SOW - 12CG asbestos abatement and attachment -19UK5626Q0047.pdf

PDF 4 MB Posted

Attached to
Asbestos Abatement Project
Solicitation number
19UK5626Q0047
Issued by

About this file

This is a Statement of Work (SOW) for asbestos abatement services at 12 Cresswell Gardens, London, a U.S. Department of State property. The contractor must complete all asbestos removal work within 10 calendar days from the Notice to Proceed, including mobilization, material ordering, execution, site clearance, and snagging. The scope includes asbestos removal from the attic (insulation residue with Chrysotile asbestos rated as medium risk), radiator covers in three rooms (cement panels with Chrysotile, rated very low risk), and the garage. Work must comply with UK Health and Safety Executive regulations and Construction (Design and Management) Regulations 2015, with all contractor personnel requiring security clearance and completing security questionnaires before work commences.

Cost proposals must include a detailed breakdown separating main house and garage costs, with materials and labor itemized for each task: asbestos removal in attic, asbestos removal from radiator covers, asbestos removal from garage, four-stage air clearance testing, and technical deliverables. A four-stage clearance by a UKAS-accredited independent analyst is mandatory, with a Certificate for Reoccupation required upon completion. Contractor submittals include Risk Assessments and Method Statements (RAMS), proof of HSE notification, asbestos waste disposal certificates, and a detailed Gantt chart work schedule. Evaluation criteria require proof of UK business registration, relevant licenses and permits, technician qualifications and three references, Health and Safety certifications, insurance documentation, and completed SF-18 form. Proposals are due to Procurement_Box6@state.gov by August 20 at 5:00 PM. The attached refurbishment survey documents identify specific asbestos locations and quantities requiring removal.

View the file

Other files

File Type Posted
SF-18 Asbestos Abatement - 19UK5626Q0047.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US EMBASSY, LONDON – FACILITY MANAGEMENT

SENSPLITEAIVSEERBEPUOTRTUANNYCDLIASCSRSEIPFAINECDIES TO BARRIOLA@STATE.GOV

SCOPE OF WORK

12 CRESSWELL GARDENS

ASBESTOS ABATEMENT

JUNE 2026

mailto:BARRIOLA@STATE.GOV

SOW – 12 CRESSWELL ASBESTOS ABATEMENT - Page 2 of 12

SENSITIVE BUT UNCLASSIFIED

CONTENTS:

1 Site address

2 General requirements

2.1 Security requirements

2.2 Commencement of the Contract

2.3 Contractor’s personnel certifications

2.4 Access and parking

2.5 Working hours

2.6 Health and safety, welfare and environmental procedures

2.7 Standards of conduct in the premises

2.8 Key control

3 Background and introduction

3.1 Background

3.2 Introduction

4 Specific requirements

4.1 Period of performance

4.2 Cost breakdown requirements

4.3 Submittals

4.4 Special construction and demolition (asbestos)

4.5 Technical deliverables

5 Definitions and acronyms used

ATTACHMENTS:

Att1 – Targeted refurbishment survey by Inspectas (main house) Att2 – Targeted refurbishment survey by Inspectas (garage)

SOW – 12 CRESSWELL ASBESTOS ABATEMENT - Page 3 of 12

1 SITE ADDRESS

12 Cresswell Gardens

LONDON

SW5 0BJ

SOW – 12 CRESSWELL ASBESTOS ABATEMENT - Page 4 of 12

2 GENERAL REQUIREMENTS

2.1 SECURITY REQUIREMENTS

2.1.1 The US Department of State operates strict security procedures for entry into its properties. All the personnel likely to be involved on site at any time during the work shall complete the security questionnaire on the attachment. This form shall be completed and submitted to the Embassy immediately after award along with a photocopy of the employee’s current passport.

2.1.2 The right is reserved to refuse entry to the building at any time. Any decision on this matter shall be final and conclusive and at no additional cost to the US Department of State.

2.1.3 When necessary, contractor employees shall be escorted by security personnel during the performance of their work.

2.1.4 When escorted, a maximum number of 4 contractor employees are allowed per escort. If the contractor estimates that more than 4 employees are required or if the work needs to be done simultaneously in separate areas of the building, this needs to be notified to the Embassy at least 7 days in advance, so adequate escort resources can be mobilized.

2.1.5 The US Department of State reserves the right to request additional information in certain cases.

2.1.6 The contractor’s employees must work only within areas relevant to the equipment they are responsible for maintaining. No contractor’s personnel shall wander outside these areas without prior approval.

2.2 COMMENCEMENT OF THE CONTRACT

2.2.1 No work shall start or equipment and materials be ordered until the contractor has received a purchase order for the works stating the start date and the end date of the contract.

2.2.2 The Contractor shall designate a representative person who shall supervise the Contractor's employees and be the Contractor's liaison with the U.S. Government.

The Contractor's employees shall be on-site only for contractual duties and not for any other business or purposes. Contractor employees shall have access to

SOW – 12 CRESSWELL ASBESTOS ABATEMENT - Page 5 of 12 the relevant rooms, either with or without security escorts, only with specific permission by either the Facility Manager or the COR.

2.3 CONTRACTOR’S PERSONNEL CERTIFICATIONS.

2.3.1 It is the contractor’s responsibility to ensure that their employees are competently qualified, trained and certified to work on all specialist equipment or materials named within this document and attachments

2.3.2 The contractor shall proceed to provide proof of competency of all his operatives, including, but not limited to, qualifications, certifications, training and experience on similar work in other locations.

2.4 ACCESS AND PARKING

2.4.1 The contractor is responsible for providing the COR with operatives’ names, vehicle registration plate number, make and colour, and any other details relevant to the work on site (i.e. deliveries expected) with at least 24 hours in advance.

2.4.2 The contractor is advised that a maximum of one parking space is available.

However, the US Government may not be able to provide parking on certain occasions.

