SOW 2.docx

DOCX document 64 KB Posted

Attached to
USCGC Saginaw Dockside Exhaust Cleaning
Solicitation number
70Z02926QNEWO6034
Issued by

About this file

This is a Statement of Work (SOW) for dockside repairs to the USCGC Saginaw (WLIC 803) scheduled for FY2026. The document specifies three primary work items: cleaning the Main Diesel Engine (MDE) exhaust piping system, cleaning the Ship Service Diesel Generator (SSDG) exhaust piping for units #1 and #2, and cleaning the Boiler exhaust stack uptakes. Each work item requires the contractor to disconnect exhaust piping as necessary, mechanically clean and vacuum all interior surfaces of exhaust pipes, stack uptakes, and mufflers from the exhaust outlet to the topmost external location to remove soot, tar, and all foreign matter. The contractor must reassemble all piping, renew all disturbed flange connection gaskets with high-temperature, non-asbestos gasket materials, and replace all disturbed fasteners.

All work requires the contractor to develop and submit a detailed work plan for Coast Guard approval prior to commencing work, establish appropriate staging, scaffolding, and safety netting in accordance with 29 CFR 1915 requirements, and perform initial and post-repair operational testing in the presence of Coast Guard inspectors. The contractor must document completion through Contractor Field Reports (CFRs) and perform visual inspections of exhaust stack access hatches, cleaned exhaust surfaces, and exhaust expansion joints. All work must comply with Surface Forces Logistics Center Standard Specifications for general requirements, preservation of ship structures, and temporary hull accesses. The contractor must dispose of all debris and cleaning materials in accordance with applicable Federal, state, and local regulations and prepare all new and disturbed surfaces with touch-up preservation coating to match existing adjacent surfaces.

View the file

Other files

File Type Posted
Wage Rates 2015-5189.txt TXT text file
Fixed Price Service FAR - HSAR Clauses.docx DOCX document
Booklet of General Plans.pdf PDF
SOW.docx DOCX document
SF1449.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC SAGINAW (WLIC 803)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2026

Developed By: Erik C Elasik (Rev-1, 18 December 2025)

25901_ESD_0323_FLT

REC_25901_FLT_160 WLIC (ALL) (0323)

WORK ITEM 2: Main Diesel Engine, MDE, Exhaust Piping, Commercial Clean

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the Main Diesel Engine (MDE) exhaust piping system, including the associated stack uptakes.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 160 WLIC 1107-1, Rev L, Dk House Eng Casing & Stacks Coast Guard Drawing 160 WLIC 4105-3, Rev H, Arrgt Eng & Boiler Exhaust Coast Guard Publications Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

Other References Code of Federal Regulations (CFR) Title 29, Part 1915, 2014, Occupational Safety and Health Standards for Shipyard Employment

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3. (Interferences). Known interferences include, but are not limited to the following:

Access covers Exhaust stack

MDE

Piping Pipe insulation Vent ducting Wiring Exhaust pipe expansion joints Exhaust insulation blankets Chaulk Compound

3.2 Staging or scaffolding, netting. The Contractor must erect suitable staging or scaffolding in accordance with 29 CFR 1915, Subpart E (Scaffolds, Ladders and Other Working Surfaces) to facilitate work, as required.

3.2.1 Rig suitable safety netting, to protect workers during possible falls, and to protect the Engine Room and machinery from falling tools.

3.3 Work plan. The Contractor must develop and submit, to the COR, a plan for collecting and disposing of waste extracted during cleaning process. Ensure that the proposed plan must detail how and where exhaust piping will be disconnected, how entire length of exhaust piping will be divided/sectioned for cleaning, and precautions to protect the MDE. The Contractor must perform this work upon receiving Coast Guard approval of the plan.

note Coast Guard personnel will operate all shipboard machinery and equipment.

