South_Grandview_WM_-_Phase_2_Installation_-_Specifications.pdf

PDF 5 MB Posted

Attached to
2559ITB - Grandview Avenue Watermain Replacement - Phase 2
Solicitation number
2559
Issued by
Volusia County, Florida

About this file

This document is a comprehensive technical specification file for the City of Daytona Beach's South Grandview Avenue Watermain Replacement - Phase 2 project. The project involves removing approximately 1,300 linear feet of existing 10-inch Ductile Iron Pipe watermain between Harvey Avenue and International Speedway Boulevard, and replacing all water services, water meters, and meter boxes along the route. The work includes installing new water mains approximately 3 feet west of the existing main, with associated valves, main extensions, and other infrastructure improvements. The project will be competitively bid through an online procurement platform, with a non-mandatory pre-bid conference and a deadline for questions prior to the bid opening.

The technical specifications provide extensive details on materials, installation methods, testing requirements, and quality control standards for the watermain replacement. The project includes multiple bid items covering everything from mobilization and survey/layout to specific pipe installations, valves, fittings, and surface restoration. The City has allocated a $20,000 allowance for maintenance of traffic and requires detailed documentation, including pre-construction video recordings, as-built drawings, and manufacturer certifications. The specifications outline rigorous testing protocols for piping, including hydrostatic pressure tests, leakage tests, and cleaning procedures, with strict requirements for material quality, installation techniques, and final system performance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TOC-1

TECHNICAL SPECIFICATIONS

Section No. Title

DIVISION 0 – BIDDING REQUIREMENTS, CONTRACT DOCUMENTS AND FORMS

00848 Certificate of Substantial Completion

00849 Certificate of Final Inspection & Completion

00852 Contractor’s Request for Information

00853 Hydrostatic Test Results

00865 Check Out Form

00866 Certificate of Completed Demonstration Form

DIVISION 1 - GENERAL REQUIREMENTS

01010 Summary of Work

01011 Mobilization

01014 Maintenance of Operations

01025 Measurement and Payment

01026 Schedule of Values & Payment Applications

01040 Coordination

01045 Cutting and Patching

01050 Field Engineering

01200 Project Meetings and Video

01300 Submittals

01340 Shop Drawing Procedures

01380 Construction Schedules

01390 Pre-Construction Audio-Video Recordings

01500 Temporary Facilities and Controls

01515 Temporary Bypass Pumping Systems

01541 Protection of the work and Property

01568 Erosion and Sedimentation Control

01570 Traffic Regulation

01580 Project Identification and Signs

01600 Material and Equipment

01611 Storage of Material

01640 Substitutions and Product Options

01700 Contract Closeout

01710 Final Cleaning

01720 As-Built Record Documents

01730 Operation and Maintenance Data

01740 Warranties

01760 Spare Parts and Maintenance Materials

DIVISION 2 – SITE WORK

02050 Demolition and Maintenance of service during construction

TOC-2

02080 Abandonment, Removal, and salvage or disposal of existing pipeline and structures

02202 Excavating, Backfilling and Compacting

02220 Selective Demolition

02240 Dewatering (During Construction)

02270 Temporary Erosion Control

02310 Site Grading

02489 Grassing

02616 Fittings for Pressure Service

02641 Gate Valves

02661 Pressure Testing of Piping

02801 Restoration of Surface Improvements

DIVISION 3 – CONCRETE

03800 Leakage Testing of Hydraulic Structures

DIVISION 5 - METALS

05500 Miscellaneous Metals

DIVISION 9 - FINISHES

09900 Painting and Coatings

09901 Painting Schedule

09905 Surface Preparation and Shop Coatings

DIVISION 13 - SPECIAL CONSTRUCTION

13200 Prestressed Concrete Storage Tank

DIVISION 15 – MECHANICAL

15000 Mechanical – General Requirements

15044 Pressure Testing of Piping

15045 Pipe Cleaning and Pigging

15050 Pipe and Pipe Fittings

15062 Ductile Iron Pipe

15066 Tracer Wire and Alarming Tape

15088 Couplings and Connectors

15100 Ancillary Equipment

15127 Air Release Valves

15399 Disinfection of Water Mains

15998 Joint Wrap

CERTIFICATE OF SUBSTANTIAL COMPLETION 00848-1

SECTION 00848

CERTIFICATE OF SUBSTANTIAL COMPLETION

THE CITY OF DAYTONA BEACH

Project:

Purchase Order No.: Contract Date:

This Certificate of Substantial Completion applies to:

[ ] All work under Contract [ ] Portion of work described as follows:

The Work to which this Certificate applies shall be inspected by authorized representatives of the CITY and the CONTRACTOR and that Work is hereby declared to be substantially complete in accordance with the Contract Documents on: DATE .

A tentative list of items shall be completed or corrected is attached hereto. This list shall not be all-inclusive, and the failure to include an item in it does not alter the responsibility of CONTRACTOR to complete all the Work in accordance with the Contract Documents. The items in the tentative list shall be completed or corrected by THE CONTRACTOR within days of the above date of Substantial Completion.

The date of Substantial Completion is the date upon which all guarantees and warranties begin.

SIGNED:

THE CITY OF DAYTONA BEACH CONSTRUCTION INSPECTOR

By: DATE:

THE CITY OF DAYTONA BEACH PROJECT MANAGER

By: DATE:

CONSULTING ENGINEER/ARCHITECT, ETC.:

By: DATE:

CONTRACTOR:

By: DATE:

CERTIFICATE OF SUBSTANTIAL COMPLETION 00848-2

TENTATIVE LIST OF ITEMS TO BE COMPLETED OR CORRECTED

(PUNCH LIST)

Date: Purchase Order No.:

Project:

Contractor:

This list shall not be all-inclusive, and the failure to include an item does not alter the responsibility of the CONTRACTOR to complete all the Work in accordance with the Contract Documents.

NO: ITEM:

END OF SECTION

CERTIFICATE OF FINAL INSPECTION & COMPLETION 00849-1

SECTION 00849

CERTIFICATE OF FINAL INSPECTION & COMPLETION

THE CITY OF DAYTONA BEACH

Project:

Purchase Order No.: Contract Date:

This Certificate of Final Inspection & Completion applies to:

The Work under this Contract has been inspected by authorized representatives of the CITY and the CONTRACTOR and all Work is hereby declared to be complete in accordance with the Contract Documents on:

DATE

SIGNED:

THE CITY OF DAYTONA BEACH CONSTRUCTION INSPECTOR

By: DATE:

THE CITY OF DAYTONA BEACH PROJECT MANAGER

CONSULTING ENGINEER/ARCHITECT/ETC.

CONTRACTOR

CONTRACTOR’S REQUEST FOR INFORMATION 00852-1

SECTION 00852

CONTRACTOR’S REQUEST FOR INFORMATION

TO: THE CITY OF DAYTONA BEACH

FROM: (CONTRACTOR) DATE:

CONTRACTOR REQUEST FOR INFORMATION NO.:

PROJECT NAME:

PURCHASE ORDER NO.:

QUESTION:

BY: DATE:

REPLY:

BY: DATE:

HYDROSTATIC TEST RESULTS 00853-1

SECTION 00853

HYDROSTATIC TEST RESULTS

THE CITY OF DAYTONA BEACH

Project Date Purchase Order No.:

Contractor Road or Street Station to Station Water Main Reuse Main Raw Water Main Force Main

Length of Pipe Tested (Ft.)

Nominal Pipe Diameter (In.)

Square Root of Avg.