2.5 WORKING HOURS

2.5.1 Unless prior arrangement the work shall be undertaken on weekdays (Monday to

Friday) and during working hours (8am to 5pm)

2.5.2 No work shall be undertaken on local and American holidays unless prior agreement and at no addition costs to the US Department of State. Please refer to the London embassy website for observed local and American holidays.

2.6 HEALTH AND SAFETY, WELFARE AND ENVIRONMENTAL PROCEDURES

2.6.1 The contractor shall fully comply with the Construction (Design and Management)

Regulations (CDM 2015).

SOW – 12 CRESSWELL ASBESTOS ABATEMENT - Page 6 of 12

2.6.2 The contractor shall provide the COR with all sites specific Risk Assessments and Method Statements (RAMS) after award and prior to commencement of works.

The notice to proceed cannot be used

2.6.3 After surveying the facilities and the relevant equipment, the contractor shall inform the US Government of any health and safety concerns or special requirements so their work can be carried out safely. This information will have to be included in the contractor’s cost proposal.

2.6.4 It is the contractor’s responsibility to ensure that all their employees are equipped with certified safety equipment (PPE) to complete the tasks as requested within this document and provided attachments, and in accordance with the contractor’s method statements and health & safety plan.

2.6.5 The COR shall inform the contractor of the Embassy Health & Safety procedures to include but not be limited to egress routes, exits and assembly points in the event of an emergency.

2.6.6 Restrooms and welfare facilities are available for the use of the contractor at the US Consulate building.

2.6.7 The contractor shall be responsible for the safe and environmentally friendly disposal of all redundant materials, parts and consumables. Safe disposal records copies shall be provided to the Embassy after each visit.

2.6.8 All work shall comply with the local Health and Safety regulations in the UK. The link to the website is www.hse.gov.uk

2.7 STANDARDS OF CONDUCT IN THE PREMISES

2.7.1 The contractor employees shall maintain satisfactory standards of competency, conduct and cleanliness when working within a US Government property. These standards are especially strict when working within office environments or when working in or accessing adjacent areas.

2.7.2 The Government reserves the right to ask the contractor employee to leave the premises when the above is not complied with or the employee is deemed disruptive. The contractor shall immediately replace such an employee to maintain continuity of services at no additional cost for the Government.

2.7.3 The Contractor's employees shall wear clean, tidy and complete uniforms with clear means of identification when on duty.

http://www.hse.gov.uk/

SOW – 12 CRESSWELL ASBESTOS ABATEMENT - Page 7 of 12

2.7.4 The contractor employees must not smoke outside the designated areas, play music in any part of the premises or use abusive or loud language at any time within the US Consulate boundaries.

2.8 KEY CONTROL

2.8.1 The Contractor shall not depart the Consulate grounds whilst in possession of any keys. All keys shall be controlled and given back to the Consulate designated person prior to leaving the premises. However, if the contractor or their employees depart the building without giving keys back, the contractor may be responsible for the costs of as a minimum: gaining entry through locked doors or gates, repairs, replacing locks and providing additional keys.

SOW – 12 CRESSWELL ASBESTOS ABATEMENT - Page 8 of 12

3 BACKGROUND AND INTRODUCTION

3.1 BACKGROUND

12 Cresswell Gardens is an end of terrace house located in The Royal Borough of

Kensington and Chelsea and within the conservation area known as The Boltons.

This property’s roof went through an extensive waterproof and thermal upgrade in

2023. In addition, a refurbishment survey was undertaken, and asbestos material was identified in various locations including the main house and the garage as described on the attached documents.

3.2 INTRODUCTION

This document is issued by the US Department of State with the purpose to enter a contract to undertake all the work to the residence known as 12 Cresswell Gardens as described herein. This includes the main house and the garage.

The contractor shall provide all necessary managerial, administrative and direct labour personnel as well as supply, deliver and install all the materials, provide all the access equipment, tools and permits and the warranty to undertake the work explained here

in. The contractor is also responsible for making good of all the elements disrupted during the above works, to safely dispose of all the redundant materials and equipment generated, clear, clean and tidy up the site daily and professionally clean the site at the end of the project.

The contractor shall supply a proposed work schedule presented in the form of a Gantt chart (Microsoft Project is preferable), including a complete breakdown of all the tasks, indicating commencement and completion of the entire project. This shall be included in the bid proposals.

SOW – 12 CRESSWELL ASBESTOS ABATEMENT - Page 9 of 12

4 SPECIFIC REQUIREMENTS

To be read in conjunction with the attachments provided.

4.1 PERIOD OF PERFORMANCE

4.1.1 The contractor shall complete the work described in no longer than 10 calendar days (2 weeks) from the day stated in the NTP (notice to proceed). This time includes all the mobilization, ordering and delivering of materials, preparation, execution, commissioning and clearing and cleaning the site and completion of the snagging. If there is any notification time for the local authorities this shall be requested and completed in a timely manner by the contractor in advance to the start day on site (to be confirmed).

4.1.2 The Gantt chart shall include every task from NTP till completion.

4.2 COST BREAKDOWN REQUIREMENTS

4.2.1 As part of the cost proposal, the contractor shall include a cost breakdown to follow the structure below. Each item shall include the amounts correspondent to the main house work and the amount correspondent to the garage. In addition, each sub-item shall indicate both the materials cost and the labour cost.

4.2.1.1 Asbestos removal in attic

4.2.1.2 Asbestos removal from radiator covers

4.2.1.3 Asbestos removal from garage

4.2.1.4 Air tests (four-stage clearance)

4.2.1.5 Technical deliverables

4.3 SUBMITTALS

4.3.1 At the relevant time, the contractor shall submit to the COR proof of notification to the HSE and any other documents required by the local authorities.

SOW – 12 CRESSWELL ASBESTOS ABATEMENT - Page 10 of 12

4.4 SPECIAL CONSTRUCTION AND DEMOLITION (ASBESTOS)

4.4.1 Mobilization

4.4.1.1 An asbestos survey for the main house was undertaken in 2023 and it is provided.

The contractor shall base their abatement proposal on the survey report. See attachment 1.

