- Solicitation number
- 1305M226Q0199
About this file
This is a Statement of Work (SOW) for maintenance of the Hawaiian Islands Humpback Whale National Marine Sanctuary, specifically for lowering an entrance concrete berm at 726 S. Kihei Rd, Kihei, HI 96753.
The vendor must survey the existing entrance berm and lower it to prevent emergency vehicles from bottoming out. The berm is currently 15 inches high from the road asphalt and approximately two feet high from the parking lot asphalt. The site's initial request is to lower the berm by one foot from the parking lot elevation, subject to vendor recommendations following site assessment. Scope of work includes: surveying and consulting with the site on best mitigation strategies; manipulating the concrete berm to the necessary elevation; regrading the area between road and parking lot for smooth vehicle access; restoring any disturbed surfaces; and cleaning up and disposing of excess material while restoring site aesthetics. The vendor may propose alternative approaches to berm manipulation provided cost estimates remain within scope and emergency vehicle access is maintained while preserving access to all parking stalls. Installation timing must be coordinated to integrate seamlessly with separate entrance berm grading/lowering and automated electric swing gate installation. No power is required for this passive/manual system. IT security requirements specify that no Certification and Accreditation is required, and the contractor will not access US government computers, IT systems, or non-public information. Contact Shelly Rofrits, NOAA Facilities Coordinator, at 808-264-3043 or shellyann.rofrits@noaa.gov to schedule site assessments.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_1305M226Q0199.pdf | ||
| WD_2015-5739.pdf | ||
| SOW_-_0002_Flood_Barrier_Fab_and_Install.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Maintenance of Site (Site Entrance Berm Lowering)
Hawaiian Islands Humpback Whale (HIHW) National Marine Sanctuary
Summary
The facility requires the lowering of the existing entrance concrete berm, located 15 inches from the road and approximately two feet from the parking lot, to prevent emergency vehicles from bottoming out. The site’s initial request is to lower the berm by one foot from the parking lot, provided vendor recommendations upon site assessment.
1. Scope of Work
The vendor will:
● Survey and consult with the site over best mitigation strategy for manipulating berm to account for emergency vehicle access.
● Manipulate the concrete berm to the necessary elevation.
● Regrade the area between the road and the parking lot to ensure smooth vehicle access.
● Site restoration of any disturbed surfaces.
● Cleanup and disposal of any excess material and restoration of site to prior aesthetics.
Prior to conducting work, the vendor will survey the berm and make recommendations based on appropriate lowering height and gradient. The vendor may also make recommendations, provided that cost estimates stay within scope, on alternative approaches on how to best manipulate the berm so that emergency vehicles will not bottom out while maintaining vehicle access to all parking stalls in the lot.
2. IT Security Requirements
The Certification and Accreditation (C&A) requirements of 48 CFR 1352.239-73 do not apply, and a Security Accreditation Package is not required. The Contractor will not be accessing US government computers or IT systems for this effort. The Contractor will not be accessing any information that is not within the public domain for this effort. The contractor will not be processing, transmitting or storing privileged access information (i.e., non-public) in carrying out the tasks of this contract.
3. Facility Information
The installation site is located across the main driveway entrance. Power is not required for this passive/manual system. The vendor must coordinate installation timing to ensure it seamlessly integrates with the separate grading/lowering of the entrance berm and the installation of the automated electric swing gate.
LOCATION: 726 S. Kihei Rd, Kihei HI 96753
NOAA ON-SITE CONTACT
For appointments to assess the Site please contact the following:
Shelly Rofrits NOAA Facilities Coordinator 808-264-3043 cell shellyann.rofrits@noaa.gov
View of the site entrance berm from the site parking lot. It is approximately two feet high from the parking lot asphalt to the top of the berm.
mailto:shellyann.rofrits@noaa.gov
View of the concrete berm from the main road. The height from the asphalt to the top of the berm is 15 inches.
File details come from the government source that posted it. Updated .