Southwest Coastal Industry Day Slides .pptx
PPTX presentation 15 MB Posted
- Attached to
- Southwest Coastal Industry Day
- Solicitation number
- Not on record
About this file
The document is an industry day presentation slide deck for the U.S. Army Corps of Engineers (USACE) New Orleans District's Southwest Coastal Louisiana Nonstructural Coastal Storm Risk Management Project. The project involves a Design-Build Indefinite-Delivery, Indefinite-Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) with a total shared capacity of $99M to design and implement localized non-structural solutions for flood risk reduction. The project targets 3,462 residential structures for elevation (5-13 feet), 342 non-residential structures for dry flood-proofing, and 157 warehouses for berm construction in Cameron, Calcasieu, and Vermilion Parishes.
The slides detail the comprehensive design-build process, including government-furnished information requirements, engineering specifications, code compliance standards, construction quality management, and safety protocols. The industry day is scheduled for December 10, 2025, at 7400 Leake Ave., New Orleans, with a registration deadline of December 3, 2025, at 10:00 AM CST. The project emphasizes voluntary participation, with no cost-share for homeowners, and focuses on structures at or below the 2025-25-year base flood elevation. Potential contractors are encouraged to prepare for bidding by monitoring SAM.gov, understanding solicitation requirements, and ensuring capability to meet technical and safety standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Southwest Coastal Industry sign in roster.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WELCOMING REMARKS
COL Autin Scotty M. Autin Colonel, Engineer 66th Commander & District Engineer New Orleans District U.S. Army Corps of Engineers
Agenda Introductions Project Overview USACE Design Build Process Construction Doing Business with the Government Closing Remarks / Q&A
Durund Elzey Deputy District Engineer USACE – New Orleans District 10 Dec 2025 Project Overview
Project Overview
Distribution of Structures – 0-25 Year Floodplain The project is 100% voluntary Buyouts & acquisitions are not part of the project.
The Project recommends 3,462 residential structures will be considered for elevation equivalent to the 2075 100- year BFE. Qualifying residential structures will be raised approximately 5 feet on average, but no higher than 13 feet.
3,462
RESIDENTIAL STRUCTURES ELIGIBLE
TO BE
RAISED
DRY FLOOD-PROOFING
342 non-residential structures will be considered for dry flood- proofing to 3 feet above ground.
BERMS
Localized risk reduction measures (constructing berms) for 157 warehouses will be considered less than or equal to 6 feet above the ground.
Home Elevations What You Need to Know This is 100% voluntary and there is no cost-share to the homeowner Flood insurance is not required for participation Buyouts and acquisitions are not allowed Homeowner must complete the application process What You Need to Know Covered Costs:
Raising you home 3-13 feet Utility and structural adjustments NOT Covered:
Temporary relocation for homeowners Add-ons or upgrades Hazardous material remediation (mold/asbestos, lead, etc.)
What’s Covered & What’s NOT in a Home Elevation Home must be identified in the Feasibility Study in 2016 Home mist be structurally sound Applicant possesses a clear title and owns the home No unresolved estate issues or liens on the home Have not received previous federal funding for elevation Properties must be free from hazardous materials or contamination (mold, asbestos, lead, etc.)
Homeowner must sign a participation agreement agreeing to keep the area below 1st floor non-habitable (can be used for parking, access, storage, etc.)
What is Required?
Around 3,462 properties are eligible in Cameron, Calcasieu, and Vermilion Parishes – you may be one of them!
Scan the QR code or visit https://www.mvr.usace.army.mil/SWCoastal/ to find out if you are eligible and apply Is Your Home Eligible?
SCAN HERE
The Project recommends 3,462 residential structures will be considered for elevation equivalent to the 2075 100- year BFE.
Qualifying residential structures will be raised approximately 5 feet on average, but no higher than 13 feet.
Project Purpose 3,462
RESIDENTIAL STRUCTURES
ELIGIBLE TO BE RAISED
DRY FLOOD-PROOFING
BERMS
342 non-residential structures will be considered for dry flood- proofing to 3 feet above ground.
Localized risk reduction measures (constructing berms) for 157 warehouses will be considered less than or equal to 6 feet above the ground.
The Project includes structures at or below the 2025- 25-year base flood elevation (BFE).
USACE issue MATOC Task Order Sponsor initiate Real Estate Work MATOC KTR prepares template schedule for all structures in TO MATOC KTR prepares design package and meets with Homeowner (Initial design conference) MATOC KTR submits design package with input from Homeowner
USACE accept design package USACE send comments to MATOC KTR MATOC KTR address comments MATOC KTR prepares final design package and meets with the Homeowner (Final Design Conference) Sponsor and Homeowner execute Participation Agreement Sponsor sends Authorization for Entry to USACE USACE Release for Construction Workflow Overview
Christopher L. Dunn, Ph.D., P.E.
Chief, Engineering Division USACE – New Orleans District
Design Build Process
Government Furnished Info (GFI)
Bridging documents provide site specific design requirements set by USACE and field data.
