DNR White Pines Forest - Replace Lodge Hot Water Heater
Solicitation number
22-422DNR-REALT-B-28931
Issued by
Lake County, Illinois

About this file

This document is a Scope of Work for a small purchase procurement issued by the Illinois Department of Natural Resources for the replacement of an existing natural gas hot water heater at the White Pines Forest State Park Lodge. The project requires the contractor to disconnect the existing hot water heater, remove it, and install a new 80-gallon, 199,000 BTU/HR natural gas hot water heater. The project specifications require the contractor to have 3 years of commercial plumbing experience and the ability to provide documentation of at least 5 similar projects. The solicitation provides a list of acceptable manufacturers for the hot water heater. The work must be completed by December 31, 2022, with substantial completion anticipated within 6 weeks of the notice to proceed. Bids may be submitted electronically or using the provided bid form, and all questions must be submitted in writing no later than 3 business days before the bid date.

The document outlines insurance, bonding, and prevailing wage requirements for the project. It also specifies that a minimum of 50% of the work must be completed by the prime contractor, and that the contractor must identify all subcontractors and the anticipated amount of money each will receive. The contract may be funded in whole or in part by tax-exempt bonds, and payments will be made in accordance with the State Prompt Payment Act.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ILLINOIS DEPARTMENT OF NATURAL RESOURCES

SMALL PURCHASE PROCUREMENT

SCOPE OF WORK & PROJECT REQUIREMENTS

Date: April 1, 2022 File# 1-22-048

LOCATION:White Pines Forest State Park - Lodge
6712 W. Pines Road
Mt. Morris, IL 61054

PROJECT TITLE: Replace One (1) Existing Natural Gas Hot Water Heater

PROJECT NARRATIVE:

The existing Natural Gas Hot Water Heater (A. O. Smith Model BTR 199 118, Serial # 1524M001738) located in the White Pines Forest State Park Lodge, has failed. This water heater provides hot water to the entire lodge. Due to its age and condition, it is more cost effective to replace this water heater in lieu of expensive repairs. Failure to replace the existing water heater will result in a disruption to State services and the loss of future State revenues.

SCOPE OF WORK:

· Disconnect existing gas line, water lines, and flue from existing Natural Gas hot water heater.

· Remove one (1) existing Natural Gas hot water heater (A. O. Smith Model BTR 199 118) from existing location.

· Provide and install one (1) new 80 Gallon Natural Gas hot water heater:

· rated at 199,000 BTU/HR input with a minimum recovery rate of 190 gallons per hour and

· includes one new viewable exterior temperature gauge

· Plumb high pressure copper relief line to nearest floor drain.

· Reconnect existing gas line, water lines, and flue to new Natural Gas hot water heater.

· New copper lines to be installed with pressure fittings.

· All new plumbing work shall comply with the current Illinois State Plumbing Code.

· Remove old hot water heater and any construction debris from the property and dispose of per applicable EPA guidelines.

· The existing adjacent water storage tank and secondary natural gas hot water heater are to remain in place, refer to attached photographs.

ATTACHMENTS:

The following documents are included:

1) Photographs of Existing Installation

PROJECT SPECIFICATIONS & REQUIREMENTS:

A. Project Specifications:

1) The awarded contractor must have three (3) years of experience in the commercial plumbing industry and be able to provide documentation of completion of at least 5 projects similar in size and scope to this one.

2) Acceptable Manufacturers include the following which have undergone numerous safety testing and wear testing by Underwriters Laboratories (UL), Applied Research Laboratory (ARL) and many other nationally recognized testing laboratories. These manufacturers have also been recognized for quality construction and superior performance by consumer-based organizations such as Consumer Reports. [Bidders must be certified by the manufacturer to sell and / or install the equipment from the specified acceptable manufacturers listed below.

“Or Equal” submissions will not be rejected because of minor differences in design, construction or features that do not affect the suitability of the product for its intended use. Burden of Proof that the product is equal is on the bidder.

