This document is a Scope of Work (SOW) for a renovation project at Building 2220 in the Fort Barfoot area. The project will involve the demolition of existing flooring, tile, decking, and steps, followed by the installation of new subfloors, luxury vinyl tile, a new rear porch and steps with railings, and the replacement of porch handrails on the west side of the building. Additionally, the project includes painting the walls in the dining area, kitchen, and porches, as well as electrical upgrades to replace the kitchen and storage area lighting with new LED fixtures.

The contract opportunity, identified as #24-85748, is being offered by the state of Virginia, specifically in Nottoway County. A mandatory pre-bid conference will be held on July 3, 2024, at 10:00 AM in Building 2220. The Point of Contact for the project is Scott Newcomb, who can be reached at 434-292-9162 or Edward.s.newcomb.nfg@army.mil. The SOW provides detailed information on the contractor's responsibilities, including adhering to OSHA safety standards, providing employee personal protective equipment, and ensuring contractor vehicles have current tags and inspections.

View the file

Other files

File Type Posted
IFB-2220 DFAC.pdf PDF
BID FORM for 2220 Dining Facility Repairs.pdf PDF
Vendor eVA Registration Requirements.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW

BLDG 2220

Ft. Barfoot is inviting your company to participate in bidding on the following project intended for 1 building in the 2200 area.

This project will consist of the below listed renovations in 1 building.

Below are the intended renovations that will be expected to be performed within these projects.

Contractor shall provide submittals for all replacement equipment for approval prior to preforming the task.

Demo:

Remove all tile.

Remove all underlayment.

Remove all floor trim.

Remove threshold and retain.

Remove deck and steps on the rear of the building.

Remove the handrails on the porch on the west side of the building.

Construction:

Make repairs to subfloor if necessary. (Up to 100 SqFt) Install moisture barrier in areas to be retiled.

Install new ¼ inch underlayment material (Luan) over moisture barrier and properly secure.

Install new LVT (luxury vinyl tile) using an acceptable adhesive product.

Install new floor molding, caulk all nail holes and paint matching existing trim.

Reinstall thresholds and caulk.

Build new rear porch and steps to include railing.

Replace handrails on west side porch.

Painting:

Prep, prime and paint all walls in the dining area. (1 Primer coat and 2 finish coats) Paint all porches and steps with color matching paint.

Clean, scrape and make minor repairs to the kitchen walls.

Paint all walls in the kitchen with a neutral durable paint.

Kitchen floor:

Clean and fill all cracks in the floor with an acceptable epoxy.

Apply a concrete sealant to the kitchen floor.

Electrical:

Replace all lights in the kitchen and storage areas with 4-foot LED lights. Lights shall be designed for use in a commercial kitchen.

Contractor Responsibilities:

Adhere to all OSHA safety standards.

Provide employees PPE.

Responsible that all personnel have a valid photo ID before attempting to enter the post.

Ensuring that contractor vehicles have current tags and inspection.

Supply construction dumpster.

Cleaning job site at the end of the day.