The Designer of Record (DOR) is responsible for site condition and field data verification prior to commencement of design and work.
Government Furnished Info – Bridging Document Summary The floodproofing bridging documents will include:
Work Summary Floor Elevation Survey Sheet (FESS) Structural Conditions Assessment Report (SCAR) Structural Conditions Assessment Survey (SCAS) Phase 1 Hazardous, Toxic and Radioactive Waste (HTRW) Report Archaeological Report These documents will contain detailed information collected by the third-party contractor, to be used in developing the design.
The information and summaries in the bridging documents are provided for reference in preparation of Task Orders.
Government Furnished Info – FBD Floodproofing Bridging Document Property Information (LOCATION) Structural Work Summary Architectural Work Summary Mechanical/Electrical/Plumbing Work Summary Site Assessment
Government Furnished Info – FESS Floor Elevation Survey Sheet
Structural Condition Assessment Report Includes photographs of each face of the building, noting visible conditions.
Government Furnished Info – SCAR
Structural Condition Assessment Summary Year built Sq Ft, No. of floors Existing Foundation type Additions (attached/detached/monolithic) Finishes Mechanical/Electrical/Plumbing (MEP) Building Elevation/Floodproofing Summary Assessment of the Condition Professional Opinion from Inspector
Government Furnished Info – SCAS
Engineering - Overview Code Compliance All elements of the design must be code compliant.
Design Requirements Assumptions must be founded in code, USACE regulations, and recorded observations in the field.
DOR must submit standardized designs.
Review Process Review packages must contain appropriate level of design documentation.
Schedules will include time for USACE review and coordination with property owners.
Standard Level of Professional Care DOR and subcontractors must be expected to meet standard level of professional care.
Design Build (DB) Prime Contractor is responsible for the quality of the DOR.
Pre-lift Requirements Post-lift Requirements
Pre-Lift
| * Perform site inspection | |
| - Document any changes from government furnished information | |
| - Document results from any field investigations – GPR or other methods | |
| * Submit Design Package | |
| - Will require a lift plan as part of the documentation for government review. | |
| - Design package required to have input by all subcontractors before final concurrence and “release for construction”. | |
| - D-B Contractor (Prime) is responsible for the quality and performance of all subs including the DOR. |
Post-Lift
| * Contractor must construct the design as shown in the release for construction documents |
| * If conditions differ from pre-lift assumptions, a RFI shall be submitted |
| - Changes to the “Released for Construction” plans must be documented with supporting calculations. |
| - Changes are highlighted with a revision cloud and summarized in the title block. |
| * A final Certified Engineer Report to include: |
| - Punchlist resolution |
| - List of corrective action for differing conditions (if applicable) |
| - Final As-built with all revisions (redline & CADD) |
| - Support calculations of deviations from the “Released for Construction” plan |
Engineering – Code Compliance Codes that must be followed include, but are not limited to, the most current versions of:
ASCE 7, 24, 37
ACI 117, 301, 302.1, 318, 332, 562
AISC 325, 360
APA E30
ASME A17.5, A18.1
AWC NDS
EM 1110-2-1913
ICC - IBC, IEBC, IMC, IPC, IRC
NFPA 70
TMS 402/602
ASCE 24-24
- Provides definitions and considerations for FRM work
ACI 562-25
- Identifies requirements for structural inspection of existing slabs (GPR)
- Recommended reduction factors
- Retrofits for slab-on-grade lifts
Engineering – Design Requirements Max. Area of Steel for Existing Concrete Grade Beams and Slabs As = 0.0015** ** Ground Penetrating Radar (GPR), coring, or chipping may be used to verify slab and footing widths, depths and rebar size and spacing to prove otherwise Segmental Concrete Press Piles may only be used to initiate the lift and as temporary shoring in combination with timber cribbing. Inclusion of any above-grade portion of a segmental concrete press pile into the permanent foundation is prohibited.
Dry stacking concrete blocks above grade is not permitted.
All new columns, piers, and walls are to be supported on reinforced concrete footings.
Existing shallow foundation elements left in place after elevation shall not be used to support new construction and must be demolished.
Engineering – Design Requirements Design Package will include:
Basis of Design (BOD) Architectural and Engineering Plans Specifications Calculations Field Investigation Documentation Design Quality Control (DQC) with subcontractor review Internal Technical Review (ITR) Comments and Responses (from previous reviews)
Calculations may include –
Hand Calculations Design Software Model File Input and Output Files DOR Interpretation of Results 3D Models
Engineering – Examples Standard Crawl Space Foundation Block Wall Foundation Elevated Access Elevated HVAC/Mechanicals Continuous Connected Roofline Vents Continuous Load Path
Engineering – Examples Standard Open Foundation Grouted Columns Elevated Access Elevated HVAC/Mechanicals Monolithic Foundations Continuous Connected Roofline Continuous Load Path
Stuart S. Waits, P.E.
Chief, Construction Division USACE – New Orleans District
Construction
Construction – QA/QC USACE contracts require a comprehensive Construction Quality Management Program Construction Quality Management (CQM) is the performance of tasks that ensure construction is performed according to plans and specifications, on schedule, within the defined budget, and in a safe work environment.