4.4.1.2 An asbestos survey for the contiguous garage was undertaken in 2025 and it is provided. Since this garage was built at the same time it is assumed that the same construction methods and materials were used and therefore asbestos is also present. The contractor shall base their abatement proposal on this survey report.

See attachment 2.

4.4.1.3 The contractor shall inform the embassy of all the notification period required by the Health Executive and include this in the Gannt chart program.

4.4.1.4 Make good the disturbed parts of the building.

4.4.2 Asbestos abatement

4.4.2.1 An asbestos specialist contractor shall abate all the asbestos identified or in both reports.

4.4.2.2 Regarding the 2025 survey undertaken for number 10, the contractor shall remove all the asbestos identified or presumed on the “asbestos register” page.

4.4.2.3 The asbestos waste certificates shall be provided in a timely manner.

4.4.3 Four-stage clearance

4.4.3.1 A four-stage clearance must be undertaken at the completion of the abatement by an independent and qualified analyst. A UKAS-accredited organization must be used for the four-stage clearance procedure. A Certificate for Reoccupation must be issued by the analyst to the COR in a timely manner.

4.5 TECHNICAL DELIVERABLES

4.5.1.1 Prepare and submit one electronic copy of the following within two days of abatement completion. To include:

Description of work undertaken.

Asbestos waste disposal certificates.

A certificate for Reoccupation.

SOW – 12 CRESSWELL ASBESTOS ABATEMENT - Page 11 of 12

4.6 EVALUATION CRITERIA

In order for a quotation to be considered, the vendor must provide:

4.6.1 Proof of licenses and permits required by local law (see DOSAR 652.242-73 in Section

2). If the offeror already possesses the locally required licenses and permits, a copy shall be provided.

4.6.2 Evidence of the technicians’ training, qualifications, experience and expertise in providing asbestos removal services

4.6.3 Proof of demonstrable experience in undertaking similar projects including three (3) references

4.6.4 Detailed description of their experience with asbestos removal

4.6.5 Proof of Health and Safety regulations and certifications required.

4.6.6 Proof of all insurance (such as public and employer’s liability) and accreditation as may be required under applicable UK law. A copy of the certification of insurance or a statement that the contractor will get the required insurance, and the name of the insurance provider to be used.

4.6.7 Vendors must provide evidence that the offeror/quoter operates an established business with a permanent address and telephone listing in the United Kingdom that can be confirmed on Companies House.

4.6.8 A signed & completed SF-18

4.6.9 If sub-contracting out the work, provide documentation demonstrating an established sub-contractor relationship with the proposed vendor for the past 3 years and evidence of payment of services rendered under prior contracts.

4.6.10 Supply a proposed work schedule presented in the form of a Gantt chart (Microsoft Project is preferable), including a complete breakdown of all the tasks, indicating commencement and completion of the entire project.

4.6.11 Submit quote to Procurement_Box6@state.gov no later than August 20, by 5:00 PM.

mailto:Procurement_Box6@state.gov

SOW – 12 CRESSWELL ASBESTOS ABATEMENT - Page 12 of 12

5 DEFINITIONS AND ACRONYMS USED

US DOS. Department of State of the United States of America.

OBO. Bureau of Overseas Buildings Operations. This is the department that directs the worldwide overseas building program for the Department of State.

CO. Contracting officer. A person in the US DOS with the authority to enter, administer and/or terminate contracts and make related determinations and findings.

COR. Contracting officer representative. A person in the US DOS who is responsible for the technical direction and evaluation of the contractor performance.

CDM. Construction Design and Management regulations. UK Construction (Design and

Management) regulations intended to improve the overall management and coordination of health and safety and welfare throughout all stages of a construction project.

Issue No: 1 Refurbishment Survey Issue Date: 11 Aug 2023 Issued By: Craig Candlish

Page 1 of 36 J023101

Targeted Refurbishment Survey

12 Creswell Gardens London

Inspectas Compliance Ltd Head Office: Atlas House, 5 Bradford Road, Drighlington, BD11 1AS Suite 19 Caxton Point, Caxton Way, Stevenage, Hertfordshire SG1 2XU E info@inspectas.co.uk W inspectas.co.uk T 0844 264 0094 mailto:info@inspectas.co.uk

Issue No: 1 Issue Date: 11 Aug 2023 Issued By: Craig Candlish Refurbishment Survey

Page 2 of 36 J023101

Contents

1. Executive Summary [Conclusions and actions]

2. Contract Review

3. Introduction - Purpose, Aims and Objectives

4. Desk Top Review and Survey Planning

5. Survey Method

6. Exclusions and Caveats

7. Sampling and Analysis

8. Survey Results - Interpretation

9. Recommendations

*This report shall not be reproduced except in its entirety

Contents:

Appendix 5 - Plans

Appendix 4 - Analysis Certificates

Appendix 3 - General Building Construction by location

Appendix 2 - Survey Data Sheet

Appendix 1 - Asbestos Register - Results

APPENDICES - Survey Results

Page 3 of 36 J023101

HIGH RISK MATERIALS - SCORES 10+

Building Floor Room Item Material Risk assessment Score

Recommendations

There were no high risk items found.

MEDIUM RISK MATERIALS - SCORES 7-9

Asbestos containing materials, which have been identified as unsealed or damaged are listed in the table below. It is recommended that remedial work to seal or remove these materials is undertaken as a priority and that air monitoring is carried out within adjacent areas in order to assess airborne fibre levels.

Score

Recommendations

12 Creswell Gardens

Roof Void

Loft Space R/001

Insulation residue lining structural timbers surrouding pipework

Asbestos Insulating Board

MEDIUM (9) Restrict access/remove

1.0 Executive summary:

Page 4 of 36 J023101

LOW RISK MATERIALS - SCORES 1-6

Asbestos Containing Materials which have been identified in good condition are located in the table below. A management policy and plan needs to be implemented to ensure the ongoing safe management of these products and regular inspection of these products by suitably trained personnel is recommended.