Test Pressure

Divided by 133,200

Allowable Loss In Gallons/Hour

Test Began at Pressure on Gauge

First Hour Gallons Used Pressure on Gauge

Second Hour Gallons Used Pressure on Gauge

Third Hour Gallons Used Pressure on Gauge

3-Hour Total Gallons Used Pressure on Gauge

Test Completed at Pressure on Gauge

RESULTS Passed Failed

Remarks:

Contractor's Signature

Inspector's Signature

NOTE: TEST TO BE PERFORMED PER CITY OF DAYTONA BEACH STANDARD DETAILS

(LATEST EDITION)

CHECK OUT FORM 00865-1

SECTION 00865

CHECK OUT FORM

[ ] OWNER: THE CITY OF DAYTONA BEACH No. Copies [ ] ENGINEER: No. Copies [ ] ARCHITECT: No. Copies [ ] CONTRACTOR: No. Copies [ ] FIELD: No. Copies [ ] OTHER: No. Copies

PROJECT:

PURCHASE ORDER NO.: DATE:

DRAWING NO.: SPECIFICATION SECTION:

Name of equipment checked: ______________________________________________________________

Name of manufacturer of equipment: _______________________________________________________

1. The equipment furnished by us has been checked on the job by us. We have reviewed (where applicable) the performance verification information submitted to us by the Contractor.

2. The equipment is properly installed, except for items noted on page 00865-2.

3. The equipment is operating satisfactorily, except for items noted on page 00865-2.

4. The written operating and maintenance information (where applicable) has been presented to the Contractor, and gone over with him in detail. Five (5) copies of all applicable operating and maintenance information and parts lists have been furnished to him.

Checked by:

Name of Manufacturer's Representative Name of General Contractor

Signature of Person Performing Check-out Authorized Signature

Title Title

Address of Representative Date

Phone No. of Representative Name of Subcontractor

Date Checked Authorized Signature/Title/Date

CHECK OUT FORM 00865-2

Manufacturer's Representative Notations: Exceptions noted at time of check were:

Manufacturer's Representative to note adequacy of related equipment that directly affects operation, performance or function of equipment checked. (No comment presented herein shall indicate adequacy of related systems or equipment):

CERTIFICATE OF COMPLETED DEMONSTRATION FORM 00866-1

SECTION 00866

CERTIFICATE OF COMPLETED DEMONSTRATION FORM

[ ] OWNER: THE CITY OF DAYTONA BEACH No. Copies [ ] ENGINEER: No. Copies [ ] ARCHITECT: No. Copies [ ] CONTRACTOR: No. Copies [ ] FIELD: No. Copies [ ] OTHER: No. Copies

PROJECT:

PURCHASE ORDER NO.: DATE:

DRAWING NO.: SPECIFICATION SECTION:

NOTE TO CONTRACTOR:

Submit five copies of all information listed below for checking at least one week before scheduled demonstration of the Work. After all information has been approved by the City, give the City a Demonstration of Completed Systems as specified and have the City sign five copies of this form. Once signed, a written request for a final inspection of the system shall be made.

MEMORANDUM:

This memo is for the information of all concerned that the City has been given a Demonstration of Completed Systems on the work covered under this Specification Section. This conference consisted of the system operation, a tour on which all major items of equipment were explained and demonstrated, and the following items were given to the City:

(a) City's copy of Operation and Maintenance Manual for equipment or systems specified under this section containing approved submittal sheets on all items, including the following:

(1) Maintenance information published by manufacturer on equipment items.

(2) Printed warranties by manufacturer on equipment items.

(3) Performance verification information as recorded by the Contractor.

(4) Check-Out Memo on equipment by manufacturer's representative.

(5) Written operating instructions on any specialized items.

(6) Explanation of guarantees and warranties on the system.

(b) Prints showing actual "As-Built" conditions.

CERTIFICATE OF COMPLETED DEMONSTRATION FORM 00866-2

(c) A demonstration of the System in Operation and of the maintenance procedures which shall be required.

