should remain in place until the new cable is ready to be run via the conduit to the junction box one deck above.
3.2.2.3 The Contractor must install the gland blanking plug in accordance with UWSH manual 19-
9.2.2.10. Make report to ship’s force Engineering Department representative when watertight integrity of the is installed in accordance with 19-9.2.2.14 before proceeding further with the removal procedure.
3.2.3 Reference Electrode Installation. The Contractor must conduct the procedure for installation of the new reference electrode in accordance with UWSH Manual, Section 19-9.2.3.
3.2.3.1 In the presence of the Coast Guard Inspector, measure electrical potential of the reference cell in accordance with UWSH Manual, Section 19-9.2.3.20. Satisfactory voltage is between 550 and 650 mV.
Submit a CFR.
3.2.3.2 Assemble the gland assembly in accordance with UWSH Manual, Section 19-9.2.3.21 through 19-
9.2.3.24. Submit a CFR.
3.2.3.2.1 After inserting the connector with cable over the RE pin, when tightening the gland nut, ensure that the cable does not rotate with the gland nut. If rotation occurs, the cable’s connection inside the connector could become damaged, so the cable must be held steady while the nut is tightened.
3.3 Reference Electrode Cable Installation. The Contractor must connect the new reference electrode cable to the existing junction box terminal board in accordance with CG Drawing 750-WMSL-320-025.
3.3.1 The existing cable may be used to assist running of the new cable through the conduit to the connection box on the deck above. Ensure
3.3.2 In presence of the Coast Guard Inspector, measure the electrical potential at the terminal board TB1 in connection box CB-K-CPS-3 relative to ground connection at the CAPAC system DC power supply.
Submit a CFR.
3.3.3 Open the Aft DC power supply, and ensure that cable K-CPS-13 is connected to terminal RE2 at
TB1 in accordance with CG Drawing 750-WMSL-320-025.
3.4 Restoration. With support of ship’s force, clear any tagged-out equipment and reenergize the ICCP system.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.5 Operational tests. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector, in order to demonstrate the ICCP system to be in satisfactory operating condition in accordance with TP 7140. Submit a CFR.
3.6 Mandatory Turn-in Item (MTI) removal. The Contractor must remove and turn over the following
MTI(s) to the Coast Guard PA:
• Reference Electrode Assembly, part number 50910-001.
4. NOTES
4.1 Useful lifespan. The useful life span of each reference cell is expected to be 10 years. If an electrode has failed prematurely, the cause should be investigated and corrected.
Period of Performance: 30JUN25-03JUL25
Location:
10th Ave Marine Terminal
San Diego, CA, 92101
File details come from the government source that posted it. Updated .