Score

Recommendations

12 Creswell Gardens

2nd Bedroom 2/003 Cement panel lining underside of timber radiator boxing

Asbestos Cement VERY LOW (4) Remove

12 Creswell Gardens

1st Living Room 1/003

Cement panel lining underside of timber radiator boxing

Asbestos Cement VERY LOW (4) Remove

12 Creswell Gardens

Ground Dining Room G/001

Cement panel lining underside of timber radiator boxing

Asbestos Cement VERY LOW (4) Remove

Page 5 of 36 J023101

PRESUMED ASBESTOS/NO ACCESS AREA

Building Floor Room/Area Recommendation There were no results found.

Surveyor Site Notes:

Internal notes: N/A

External notes: N/A

Page 6 of 36 J023101

Name and address of site: 12 Creswell Gardens, London, SW5 0BJ

Name and address of client: T & D Barrs,Unit 7 Thundridge Business Park, Thundridge, Nr. Ware, Hertfordshire, SG12 0SS

Client contact: Alison Temple

Type of survey: Refurbishment Survey

Date of survey: 7 Aug 2023

Project Number: J023101

Lead surveyor[s]: John Arnold Signature:

Technically reviewed by: Craig Candlish Signature:

Report issue date: 11 Aug 2023

Report QC Check Introduction to report covers all areas requested by the client Yes Conclusions and recommendations are appropriate Yes

All data and MA checks are correct, including material type Yes Bulk Certificate present Yes

Exec. Summary accurate and complete by risk band Yes Plans marked correctly and present and no access areas identified appropriately Yes

Have any ACM’s have been omitted from the report No Caveats are specific to the survey Yes

2.0 Contract Review:

Page 7 of 36 J023101

Inspectas Compliance Ltd received an order of confirmation to undertake a Refurbishment Survey from T & D Barrs. This order has been accepted on the basis of the original quotation and our terms and conditions of business.

The order relates to a Refurbishment Survey of:

Site Address Building Designation Building Description Age of building

London

12 Creswell Gardens Residential Circa 1900s

General Building Construction Type *Individual room construction can be found within Appendix 3 of this report

Three storey brick building

The survey was carried out by John Arnold.

The Type of survey selected / requested by the client was a Refurbishment Survey.

The reason for selecting this survey is to enable the client to identify asbestos in his premises so that it can be removed prior to major refurbishment

This survey was carried out in accordance with documented in house procedures, which are based on the HSE Guidance document HSG 264.

Purpose of Survey

The purpose of this Major Refurbishment Survey is to help the duty holder identify asbestos in these premises, prior to major refurbishment. It provides sufficient information to help the tendering process for removal works prior to any work starting. However it is strongly recommended that any asbestos removal should be undertaken against a detailed specification. We further recommend the appointed removal contractor should attend the site to confirm for themselves the quantities and location of asbestos to be removed, prior to costing.

Aim of Survey

The aim of the survey was to;

1. Locate and record the location, extent, and product type as far as reasonably practicable of known or presumed ACM’s.

2. Inspect and record information on the accessibility, condition and surface treatment of know or presumed ACM’s

3. Determine and record the asbestos type based on sampling or by making a presumption based on product type and appearance

4. Locate all ACM's within the fabric of the building prior to refurbishment.

3.0 Introduction/Objectives:

Page 8 of 36 J023101

3.4 Type of Survey – Refurbishment Survey

The purpose of this major refurbishment survey is to identify ACM’s to be removed prior to any major refurbishment work being carried out. This type of survey is used to locate and describe as far as is reasonably practicable all ACM’s in the whole building if major refurbishment is planned.

Major refurbishment surveys are intended to locate all asbestos within the building. It is a disruptive, fully intrusive survey that involves destructive inspection techniques that penetrate the building structure extensively. This involves breaking into floors, through walls, into wall voids ceilings, cladding, boxing, as necessary to gain access to all areas, including the inner fabric of the building. A full sampling programme is undertaken to identify possible ACM's and estimate their quantities.

The survey is designed to be used to help the tendering process, and should be used to start generating a specification for tendering the removal of ACM’s from the building prior to major refurbishment.

Whilst all asbestos materials have been identified as far as is reasonably practicable, some asbestos materials may remain unidentified buried within the fabric of the building during the survey. Asbestos shuttering buried within concrete slabs, asbestos hidden by structural supports, asbestos hidden behind other asbestos products, and building structures which are unsafe to fully access are potential locations.

It must be presumed that asbestos may remain unidentified to these type of areas and if suspect materials are uncovered during major refurbishment then samples should be taken for analysis.

3.0 Introduction/Objectives(Cont):

- Type of Survey

Page 9 of 36 J023101

4.1 Details of information requested from the Duty Holder by Inspectas Compliance Ltd in order to carry out a desk top review and plan the survey in accordance with HSG 264 were recorded on our pre-survey questionnaire, along with details of all the information that were provided by Alison Temple on behalf of the client.

The Information provided was assessed during the desktop review and a survey plan, and risk assessment was produced for the survey of:

The survey was carried out to Refurbishment survey to property prior to interior decoration works and roofing works. Limited intrusive inspections made as not all areas of the building are being disturbed. .

Where information was provided regarding the presence of known or presumed asbestos materials then this has been validated during the course of the survey, and recorded within this report.

Detailed drawing were not provided by the client at the time of the survey.

A decontamination unit was not needed onsite during the survey.

Utilities and services were still live at the time of the survey.

Access equipment for working at heights was not required.

The survey did not involve confined space working.

The client did not inform Inspectas of any chemical/biological hazards.

No previous asbestos information was made available to Inspectas prior to survey works.