Name of General Contractor

By:

Authorized Signature

Title Date

Name of Subcontractor

By:

Authorized Signature

Operations and Maintenance Manual, Instruction Prints, Demonstration & Instruction in Operation Received:

THE CITY OF DAYTONA BEACH

By:

Authorized Signature

SUMMARY OF WORK 01010-1

SECTION 01010

SUMMARY OF WORK

PART 1 – GENERAL

1.01 SUMMARY OF WORK

Work under this project includes:

A. This project includes removal of approximately 1,300 LF of existing 10-inch Ductile Iron Pipe watermain along South Grandview Avenue between Harvey Avenue and International Speedway Boulevard. This project will include replacing all water services, water meters and meter boxes along this route. 1-inch services will also be provided at the edge of the right at the vacant lot locations to ensure no open cutting of the roadway for these lots after this project has been completed.

The existing water main is located along the eastern side of the roadway along South Grandview Avenue and the proposed water main will need to be installed approximately 3 feet to the west of the existing water main. Valves, main extensions and other various work will need to be provided with this watermain replacement to ensure that the switchover from the existing to the proposed goes smoothly. The Contractor shall refer to the notes located within the plan view sheets of the construction plans for any site-specific work related to this project.

1.02 WORK COVERED BY CONTRACT DOCUMENTS

A. The CONTRACTOR shall furnish all labor, materials, equipment, tools, services and incidentals to complete all Work required by these Specifications and as shown on the Drawings.

B. Omission of a specific item or component part of a system obviously necessary for the proper functioning of the system shall not relieve the CONTRACTOR of the responsibility of furnishing the item as part of the work at no additional cost to the

CITY.

C. The CONTRACTOR shall perform the Work complete, in place, and ready for continuous service, and shall include repairs, testing, permits, cleanup, replacements and restoration required as a result of damages caused during this construction.

D. The CONTRACTOR shall comply with all Federal, State and local laws, rules and regulations which are applicable to this Project.

1.03 REQUIRED NOTICES TO AGENCIES AND PUBLIC

SUMMARY OF WORK 01010-2

A. The CONTRACTOR shall provide advanced notice to affected businesses, property owners and utility customers of scheduled temporary utility service disruptions and changes in access. The CONTRACTOR shall provide alternative accommodations when required by the CITY.

1.04 SALVAGED MATERIALS

A. Unless otherwise noted in the Contract Documents, materials, equipment and supplies no longer needed as a result of the Work shall become property of the CONTRACTOR and shall be removed and disposed of by the CONTRACTOR in areas provided by the CONTRACTOR.

1.05 CONTRACTOR'S USE OF PREMISES

A. The CONTRACTOR shall assume full responsibility for the protection and safekeeping of products and materials stored at the job site. If additional storage or work areas are required, they shall be obtained by the CONTRACTOR at no additional cost to the CITY.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION

3.01 The CONTRACTOR shall review the site conditions and Contract Documents to verify the Summary of Quantities and Bid Schedule include all items and costs necessary to complete the Work prior to preparing and submitting a balanced and responsive bid.

MOBILIZATION 01011-1

SECTION 01011

MOBILIZATION

PART 1 – GENERAL

1.01 SUMMARY OF WORK

Work under this project includes:

A. The work specified in this Technical Provision consists of the preparatory work and operations in mobilizing for beginning work on the project and shall conform with the requirements of Section IO I of the Florida Department of Transportation Standard Specifications for Road and Bridge Construction, latest edition except as amended hereinafter.

1.02 WORK COVERED BY CONTRACT DOCUMENTS

A. Perform preparatory work and operations in mobilizing for beginning work on the project, including, but not limited to, those operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site and for the establishment of temporary offices, buildings, safety equipment and first aid supplies, and sanitary and other facilities. This item shall not include ongoing cost for above items.

B. Include the costs of all required permits, including the National Pollutant Discharge Elimination System permit, and any preconstruction expense necessary for the start of the work, excluding the cost of construction materials.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION

3.01 A pre-construction video shall be provided to the City that covers all aspects of existing roadway including adjacent houses, driveways, mailboxes, roadways, drainage structures and other adjacent items to the full extent of this project including any MOT that extends beyond the limits shown on the plans.