Acceptable Manufacturers include:

1)A. O. Smith
2)State
3)Lochinvar
4)PVI
5)Rheem
6)Bradford White
7)Weil - McLain

B. Project Instructions and Notes:

1) Work Completed by Prime Contractor:

A minimum of fifty percent (50%) of the work shall be completed by the Prime Contractor on this project. Pursuant to (30 ILCS 500/1-15.17) the Contractor is the person having a contract with the Illinois Department of Natural Resources.

2) Coordination of Work Activities:

All work activities and entry to the site must be coordinated with the site superintendent.

3) Deliverables and Staff Training:

Two (2) sets of operating and maintenance manuals and start-up procedures shall be provided to DNR. DNR staff shall receive one (1) hour of training and instruction on the operation and maintenance of all new equipment.

4) Shop Drawings:

Submit for the approval of the DNR Project Architect/Engineer, shop drawings and product data for the following items:

a. New 199,000 BTUH Natural Gas Hot Water Heater

5)Extended Warranty:
a)Workmanship, materials and equipment subject to seasonal loads will be in conformance with the contract and free from defects for a period of two years, commencing from the goods acceptance date. This includes, but is not limited to, heating, ventilating, air conditioning, temperature control and test and balance work, as specified.
b)Seeded areas shall be warranted for a period of one year plus one growing season.

6) Contractor’s Schedule of Values:

The Contractor shall provide to the DNR Project Architect/Engineer, a cost breakdown of each item of work required to fulfill the contract. The breakdown shall be identified on the Contractor’s Schedule of Values (CSV) form included in the Attachments.

C. Project Requirements:

1)Project Meeting
PROJECT MEETING TO BE HELD: YES |_| NO |X|
MANDATORY ATTENDANCE: YES |_| NO |X|

There will be no pre-bid meeting for this solicitation.

2) COVID-19 Requirements In response to the COVID-19 pandemic, Governor J.B. Pritzker issued Executive Order 2021-22 and 2021-23. These Executive Orders mandate certain contractors shall use face coverings, have COVID-19 vaccinations, or undergo testing for COVID-19 when in indoor public places, Health Care Facilities, Schools, Institutions of Higher Education, and State-owned and operated congregate facilities. Vendor shall adhere to the requirements of these Executive Orders as applied by the Agency. The Agency may also implement vaccination or testing requirements that exceed those in the Executive Orders.

3) Duration Bids shall be good for ninety (90) calendar days after the submittal date, or for an extended period, if agreed to in writing by the Bidder and DNR.

4) Prevailing Wage Rates

This contract [or agreement] calls for the construction of a “public work,” within the meaning of the Illinois Prevailing Wage Act, 820 ILCS 130/.01 et seq. (“the Act”). The Act requires contractors and subcontractors to pay laborers, workers and mechanics performing services on public works projects no less than the current “prevailing rate of wages” (hourly cash wages plus amount for fringe benefits) in the county where the work is performed. The Illinois Department of Labor (IDOL) publishes the prevailing wage rates on its website at http://labor.illinois.gov/. IDOL revises the prevailing wage rates and the contractor/subcontractor has an obligation to check the IDOL’s web site for revisions to prevailing wage rates. For information regarding current prevailing wage rates, please refer to IDOL’s website. All contractors and subcontractors rendering services under this contract must comply with all requirements of the Act, including but not limited to, all wage requirements and notice and record keeping duties.

Certified Payroll, The Vendor and each subcontractor who participate in public works shall be in accordance with 820 ILCS 130/5

Make and keep, for a period of not less than 3 years from the date of the last payment made before January 1, 2014 (the effective date of Public Act 98-328) and for a period of 5 years from the date of the last payment made on or after January 1, 2014 (the effective date of Public Act 98-328) on a contract or subcontract for public works, records of all laborers, mechanics, and other workers employed by them on the project.