The following exclusions were agreed at the time of the survey on site:

No exclusions agreed

4.0 Desk Top Review and Survey Planning:

Page 10 of 36 J023101

This survey has been undertaken in accordance with HSG264 and Inspectas Compliance Ltd in house procedures.

Clients of Inspectas Compliance Ltd that have signed our terms and conditions are deemed to have agreed, and accepted, our surveying approach, our sampling strategy, and our standard planning, surveying and reporting format unless they have made specific requests to the contrary.

The information provided by the client or their representative are recorded in the planning document and has been used to define the scope of the survey.

Photographs of suspected ACM's will be taken at the time of the survey unless the client expressly requests otherwise. Sampling points and suspected ACM's will not be identified with labels unless the client expressly requests otherwise.

All fibrous materials and item will be included in the survey unless, in the surveyors professional opinion, these items can be excluded (eg. Wood, wallpaper, man-made mineral fibre). Samples of all thermoplastic floor coverings will be taken unless, in the surveyors professional opinion, such items can be excluded. All textured coatings and novel bituminous will be sampled.

Areas that could not be accessed were presumed to have ACM's present until proven otherwise. Each area requiring further inspection is documented within the Executive summary (Inaccessible areas). Inaccessible areas are also shown on the plan drawings (Appendix 5)

Materials that could not be accessed and in the surveyors opinion can be dismissed will be presumed to be ACM unless proven otherwise. Materials that are not sampled but, in the surveyors opinion, have a similar appearance, location and function as a previously sampled material will be strongly presumed to be similar to the sampled material.

The quantity of samples taken may have been minimised by using 'strongly presumed' as defined above. Materials that are 'strongly presumed' to be similar to a material that has already been sampled will be recorded in the comments section of the survey and referenced against the original sampled material.

Intrusive damage that is required to gain access to an area/location that is within the scope of the survey has been agreed with the client or the clients representative. Any control measures will be put in place before such action is attempted. If control measures cannot be arranged, no attempt to access the area will be made and the reasons recorded. The area/location will be presumed to have ACM's present until proven otherwise.

Non fibrous materials and item known not to contain asbestos (eg Breeze block, plaster, plasterboard plastics and non textured paints) will be excluded from the survey unless the surveyor suspects that these materials have been contaminated with asbestos from other sources or specifically requested by the client.

Older electrical equipment, which cannot be shown to contain ACM's, has been presumed to have ACM's present unless, in the surveyors professional opinion, such items can be excluded.

5.0 Survey Method

Page 11 of 36 J023101

6.1 For safety reasons it is not possible to inspect internal areas of plant and machinery.

During the course of the survey any areas not accessed, are detailed within the Data Sheets of this report, along with a comment on the reason for non access. Asbestos has been presumed to be present until further inspection and sampling to these areas proves otherwise

Residual asbestos material may be present beneath re-lagged services and cannot be detected unless the re-lagging is systematically removed. Caution should therefore be taken when working on such materials for the potential presence of asbestos residue.

Textured Coatings such as “Artex” may contain a trace quantity of Chrysotile asbestos. Due to this low asbestos content, applications of this product may be non-homogenous and may elicit both positive and negative samples. Where both positive and negative samples are obtained the client should presume that the textured coating contains Chrysotile throughout even though a non-detected result has been obtained.

This report does not include investigations into land contamination associated with asbestos or any other contaminant.

6.2 – Specific caveats

It was agreed with the client that access above or behind known ACM’s was not required within the survey.

It was agreed with the client that core boring into the concrete slabs was not required within the survey.

The client was advised that destructive inspection will involve that removal of a number of windows, which will be required making secure during/after the survey. The client has requested a less intrusive survey into these areas and for the window frames to remain in situ.

Underground services were not included in the survey.

It has been agreed with the client that there was not any unsafe structures on site.

6.0 Exclusions and Caveats:

Page 12 of 36 J023101

7.1 The object of bulk sampling is to identify the nature and extent of any visible ACM.

7.2 Bulk sampling is undertaken inline with the recognised safe procedures in order to cause minimal possible nuisance and potential risk to health of the building occupants and visitors. Bulk samples are taken in accordance with documented in house procedures, following guidelines detailed in HSG264 'The Survey Guide' and HSG248 'The Analyst Guide'. The quantity of samples taken will be minimised by using 'strongly presumed'. Materials that are 'strongly presumed ‘to be similar to a material that has already been sampled will be recorded in the comments section of the survey record and referenced against the original sampled material.

7.3 Bulk samples are returned to the appointed bulk analysis laboratory with the appropriate sample / report reference number. Where appropriate; a label will be left on site adjacent to the sample location.

7.4 The label will indicate the sample number and the date taken. This label can be used along with the report for cross reference purposes.

7.5 Bulk sample analysis is carried out in accordance with HSE document HSG 248 ‘The Analysts Guide’ . Samples are examined under a low magnification stereomicroscope and the fibres teased apart. The fibres are then mounted in liquids of known refractive indices and examined under high magnification using polarised light and dispersion staining in accordance with HSG 248 ‘The Analysts Guide’.

7.6 The bulk sample description and analysis results can be found in Appendix 4 of this report – The analysis certificate.

Key to Analysis Results:

Chrysotile - White Asbestos

Amosite - Brown Asbestos

Crocidolite - Blue Asbestos

Tremolite - Rare Asbestos

Actinolite - Rare Asbestos

Anthophyllite - Rare Asbestos

7.0 Sampling and Analysis:

Page 13 of 36 J023101

Survey Results

8.1 The results of the survey inspections and sampling undertaken are recorded on the enclosed Survey Data Sheets (appendix 2), Asbestos Register (appendix 1) and General Building Construction by location (Appendix 3). Where asbestos containing material have been identified or presumed to be present then a Material Assessment Algorithm has been calculated as detailed in HSG 264 and reproduced in the table below:

8.2 Within the survey data sheets the individual scores in brackets, for each sample variable, are added together to form the final material risk assessment algorithm score.