3.02 The Contractor shall install under the County's direction, signs conforming to the Specifications and sample provided in the General Conditions, as supplied by the County. The signs shall be the property of the Contractor for the duration of the project and shall be maintained by the Contractor to the satisfaction of the County Engineer. The Contractor shall be responsible for the relocation of the signs during the progress of construction as directed by the County Engineer.

MOBILIZATION 01011-2

2. The project signs shall be placed at locations designated by the City Project Engineer within the Right-of-Way, to be highly visible, at a position which will not obstruct pedestrian or vehicular traffic and at a location where they will not be a roadside hazard.

A. PROJECT SIGN CONSTRUCTION:

1. The project signs shall be constructed of wood or other substantial material (4' x 8') exterior grade plywood sheet with pressure treated 4" x 4" support posts and 2"x 4" cross braces if necessary).

2. The sign face shall be four feet horizontal by three feet vertical with four feet of clearance from the bottom of the sign face to ground for a total eight feet of sign height.

3. Upon completion of the contract, the Contractor shall remove and dispose of the sign and supports and restore the site to the satisfaction of the County Engineer.

B. PROJECT SIGN FACE PREPARATION:

1. The background shall be white.

2. The Lettering shall be black.

MAINTENANCE OF OPERATIONS 01014-1

SECTION 01014

MAINTENANCE OF OPERATIONS

PART 1 – GENERAL

1.01 DESCRIPTION

A. This Section covers the requirements for scheduling and performing the Work to keep existing essential facilities in continuous operation.

1.02 WORK SEQUENCE

A. The CONTRACTOR shall establish his work sequence based on the use of crews to facilitate completion of construction and testing within the allotted Contract Time.

B. CONTRACTOR shall discuss work sequence at Pre-Construction Conference.

C. Work shall be scheduled, sequenced, and performed in a manner which minimizes disruption to the operation and maintenance of existing facilities. The work shall be executed so the existing operating facilities shall not be jeopardized nor shall the efficiency of those facilities be reduced as a result of the execution of the work.

D. The CONTRACTOR shall keep existing facilities in operation unless otherwise specifically permitted in the Contract Documents or approved by the CITY in writing. The CONTRACTOR shall provide a minimum of 30 days advanced notice to the CITY of any needed system shutdown.

E. Approved shutdowns shall not begin until all materials are on-hand, pre-assembled and ready for installation. Upon commencement of the shutdown, the CONTRACTOR shall proceed with Work continuously, start to finish, until the Work is completed and the system is tested, cleared for service and ready for operation. If the CONTRACTOR completes all required work prior to the end of the specified shutdown period, the CITY may immediately place the system back in service.

F. Unless indicated otherwise, temporary roads, walks, protection of existing structures, pumping, piping, blind flanges, valves, equipment, power, lighting, controls, instrumentation, alarms, security devices, safety devices, etc. shall be provided by the CONTRACTOR whenever its work or interruption due to its work affects the existing facilities.

G. Operational functions or shutdown of the existing facilities required to facilitate CONTRACTOR’s operation will be done by the CITY’s personnel only.

H. The CITY’s operation and maintenance personnel will cooperate in every way that

MAINTENANCE OF OPERATIONS 01014-2

is practical in order to facilitate CONTRACTOR’s operation. However, certain shutdown and connections may only be permissible at times other than normal working hours such as nights or weekends. No additional payment will be made to the CONTRACTOR for any night, weekend or holiday premium or overtime payments.

I. If it becomes necessary for the proper operation or maintenance of facilities, the CITY may require the CONTRACTOR to reschedule an approved shutdown. The CONTRACTOR shall then reschedule its operations so there shall be no conflict with necessary operations or maintenance of facilities. The CONTRACTOR shall, within 2 working days, furnish the CITY a revised outage request and a plan for rescheduling the shutdown in accordance with the requirements of the construction schedule.