2. No later than the 15th day of each calendar month file a certified payroll for the immediately preceding month with the public body in charge of the project

EMPLOYMENT OF PUBLIC WORKERS ON PUBLIC WORKS: In a period of excessive unemployment rates, State contractors (1) constructing or building any public works or (2) cleaning-up and disposing on-site of hazardous waste, and that clean-up or on-site disposal is funded or financed in whole or in part with State funds or funds administered by the State, are required to employ at least 90% Illinois laborers on such project. For projects involving clean-up and on-site disposal of hazardous waste, emergency response or immediate removal activities are excluded. This requirement applies to all labor whether skilled, semi-skilled or unskilled, whether manual or non- manual.

A period of excessive unemployment rates is defined as any month immediately following two consecutive calendar months during which the level of unemployment in the State of Illinois has exceeded 5% as measured by the United States Bureau of Labor Statistics in its monthly publication of employment and unemployment figures.

Any public works project financed in whole or in part by federal funds administered by the State of Illinois is covered under the provisions of this requirement, to the extent permitted by any applicable federal law or regulation. 30 ILCS 570.

Contractors may receive an exception from this requirement by submitting a request and supporting documents certifying that Illinois laborers are either not available or are incapable of performing the particular type of work involved. The certification must: (a) be submitted to the agency within the first quarter of the Contract Term; (b) provide sufficient support that demonstrates the exception is met; (c) be signed by an authorized signatory of the contractor; and (d) be approved by the agency.

5) Apprenticeship-in-Training When applicable, the contractor and all subcontractors must be participants in apprenticeship and training programs that are both approved by and registered with the U.S. Department of Labor’s Bureau of Apprenticeship and Training. The program(s) must be in the same trade(s) in which the contractor or subcontractor performs work. For information on how to participate in or set up a program, contractors may call the U.S. Department of Labor at 312/596-5508 or visit their website http://www.doleta.gov/oa/ .

6) Illinois Office The bidder must certify that the bidder will maintain an Illinois office as the primary place of employment for persons employed in the construction authorized by the contract.

7) Subcontractors The Contractor shall identify the names of all subcontractors to be utilized by them in the performance of this contract, together with the anticipated amount of money that each subcontractor is expected to receive pursuant to this contract. Pursuant to Illinois Procurement Code (30 ILCS 500/1-15-108), a person or entity is not a “subcontractor” if that person only provides goods or supplies that are incidental to the performance of a contract by a person who has a contract subject to the Code.

9)Insurance
Contractor shall, at all times during the term of this contract and any renewals or extensions, maintain and provide a Certificate of Insurance naming the State as an additionally insured for all required bonds and insurance. Certificates may not be modified or canceled until at least thirty (30) days’ notice has been provided to the State. Contractor shall provide: (a) General Commercial Liability insurance in the amount of $1,000,000 per occurrence (Combined Single Limit Bodily Injury and Property Damage) and $2,000,000 Annual Aggregate; (b) Auto Liability, including Hired Auto and Non-owned Auto (Combined Single Limit Bodily Injury and Property Damage), in amount of $1,000,000 per occurrence; and (c) Worker’s Compensation Insurance in the amount required by law. Insurance shall not limit Contractor’s obligation to indemnify, defend, or settle any claims.

10) Performance Bond/Labor and Material Payment Bond Pursuant to the Public Construction Bond Act (30 ILCS 550/), a performance bond and a labor and material payment bond covering the faithful performance of the contract and the payment of all obligations arising thereunder, shall be required if the project cost exceeds $50,000. Each bond shall be in the full amount of the contract. The bond must be from a surety licensed to do business within the State of Illinois and acceptable to IDNR.

11) Minority Contractor Opportunity Initiative The State requires a fee of $15 to cover Expenses related to the administration of the Minority Contractor Opportunity Initiative. Any Vendor awarded a contract under Section 20-10, 20-15, 20-25 or 20-30 of the Illinois Procurement Code (30 ILCS 500) of $1000 or more is required to pay a fee of $15. The Comptroller shall deduct the fee from the first check issued to the Vendor under the contract and deposit the fee in the Comptroller’s Administrative Fund.