For a project to be successful, the Contractor and the Government must work in partnership to implement an effective CQM program.
Contractor Quality Control (QC) Ensures the project meets all quality requirements of the contract.
Develops and implements a comprehensive QC Plan that outlines quality oversight for all features of the project.
Provides a designated Quality Control Manager and staff on site daily to perform inspections and report findings.
Government Quality Assurance (QA) Verifies that the Contractor’s QC system is working effectively and that the completed work complies with the quality standards established by the contract.
Utilizes Quality Assurance Representatives (QARs) who perform site inspections and report findings.
Construction – Safety USACE contracts require a comprehensive Safety Program
Contractors must comply with all applicable safety regulations, including OSHA (29 CFR 1910 and 1926) and the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1).
Accident Prevention Plan (APP): A written APP is required and must be submitted to and accepted by the USACE before work begins. It outlines the contractor's specific safety program for the project.
A qualified Site Safety & health Officer (SSHO) is required on-site to ensure compliance, meet specified training requirements, and have experience on similar projects.
Daily safety inspections and hazard tracking are required. All documentation must be entered into the USACE Resident Management System (RMS).
Michelle R. Dalmado Contracting Officer USACE – New Orleans District
DOING BUSINESS WITH THE GOVERNMENT
Doing Business With The Government
Market Research:
Sources Sought - Ask for industry comments or provide notice that a solicitation is planned. This is your opportunity to let us know your capabilities or provide your professional input.
Pre-Solicitation Notices – A pre-solicitation notice is published a minimum of 15 calendar days before the solicitation is published, however, it can be months or even years depending on the scope of the project.
Solicitations:
Most solicitations are advertised for a minimum of 30 days.
Amendments are changes to the solicitation. Amendments often answer questions, clarify the work to be performed, or correct errors in the solicitation. Amendments also may extend the due date of the offer. You must acknowledge each amendment when submitting your offer to confirm that you are offering on the most recent version of the work to be performed.
Design Build
What is Design-Build?
Project delivery method combines design and construction phases into a single construction contract.
Pre-award process governed by:
FAR 36.303 Procedures: Subpart 36.3 - Two-Phase Design-Build Selection Procedures Engineering Regulation ER_1180-1-9 DESIGN BUILD CONTRACTING Best Value Trade-Off: DOD Source Selection Procedures (IAW FAR 15)
Two-Phase Source Selection
How Does Two Phase Design-Build Process Work?
Specifications: Preliminary design & provisional drawings only Phase 1 is used to select the most highly qualified offerors to compete for award in Phase 2. ONLY those considered highly qualified will participate in Phase 2.
Cost will be an Evaluation Factor in Phase 2.
Phase 2 is evaluated separately than Phase 1 so ensure ALL pertinent information is included in the Phase 2 proposal.
Contracting Best Practices
Read solicitation in full! Most questions can be answered by reading and re-reading the entire solicitation Q&A: Carefully note due date for questions and submit per instructions in the solicitation.
Read the Evaluation Criteria in full! Do not assume the evaluators know the information. Assumptions are not made in evaluating proposals.
File Names: Named files need to match file names outlined in the solicitation submission requirements.
Redundancy in Phase 2: Yes, repeat relevant information in Phase 2 that was provided in your Phase 1 proposals – evaluators do not look at Phase 1 proposals during Phase 2 evaluation.
Page limits! Extra pages will not be evaluated.
Early! Submit proposals well in advance of due date and time to allow for server lag, technical issues, etc.
How You Can Help MVN
Look for Prime and Subcontracting Opportunities SAM.gov District’s Acquisition Forecast Prepare to bid:
Set-asides Unrestricted Reply to Sources Sought via SAM.gov Review entire solicitation several times Clearly understand the project’s requirements!
Perform great work Work with your bonding company—highest $$ level possible
Commercial Solutions Opening
A streamlined procurement method that the DoW uses to acquire innovative commercial technologies, products, or services.
Current Areas of Interest (Subject to Change):
Maintenance of Authorized Channel Dimensions to Sustain Navigation and Production Efficiency Materials and Repair Methods for Navigation Structures Comprehensive Above- and Below-Water Imaging of Navigation Structures Locating subaqueous subsurface objects Sedimentation Prediction Modeling for Navigable Waterways Navigation and Flood Risk Management Project Delivery https://sam.gov/opp/ac84b382796a4a5e9de7cbebb11cc09a/view Mississippi Valley Division Civil Works Areas of Interest Commercial Solutions Opening
USACE – New Orleans District
Closing Remarks / Q&A image7.png image8.png image9.png image10.png image11.jpg image12.png image13.jpg image14.jpg image15.png image16.png image17.png image18.png image19.png image20.png image21.png image22.png image23.png image24.png image25.png image26.png image27.png image28.png image29.png image30.png image31.png image32.png image33.png image34.png image35.png image36.png image37.png image38.png image39.png image40.png image1.png image2.png image3.png