1.03 SUBMITTALS

A. Submit a detailed schedule and process description for proposed testing.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

MEASUREMENT AND PAYMENT 01025-1

SECTION 01025

MEASUREMENT AND PAYMENT

PART 1 – GENERAL

1.01 DESCRIPTION

A. This Section defines the method which will be used to determine the quantities of work performed, or materials supplied and establishes the basis upon which payment will be made.

1.02 ESTIMATED QUANTITIES

A. Where quantities are shown they are approximate and are given only as a basis of calculation upon which the award of the Contract is to be made. The CITY does not assume any responsibility for the final quantities, nor shall CONTRACTOR claim misunderstanding because of such estimate of quantities. Final payment will be made only for the satisfactorily completed quantity of each item.

1.03 MEASUREMENT STANDARDS

A. All work completed under the Contract shall be measured according to United

States Standard Methods.

1.04 METHOD OF MEASUREMENT

A. Measurement of Length: Unless otherwise specified for the particular items involved, all measurements of distance for items to be paid for on the basis of length shall be taken horizontally or vertically.

B. Measurement of Area: In the measurement of items paid for on the basis of area of finished work, the lengths and/or widths to be used in the calculations shall be the actual dimensions measured along the surface of the completed work within the neat lines shown or designated. At intersections, the measurement used for length of side area will be measured from the outside edge of the width allowed along the main trench.

C. Measurement of Weight of Asphaltic Concrete Materials: Measurements of the weight of Asphaltic Concrete Materials shall be made as provided in the latest edition of the Florida Department of Transportation, Standard Specifications for

Road and Bridge construction, except that the CONTRACTOR shall be responsible for writing and certifying the accuracy of truck tally tickets.

1.05 PAYMENT

MEASUREMENT AND PAYMENT 01025-2

A. Lump Sum Items: Where payment for items is shown to be paid for on a lump sum basis, no separate payment will be made for any item of work described herein and listed on the Bid Form required to complete the lump sum item.

B. Unit Price Items: Where payment for items is shown to be paid for on a unit price basis, separate payment will be made for the items of work described herein and listed on the Bid Form. Any related work not specifically listed, but required for satisfactory completion of the work, shall be considered to be included in the scope of the appropriately listed work items.

1.06 COSTS INCLUDED IN PAYMENT ITEMS

A. No separate payment will be made for the following items and the cost of such work shall be included in the applicable pay items of work:

1. Construction surveying

2. Clearing and grubbing

3. Trench and roadway excavation including necessary pavement removal, rock and cemented coquina excavation and disposal and excavation and removal of unsuitable soils and unsuitable materials of any nature except as otherwise specified

4. Paved and unpaved roadway restoration or replacement including but not limited to all disturbed areas within rights-of-way and adjacent traffic signal system components within the limits of Work except as otherwise specified

5. Dewatering and disposal of surplus water, prevention of sediment and erosion pollution and prevention of flooding

6. Temporary removal and replacement of fences and walls

7. Structural fill, backfill and grading

8. Replacement of unpaved roadways, grass and shrubbery plots

9. Cleanup

10. Foundation and borrow materials, except as hereinafter specified

11. Testing and placing system in operation

12. Any material and equipment required to be installed and utilized for tests

13. Concrete encasement

14. Pipe, structures, pavement replacement, restoration and/or appurtenances included within the limits of work, unless otherwise shown

15. Maintaining the existing quality of service during construction

16. Maintaining or detouring of vehicular and pedestrian traffic

17. Shoring, sheeting and worksite safety

18. Appurtenant work as required for a complete and operable system

B. Cleanup: CONTRACTOR’s attention is called to the fact the cleanup is considered a part of the construction work. Final payment will not be made until cleanup is essentially complete.

MEASUREMENT AND PAYMENT 01025-3

C. Work Outside Authorized Limits: No payment will be made for work constructed outside the authorized limits of work.

1.07 APPLICATIONS FOR PAYMENT

A. Applications for payment shall be prepared by the CONTRACTOR and submitted to the CITY in accordance with the schedule established by the Conditions of the Contract Documents.

