This Statement of Work (SOW) details repair requirements for an Altec Pole Truck (asset number 03C00737) for the U.S. Government. The SOW specifies comprehensive repair objectives including refinishing the upper boom and addressing spiral cracks, replacing out-of-date leveling cables, and conducting a series of post-repair tests: structural load test, dielectric test, and operational test. The contractor will be responsible for providing all necessary personnel, equipment, tools, materials, and transportation to complete the repairs, with the U.S. Government delivering the vehicle to the contractor's facility for servicing. The SOW is dated 14 March 2025 and aims to ensure the truck is certified as serviceable for all types of repairs after the maintenance is completed.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

FOR

ALTEC POLE TRUCK 03C00737

(14 March 2025)

1.0. General:

1.1. Scope: The Company shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, to replace the out-of-date leveling cables and refinish the upper boom spiral cracks meets or exceeded manufactures requirements, as defined within this statement of work (SOW).

1.1.1. Objectives: Refinish upper boom and spiral cracks, replace out of date leveling cables, perform a structural load test, perform a dielectric test, and perform an operational test after repairs are completed and certify truck is serviceable for all type of repairs.

1.3. General Information:

1.3.1. Place and Performance of Services: U.S. Government will deliver vehicle to vendor to have repair completed on 03C00737.

2.0. Contractor Furnished Property, Materials, and Equipment (CFP/M/E): The Contractor shall provide all materials and/or equipment required to complete services required within this SOW.

2.1. General: The Contractor shall furnish everything required to perform the repairs as indicated in Paragraph 1.1.

3.0. Requirements: The Contractor shall provide all labor, tools, materials, and transportation necessary to accomplish the repairs to this unit.

3.1. Transportation. US Government will deliver asset 03C00737 to contractor facility.

File details come from the government source that posted it. Updated .