8.3 The non asbestos general building construction materials identified by visual inspection are recorded in Appendix 3: General Building Construction. These items have not been sampled and consist of, non fibrous materials EG) Masonry, timber etc and fibrous materials that have not contained asbestos. EG) MMMF, plasterboard etc.

8.4 Suspected materials that were subject to bulk sampling which were confirmed as non asbestos are recorded individually within the survey data sheets: Appendix 1.

8.0 Survey Results - Interpretation:

Page 14 of 36 J023101

Material Risk Assessment Algorithm

Product type [or debris from product] Score Examples of scores

1 Asbestos reinforced composites [plastics, resins, mastics, roofing felts, vinyl floor tiles, semi- rigid paint, decorative finishes and asbestos cement etc]

2 Asbestos insulating board, mill boards, other low-density boards, textiles, gaskets, ropes and woven materials and asbestos paper.

3 Thermal insulation [e.g. pipe and boiler lagging], sprayed asbestos, loose asbestos, asbestos mattresses and packing.

Extent of damage/deterioration Score Examples of scores

0 Good condition: no visible damage

1 Low damage: a few scratches or surface marks, broken edges on boards or tiles, etc.

2 Moderate damage: significant breakage of materials or several small areas where material has been damaged exposing fibrous edges.

3 High damage or deterioration of materials, sprays and thermal insulation. Visible asbestos contamination by debris or residues.

Surface treatment Score Examples of scores

0 Composite materials containing asbestos, reinforced plastics, resins, vinyl tiles

1 Enclosed sprays or insulation, AIB [with exposed face encapsulated], cement sheets, etc.

2 Unsealed AIB, encapsulated insulation and sprays.

3 Unsealed insulation and sprays.

Asbestos Type Score Examples of scores

1 Chrysotile

2 Amphibole asbestos (excluding Crocidolite)

3 Crocidolite

8.0 Survey Results - Interpretation (cont):

Page 15 of 36 J023101

Material Risk Assessment Score

Risk Category Risk Score Range Fibre release potential

A HIGH 10 and above High risk with a high potential to release fibres if disturbed

B MEDIUM Between 7 and 9 Medium risk with a medium potential to release fibres if disturbed

C LOW Between 5 and 6 Low risk with and having low potential to release fibres if disturbed

D VERY LOW 4 and below Very low risk with and having very low potential to release fibres if disturbed

Page 16 of 36 J023101

Appendix 1 - Asbestos Register

Building Floor Location - Room - Item S,P,SP,AS

Sample No

Product Type

Condition Surface Treatment

Asbestos Type

Quantity Accessibility Material Score

Recommendation Surveyors Comments

Creswell Gardens

Roof Void

Loft Space - R/001 - Insulation residue lining structural timbers surrouding pipework

S

FK001067

Asbestos Insulating Board

High Damage

Unsealed lagging and sprays

Chrysotile 5lm Easily disturbed

9 Restrict access/remove

N/A

Creswell Gardens

2nd Bedroom - 2/003 - Cement panel lining underside of timber radiator boxing

S

FK001065

Asbestos Cement

Low Damage

Surface Sealed Chrysotile 2lm Easily disturbed

4 Remove N/A

Creswell Gardens

1st Living Room - 1/003 - Cement panel lining underside of timber radiator boxing

S

FK001063

Asbestos Cement

Low Damage

Surface Sealed Chrysotile 4lm Easily disturbed

4 Remove N/A

Creswell Gardens

Ground Dining Room - G/001 - Cement panel lining underside of timber radiator boxing

S

FK001061

Asbestos Cement

Low Damage

Surface Sealed Chrysotile 2lm Easily disturbed

4 Remove N/A

KEY:

S – Sampled, P – Presumed, SP – Strongly Presumed, AS – Cross reference to former sample

Page 17 of 36 J023101

Appendix 2 – Survey Data Sheets

Service Type Refurbishment Survey Report Revision Number 1 Surveyors John Arnold Project Number J023101 Survey Date 7 Aug 2023 Site Address: 12 Creswell Gardens

London

SW5 0BJ

Bulk Analysis Laboratory Asbestos Laboratory Services (UK) Ltd

Date Samples taken 07/08/2023

Page 18 of 36 J023101

Survey Date: Lead Surveyor Survey Type Floor Analysis

7 Aug 2023 John Arnold Refurbishment Survey Roof Void Chrysotile (1)

Building Room Item Quantity

12 Creswell Gardens Loft Space - R/001 Insulation residue lining structural timbers surrouding pipework

5lm

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

S

FK001067

Asbestos Insulating Board (2)

Unsealed lagging and sprays (3)

High Damage (3) Easily disturbed

Material Risk Score

Recommended action Restrict access/remove

Surveyor comments N/A

7 Aug 2023 John Arnold Refurbishment Survey 2nd Floor N/A

Building Room Item Quantity

12 Creswell Gardens Bathroom - 2/001 No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

Recommended action No further action required

Surveyor comments N/A

Survey Data Sheets (cont)