B. Applications for payment shall be submitted in the number and format established by the CITY at the Pre-Construction Conference. The form shall be completely filled out and executed by an authorized representative of the CONTRACTOR.

Supporting data such as schedules of stored materials shall be attached to each copy of the application.

1.08 CHANGE ORDER PROCEDURE

A. As defined in the General Conditions, a Change Order is a written order to the

CONTRACTOR signed by the CITY authorizing an addition, deletion or revision in the Work, or an adjustment in the Contract Price or the Contract Time, which is issued after the execution of the Contract. The following procedure shall be used in processing Change Orders:

1. For Additions to the Work: The CITY shall issue a written order to the

CONTRACTOR directing him to accomplish the additional work. The CONTRACTOR shall review the order and, if he feels the additional work entitles him to additional payment or additional time, he may submit a Change

Order.

2. For Deletions from the Work: The CITY shall issue a written order to the

CONTRACTOR directing him to make the change. If the CITY feels the Contract price should be reduced as a result of the change, the CITY shall make a claim for the reduction.

3. Cost of the changes in the work shall be determined in accordance with the requirements of the Contract Documents.

PART 2 - PRODUCTS (NOT USED)

PART 3 – EXECUTION

3.01 BID ITEMS

Bid Item No. 1 – Mobilization/Demobilization

MEASUREMENT AND PAYMENT 01025-4

Definition. Mobilization shall be the preparatory work and operations in mobilizing for beginning work on the project, including, but not limited to, those operations necessary for the movement of personnel, equipment, supplies and incidentals to the project site, and for the establishment of temporary offices, storage buildings, safety equipment and first aid supplies, sanitary and other facilities, as required by the Contract Documents and applicable laws and regulations. The costs of bonds, required insurance, permits and any other preconstruction expenses necessary for the start of the work, excluding the cost of construction materials, shall also be included in this item.

Demobilization shall be the work of removing temporary facilities from the site.

Mobilization/Demobilization shall be limited to a maximum of five percent (5%) of the Bid Price.

Payment. Partial payments for this item will be made in accordance with the following schedule:

Percent of Original

Contract

Amount Earned

Allowable Percent of the

Lump Sum Price for the

Item

After Contract Execution 25

10 50

25 75

50 100

These payments will be subject to the standard retainage provided in the Agreement. Payment of the retainage will be made after completion of the work and demobilization.

Bid Item No. 2 – Survey/Layout, As-Builts/Certified Record Drawings

Payment. Payment of the applicable lump sum price shall be full compensation for furnishing all plant, labor, materials and equipment necessary to submit the “As-Built” Drawings, certified by a registered land surveyor or professional engineer. The Contractor’s attention is directed to Section

01720, Paragraph 1.02, which addresses the requirements and for maintaining up-to-date “As-

Built” Drawings. Final payment will be withheld until an acceptable set of “As-Built” Drawings are delivered to the City.

Bid Item No. 3 – Dewatering

Payment. Payment of the applicable lump sum price shall be full compensation for furnishing all equipment required or needed for the Contractor to dewater the stormwater pond prior to any construction activities beginning on site. The Dewatering process must be approved by the City of Daytona Beach prior to dewatering activities commencing. Contractor to provide a SWPPP

(Stormwater Pollution Prevention Plan) at pre-construction meeting. The equipment needed for the Dewatering must be suitable for residential areas due to the projects proximity to residential housing along Oak and Walnut.

Bid Item No. 4 – Maintenance of Traffic

Payment. The City of Daytona Beach has added an allowance to this Bid Item of $20,000.00 to

MEASUREMENT AND PAYMENT 01025-5

compensate the contractor for furnishing all equipment required or needed for the Contractor to set-up and maintain the Maintenance of Traffic throughout the entire construction process for this project. The Maintenance of Traffic plan will need to be accepting by the City of Daytona

Beach Public Works Department prior to any Construction activities beginning on site.