3.4 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.5 Cleaning. The Contractor must clean the interior surfaces of the exhaust piping and stack uptakes to the MDE, shown on Coast Guard Drawings 160 WLIC 1107-1 and 160 WLIC 4105-3, to a condition free from soot, tar, and any other foreign matter as follows:

3.5.1 Disconnect the exhaust piping as necessary to facilitate cleaning.

3.5.2 Thoroughly sweep, mechanically clean, and vacuum the interior of each exhaust pipe system, including the mufflers, from the exhaust outlet to the topmost location outside the vessel. Clean all adjacent stack uptake surfaces. Ensure that all tar deposits, soot deposits, and all other surface contaminants are removed.

3.5.3 Remove all debris from the pipe surfaces, stack deck, and Engine Room areas by vacuuming. Dispose of all cleaning materials and generated debris in accordance with all applicable Federal, state, and local regulations.

3.5.4 Reassemble exhaust piping; renew all disturbed flange connection gaskets with suitable high temperature, non-asbestos-containing gasket materials; and renew all disturbed fasteners.

3.6 Inspection and report. The Contractor must perform a visual inspection of the following components; submit a CFR:

Exhaust stack access hatches, including all associated studs and nuts.

All cleaned exhaust stack surfaces.

All exhaust expansion joints, including associated bolts.

3.6.1 Following cleaning of the interior of each exhaust pipe system, the Contractor must demonstrate completeness of the cleaning process to the Coast Guard Inspector, showing that the entire length of exhaust piping cleaned according to the work plan.

3.7 Touch-up preservation. The Contractor must prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, (Touch-ups and minor coating repairs.)

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.8 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR

4. NOTES

This section is not applicable to this work item.

25902_ESD_0323_FLT

REC_25902_FLT_160 WLIC (ALL) (0323)

WORK ITEM 3: Ship Service Diesel Generator, SSDG, Exhaust Piping, Commercial Clean

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the exhaust piping system for the following ship service diesel generators (SSDG): #1 SSDG and #2 SSDG of the Ship Service Diesel Generator (SSDG) piping, including the associated stack uptakes.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 160 WLIC 1107-1, Rev L, Dk House Eng Casing & Stacks Coast Guard Drawing 160 WLIC 4105-3, Rev H, Arrgt Eng & Boiler Exhaust Coast Guard Publications Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary Hull Accesses Other References Code of Federal Regulations (CFR) Title 29, Part 1915, 2022, Occupational Safety and Health Standards for Shipyard Employment

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:

Access covers Exhaust stack

SSDG

Vent ducting Wiring Exhaust pipe expansion joints Exhaust insulation blankets Ladder.

Bulkhead heat shielding.

3.2 Staging or scaffolding. The Contractor must erect suitable staging or scaffolding in accordance with 29 CFR 1915, Subpart E (Scaffolds, Ladders and Other Working Surfaces) to facilitate work, as required.

3.3 Safety precaution. The Contractor must rig suitable safety netting, to protect workers during possible falls, and to protect the Engine Room and machinery from falling tools.

3.3.1 Temporary safety railing. To promote safety, the Contractor must limit existing safety railing removals to an area where new safety railing can be installed during the same workday. During periods when not actively working on new safety railing, secure any gaps between existing safety railing with a substantial temporary lifeline arrangement similar to that currently installed on the vessel. Remove and dispose of all temporary lifelines upon completion of work.

3.4 Work plan. The Contractor must develop and submit to the COR, a plan for collecting and disposing of waste extracted during cleaning process. Ensure that the proposed plan must detail how and where exhaust piping will be disconnected, how entire length of exhaust piping will be divided/sectioned for cleaning, and precautions to protect the SSDG. The Contractor must perform this work upon receiving Coast Guard approval of the plan.

note Coast Guard personnel will operate all shipboard machinery and equipment.