Page 19 of 36 J023101

Building Room Item Quantity

12 Creswell Gardens Bedroom - 2/002 No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

Recommended action No further action required

7 Aug 2023 John Arnold Refurbishment Survey 2nd Floor Chrysotile (1)

Building Room Item Quantity

12 Creswell Gardens Bedroom - 2/003 Cement panel lining underside of timber radiator boxing

2lm

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

S

FK001065

Asbestos Cement (1) Surface Sealed (1) Low Damage (1) Easily disturbed

Material Risk Score

Recommended action Remove

Surveyor comments N/A

Page 20 of 36 J023101

Building Room Item Quantity

12 Creswell Gardens Bedroom - 2/004 No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

7 Aug 2023 John Arnold Refurbishment Survey 2nd Floor No Asbestos Detected (0)

Building Room Item Quantity

12 Creswell Gardens Stairs and Landing - 2/005

Insulating board panel lining cupboard door

2m²

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

S

FK001066

Insulating Board (2) N/A N/A N/A

Material Risk Score

N/A

Recommended action No further action required

Surveyor comments N/A

Page 21 of 36 J023101

7 Aug 2023 John Arnold Refurbishment Survey 1st Floor N/A

Building Room Item Quantity

12 Creswell Gardens Bathroom - 1/001 No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

7 Aug 2023 John Arnold Refurbishment Survey 1st Floor N/A

Building Room Item Quantity

12 Creswell Gardens Bedroom - 1/002 No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

Recommended action No further action required

Surveyor comments N/A

Page 22 of 36 J023101

7 Aug 2023 John Arnold Refurbishment Survey 1st Floor Chrysotile (1)

Building Room Item Quantity

12 Creswell Gardens Living Room - 1/003 Cement panel lining underside of timber radiator boxing

4lm

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

S

FK001063

Asbestos Cement (1) Surface Sealed (1) Low Damage (1) Easily disturbed

Material Risk Score

Recommended action Remove

7 Aug 2023 John Arnold Refurbishment Survey 1st Floor No Asbestos Detected (0)

Building Room Item Quantity

12 Creswell Gardens Stairs and Landing - 1/004

Insulating board panel lining cupboard door

2m²

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

S

FK001064

Insulating Board (2) N/A N/A N/A

Material Risk Score

N/A

Recommended action No further action required

Surveyor comments N/A

Page 23 of 36 J023101

7 Aug 2023 John Arnold Refurbishment Survey Ground Floor Chrysotile (1)

Building Room Item Quantity

12 Creswell Gardens Dining Room - G/001 Cement panel lining underside of timber radiator boxing

2lm

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

S

FK001061

Asbestos Cement (1) Surface Sealed (1) Low Damage (1) Easily disturbed

Material Risk Score

Recommended action Remove

7 Aug 2023 John Arnold Refurbishment Survey Ground Floor N/A

Building Room Item Quantity

12 Creswell Gardens Kitchen - G/002 No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

Recommended action No further action required

Surveyor comments N/A

Page 24 of 36 J023101

Building Room Item Quantity

12 Creswell Gardens Utility Room - G/003 No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

Building Room Item Quantity

12 Creswell Gardens Lobby - G/004 No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

Recommended action No further action required

Surveyor comments N/A

Page 25 of 36 J023101

Building Room Item Quantity

12 Creswell Gardens Kitchen Cupboard - G/005 No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

Building Room Item Quantity

12 Creswell Gardens Understair Cupboard - G/006

No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

Recommended action No further action required

Surveyor comments N/A

Page 26 of 36 J023101

7 Aug 2023 John Arnold Refurbishment Survey Ground Floor No Asbestos Detected (0)

Building Room Item Quantity

12 Creswell Gardens Cupboard - G/007 Red vinly including adhesive to gloor below carpet

1m²

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

S

FK001062

Reinforced Composite (1) N/A N/A N/A

Material Risk Score

N/A

Building Room Item Quantity

12 Creswell Gardens Toilet - G/008 No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

Recommended action No further action required

Surveyor comments N/A

Page 27 of 36 J023101

Building Room Item Quantity

12 Creswell Gardens Stairwell Lobby - G/009 No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

7 Aug 2023 John Arnold Refurbishment Survey Ground Floor No Asbestos Detected (0)

Building Room Item Quantity

12 Creswell Gardens Boiler Room - G/010 Insulation residue lining walls behind pipework

20m²

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

S

FK001069

Insulating Board (2) N/A N/A N/A

Material Risk Score

N/A

Recommended action No further action required

Surveyor comments N/A

Page 28 of 36 J023101

Building Room Item Quantity

12 Creswell Gardens Gas Meter Cupboard - G/011

No asbestos bearing materials were identified at the time of survey

N/A

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

N/A N/A N/A N/A N/A

Material Risk Score

N/A

7 Aug 2023 John Arnold Refurbishment Survey External No Asbestos Detected (0)

Building Room Item Quantity

12 Creswell Gardens External - E/001 Asphalt roof covering over second floor flat roof

20m²

Sample No (S,SP,P,As)

Product Type Surface Treatment Condition Accessibility

S

FK001068

Reinforced Composite (1) N/A N/A N/A

Material Risk Score

N/A

Recommended action No further action required

Surveyor comments N/A

Page 29 of 36 J023101

Appendix 3 - General Building Construction by location

Building Floor Room No: Room Type Item 12 Creswell Gardens

Roof Void R/001 Loft Space Timber clad roof, masonry walls, cloth insulation to pipework, metal tanks, timber hatch

12 Creswell Gardens

2nd Floor 2/001 Bathroom No access below fixed timber flooring, ceramic tiled masonry walls, metal pipework within boxing, UPVC windows, fixed plaster ceiling

12 Creswell Gardens

2nd Floor 2/002 Bedroom No access below fixed timber flooring, masonry walls, metal pipework within timber boxing, UPVC windows, fixed plaster ceiling

12 Creswell Gardens

2nd Floor 2/003 Bedroom No access below fixed timber flooring, masonry walls, metal pipework and radiators within timber boxing, timber framed windows, fixed plaster ceiling

12 Creswell Gardens

2nd Floor 2/004 Bedroom No access below fixed timber flooring, masonry walls, metal pipework and radiators within timber boxing, timber framed windows, fixed plaster ceiling

12 Creswell Gardens

2nd Floor 2/005 Stairs and Landing

No access below fixed timber floor below carpet, masonry walls, plaster ceiling, timber staircase, quarry tiled sill, timber framed windows

12 Creswell Gardens

1st Floor 1/001 Bathroom No access below fixed timber flooring, ceramic tiled masonry walls, metal pipework within boxing, UPVC windows, fixed plaster ceiling

12 Creswell Gardens

1st Floor 1/002 Bedroom No access below fixed timber flooring, masonry walls, metal pipework within timber boxing, UPVC windows, fixed plaster ceiling