12) Permits and Licenses Permits and licenses necessary for the execution of the work shall be secured and paid for by the Contractor.

13) Utilities Before starting excavation, establish location and extent of underground utilities occurring in the work area. Contractor shall contact Joint Utility Locating Information for Excavators (J.U.L.I.E.) 800-892-0123.

14) Highway Permits The Contractor is responsible for contacting the appropriate County Superintendent(s) of Highways and/or other appropriate local officials concerning the proposed work activities on the project as they may relate to use of the County and local road system. Coordination of any activities of concern to the County or Township shall be the responsibility of the Contractor. Special attention shall be given to load limits and seasonal restrictions.

15) New Products Unless otherwise specifically provided in the contract documents, all materials, equipment and products incorporated in the work under the contract shall be new and of a suitable grade for the purpose intended.

16)Steel Products
Any steel product(s) used or supplied in the performance of this contract shall be manufactured or produced in the United States, in accordance with the Steel Products Procurement Act, unless a waiver is granted by IDNR (30 ILCS 565/).

17) Specified Materials Bids shall be based on providing all products/materials exactly as required by the project specifications. Contractor may select from the list of acceptable manufacturers, offer an “equal” product and provide proof of its capabilities to meet the project specifications or, for products specified only by reference or performance standards, select any product which meets or exceeds the specified standards, by any manufacturer, subject to the approval of DNR.

18) Final Cleaning Contractor shall clean-up all work related debris and construction materials and properly dispose off-site. The Contractor shall repair and otherwise make good any damage caused by the work and leave the premises in the equivalent of the original condition.

19) Warranties The Contractor warrants that all work provided under the contract will be in conformance with the contract and free from defects in workmanship, materials, and equipment for a period of one year from the goods acceptance date. See Section B. Project Instructions and Notes, for any extended warranties that may apply.

20) Change Orders Change order shall be defined as a change in a contract term, other than as specifically provided for in the contract, which authorizes or necessitates any increase or decrease in the cost of the contract or the time for completion. A change order shall be executed by the State agency and vendor evidencing the change. All changes shall be approved by the CPO, or designee, and be accompanied by a written determination that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed and the change is germane to the original contract as signed. Change orders that increase or decrease the cost of a contract or an estimated contract by a total of $10,000 or more or the time of completion by more than 30 days shall be published on the Illinois Procurement Bulletin, pursuant to Section 15-25 of the Code and documented pursuant to Section 33E-9 of the Criminal Code of 2012, in advance of execution of the change order.

21) Inducement Resolution All or a portion of this project may be paid or reimbursed from the proceeds of tax-exempt bonds subsequently issued by the State.

22) Payment Payments, including late payment charges, will be paid in accord with the State Prompt Payment Act and rules when applicable, 30 ILCS 540/; 74 III. Adm. Code 900. This shall be the Contractor’s sole remedy for late payments by the State. Payment terms contained in Contractor’s invoice(s) shall have no force or effect.

23)Contract Award
Contract award will be made to the lowest, responsible, responsive bidder. The Department of Natural Resources reserves the right to reject any or all bids.

24) Term of Contract All work shall be completed by December 31, 2022. Substantial completion (beneficial occupancy by IDNR) of work is anticipated within six (6) weeks of Notice to Proceed with work to the Vendor.

25) Bid Submittal Bids may be submitted electronically on BidBuy or by submitting the attached Bid Form.

26)Bid Submittal Date and Time
Refer to the BIDBUY solicitation for the bid date and time.

27) Questions

ALL QUESTIONS PERTAINING TO THE SCOPE OF WORK OR THE BIDBUY PROCEDURES, MUST

BE DIRECTED TO LeighAnn.Henline2@illinsoig.gov. ALL QUESTIONS MUST BE SUBMITTED IN WRITING NO LATER THAN THREE (3) BUSINESS DAYS BEFORE THE BID DATE.