3.5 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.6 Cleaning. The Contractor must clean the interior surfaces of the exhaust piping and stack uptakes to the SSDG, shown on Coast Guard Drawing(s) 160 WLIC 1107-1 and 160 WLIC 4105-3, to a condition free from soot, tar, and any other foreign matter as follows:

3.6.1 Disconnect the exhaust piping as necessary to facilitate cleaning.

3.6.2 Thoroughly sweep, mechanically clean, and vacuum the interior of each exhaust pipe system, including the mufflers, from the exhaust outlet to the topmost location outside the vessel. Clean all adjacent stack uptake surfaces. Ensure that all tar deposits, soot deposits, and all other surface contaminants are removed.

3.6.3 Remove all debris from the pipe surfaces, stack deck, and Engine Room areas by vacuuming. Dispose of all cleaning materials and generated debris in accordance with all applicable Federal, state, and local regulations.

3.6.4 Reassemble exhaust piping; renew all disturbed flange connection gaskets with suitable high temperature, non-asbestos-containing gasket materials; and renew all disturbed fasteners.

3.7 Inspection and report. The Contractor must perform a visual inspection of the following components; submit a CFR:

Exhaust stack access hatches, including all associated studs and nuts.

All cleaned exhaust stack surfaces.

All exhaust expansion joints, including associated bolts.

3.7.1 Following cleaning of the interior of each exhaust pipe system, the Contractor must demonstrate completeness of the cleaning process to the Coast Guard Inspector, showing that the entire length of exhaust piping has been cleaned according to the work plan.

3.8 Touch-up preservation. The Contractor must prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, (Touch-ups and minor coating repairs.)

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.9 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR

4. NOTES

This section is not applicable to this work item.

25903_ESD_0924_FLT

REC_25903_FLT_160 WLIC ‘B’ Class (ALL) (0323) WORK ITEM 4: Boiler Exhaust Stack Uptakes, Commercial Clean

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the Boiler exhaust stack uptakes.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 160B-WLIC 4105-3, Rev H, Eng & Boiler Exhaust Coast Guard Drawing 160B-WLIC 103-3, Rev -, Booklet of General Plans Coast Guard Publications Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Other References None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to following:

Access covers.

Exhaust stack.

Boiler.

Exhaust pipe expansion joints.

Exhaust insulation blankets.

3.2 Safety precaution. The Contractor must rig suitable safety netting, to protect workers during possible falls, and to protect the Engine Room and machinery from falling tools.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.3 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.4 Cleaning. The Contractor must clean the interior surfaces of the exhaust piping to the Boiler, shown on Coast Guard Drawing(s) , to a condition free from soot, tar, and any other foreign matter as follows:

3.4.1 Disconnect the exhaust piping as necessary to facilitate cleaning.

3.4.2 Thoroughly sweep, mechanically clean, and vacuum the interior of each exhaust pipe system, including the mufflers, from the exhaust outlet to the topmost location outside the vessel. Ensure that all tar deposits, soot deposits, and all other surface contaminants are completely removed.

3.4.3 Upon completion of cleaning, do the following:

3.4.3.1 Remove all debris from the pipe surfaces, stack deck, and Engine Room areas by vacuuming. Dispose of all cleaning materials and generated debris in accordance with all applicable Federal, state, and local regulations.

3.4.3.2 Reassemble exhaust piping; renew all disturbed flange connection gaskets with suitable high temperature, non-asbestos-containing gasket materials; and renew all disturbed fasteners.

3.5 Inspection and report. The Contractor must perform a visual inspection of the following components; submit a CFR:

Exhaust stack access hatches, including all associated studs and nuts.

All cleaned exhaust stack surfaces.

All exhaust expansion joints, including associated bolts.

3.5.1 Following cleaning of the interior of each uptake, the Contractor must demonstrate completeness of the cleaning process to the Coast Guard Inspector, showing that the entire length of uptake has been satisfactorily cleaned according to the work plan.

3.6 Touch-up preservation. The Contractor must prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs.)

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.7_Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.

4. NOTES

This section is not applicable to this work item.