12 Creswell Gardens

1st Floor 1/003 Living Room Very limited access below fixed timber flooring, masonry walls, metal pipework and radiators within timber boxing, timber framed windows, fixed plaster ceiling, marble and concrete fireplace

12 Creswell Gardens

1st Floor 1/004 Stairs and Landing

No access below fixed timber floor below carpet, masonry walls, plaster ceiling, timber staircase, quarry tiled sill, timber framed windows

12 Creswell Gardens

Ground Floor G/001 Dining Room Fixed timber flooring, not accessed below, masonry walls, timber framed windows, fixed plasterboard ceiling, timber panel lining marble fireplace

12 Creswell Gardens

Ground Floor G/002 Kitchen Fixed timber flooring not accessed below, masonry walls, UPVC framed windows, fixed plasterboard ceiling, timber panel lining service penetrations above door

12 Creswell Gardens

Ground Floor G/003 Utility Room Fixed timber flooring no access below, ceramic tiled masonry walls, UPVC window, fixed plasterboard ceiling

12 Creswell Gardens

Ground Floor G/004 Lobby Fixed timber flooring no access below, masonry walls, UPVC window, fixed plasterboard ceiling

12 Creswell Gardens

Ground Floor G/005 Kitchen Cupboard

Fixed timber flooring not accessed below, masonry walls, metal framed windows, fixed plasterboard ceiling

Page 30 of 36 J023101

Appendix 3 - General Building Construction by location (cont)

Building Floor Room No: Room Type Item 12 Creswell Gardens

Ground Floor G/006 Understair Cupboard

Concrete floor, masonry walls, plaster ceiling, timber lined door

12 Creswell Gardens

Ground Floor G/007 Cupboard Carpet and lino on timber floor, masonry walls, plaster ceiling, timber lined door

12 Creswell Gardens

Ground Floor G/008 Toilet Fixed ceramic flooring, masonry walls, timber framed windows, plaster ceiling, timber boxing housing metal pipework

12 Creswell Gardens

Ground Floor G/009 Stairwell Lobby Fixed ceramic flooring, masonry walls, meral framed windows, plaster ceiling, timber staircase

12 Creswell Gardens

Ground Floor G/010 Boiler Room Concrete floor, masonry walls, lath and plaster ceiling, redundant metal flue exiting ceiling, foam and cloth insulation to metal pipework, modern wall mounted boiler, metal door

12 Creswell Gardens

Ground Floor G/011 Gas Meter Cupboard

Concrete floor, masonry walls, plaster ceiling, metal pipework

12 Creswell Gardens

External E/001 External Slate tiled pitched roof, modern felt lining timber tank housing, plastic tank covered with fibreglass insulation, asphalt roof, timber hatch, timber boxing packed with fibreglass housing foam insulated pipework, plastic guttering

Page 31 of 36 J023101

Appendix 4 – Sample Certificates

Sycamore Court North Leigh Business Park North Leigh Oxfordshire OX29 6SW

Tel: 01993 868636 www.asbestoslabs.co.uk

CERTIFICATE OF ANALYSIS FOR ASBESTOS FIBRES

Report Number: ALS/J069146

ALS14A

Issued by: Quality Manager

SENSITIVE BUT UNCLASSIFIED

Issue Date: 12/10/2022 Issue No. 8

Analysed By Gina Kendall

Analyst Signatory

Approved By Jack Wood

Approver Signatory

Samples of material(s) [detailed below] have been examined to determine the presence of asbestos fibres, using Polarised Light Microscopy together with dispersion staining based on the HSE’s guidance document HSG248 and Asbestos Laboratory Services’ documented method. If samples have been delivered to the laboratory, the site address and sample location is reported as provided by the client. Reported results apply to samples as received. Asbestos Laboratory Services are not responsible for the accuracy or competence of the sampling by third parties. Under these circumstances, Asbestos Laboratory Services cannot be held responsible for the interpretation of the results shown. Opinions and interpretations are outside the scope of the UKAS accreditation.

All entries under ‘Fibre Type Detected’ that contain (*) indicate that the sample was found to be deviating from policies defined in document TPS63 (UKAS Policy on Deviating Samples). As a result, the test result(s) may be invalid. The Determination of Asbestos Content Report shall not be reproduced except in full, without written approval of the laboratory. V2, or subsequent “V” numbers, after the report number signifies that the original certificate (or previous amended certificate) has been replaced. All records, communications and reports pertaining to the analysis are archived for a minimum of five years. The samples analysed are retained for a minimum of six months.

Client Inspectas Compliance Ltd Attention Paula Candlish

Client Address Atlas House, 5 Bradford Road, Drighlington, BD11 1AS

Site Address 12 Creswell Gardens, London, SW5 0BJ

Site Ref J023101 No. of Samples 9

Date Received 08/08/2023 Date of Analysis 08/08/2023 - 09/08/2023

Report Issue Date 09/08/2023

Lab Ref

Client Sample Number

Sample Location

Sample Description

Fibre Type Detected

BS282439 FK001061 Ground Floor, Dining Room, Cement panel lining underside of timber radiator boxing

Chrysotile

BS282440 FK001062 Ground Floor, Cupboard, Red vinly including adhesive to gloor below carpet

N.A.D.I.S

BS282441 FK001063 1st Floor, Living Room, Cement panel lining underside of timber radiator boxing

Chrysotile

BS282442 FK001064 1st Floor, Stairs and Landing, Insulating board panel lining cupboard door

N.A.D.I.S

BS282443 FK001065 2nd Floor, Bedroom, Cement panel lining underside of timber radiator boxing

Chrysotile

BS282444 FK001066 2nd Floor, Stairs and Landing, Insulating board panel lining cupboard door

N.A.D.I.S http://www.asbestoslabs.co.uk/

Sycamore Court North Leigh Business Park North Leigh…

This is the start of the file's text. The full file is on GovTribe.