Bid Item No. 5 – Demo Existing Asphalt (assume 8’ wide trench with service cut-outs)

General. For purposes of payment, pavement classification will be based on the type of surface, or, if special details are shown, in accordance with the details. No payment will be made under this item for pavement replacement within the limits of Special Crossings or other lump sum pay items.

Payment. Payment shall be made at the applicable unit price per square yard for the actual quantity of asphalt satisfactorily replaced. Such price and payment shall be full compensation for furnishing all plant, labor, materials, equipment and incidentals and constructing the applicable item including cleanup.

Bid Item No. 6 – Remove/Replace Existing Sidewalk (5’ x 5’ panels)

General. For purposes of payment, pavement classification will be based on the type of surface, or, if special details are shown, in accordance with the details. Concrete driveways six inches or greater in thickness, or of any thickness if reinforced, shall be considered as concrete pavement.

No payment will be made under this item for pavement replacement within the limits of Special

Crossings or other lump sum pay items.

Payment. Payment shall be made at the applicable unit price per Square Yard (SY) for the actual quantity of sidewalk panels remove and satisfactorily replaced. Such price and payment shall be full compensation for furnishing all plant, labor, materials, equipment and incidentals and constructing the applicable item including cleanup.

Bid Item No. 7 – 10-inch 45-degree bends

Payment. Payment will be made as a unit price for the installation of each (EA) 10-inch 45-degree bends as shown on the South Grandview Avenue – Internation Speedway Boulevard to

Harvey Avenue Utilities Upgrade plan. Payment will be full compensation for all materials, labor, equipment, and work necessary to provide the appropriately sized 45-degree bends in accordance with the contract plans and specifications.

Bid Item No. 8 – 10-inch Tee

Payment. Payment will be made as a unit price for the installation of each (EA) 10-inch Tee as shown on the South Grandview Avenue – Internation Speedway Boulevard to Harvey Avenue

Utilities Upgrade plan. Payment will be full compensation for all materials, labor, equipment, and work necessary to provide the appropriately sized Tee’s in accordance with the contract plans and specifications.

MEASUREMENT AND PAYMENT 01025-6

Bid Item No. 9 – 10-inch Insert-A-Valve

Payment. Payment will be made as a unit price for the installation of each (EA) 10-inch Insert-a-

Valve (or approved equivalent) as shown on the South Grandview Avenue – Internation Speedway

Boulevard to Harvey Avenue Utilities Upgrade plan. Payment will be full compensation for all materials, labor, equipment, and work necessary to provide the appropriately sized Insert-a-

Valve’s in accordance with the contract plans and specifications.

Bid Item No. 10 – Fire Hydrant Assembly Replacements

Payment. Payment will be made as a unit price for the installation of each (EA) Fire Hydrant

Replacement per the City of Daytona Beach Standards as shown on the South Grandview Avenue

– Internation Speedway Boulevard to Harvey Avenue Utilities Upgrade plan. Payment will be full compensation for all materials, labor, equipment, and work necessary to provide installation of the

Fire Hydrant’s in accordance with the contract plans and specifications.

Bid Item No. 11 – 10-inch Watermain (WM) Valve

Payment. Payment will be made as a unit price for the installation of each (EA) 10-inch

Watermain Valve as shown on the South Grandview Avenue – Internation Speedway Boulevard to Harvey Avenue Utilities Upgrade plan. Payment will be full compensation for all materials, labor, equipment, and work necessary to provide the appropriately sized Watermain Valve in accordance with the contract plans and specifications.

Bid Item No. 12 – 6-inch Watermain (WM) Valve

Payment. Payment will be made as a unit price for the installation of each (EA) 6-inch

Watermain Valve as shown on the South Grandview Avenue – Internation Speedway Boulevard to Harvey Avenue Utilities Upgrade plan. Payment will be full compensation for all materials, labor, equipment, and work necessary to provide the appropriately sized Watermain Valve in accordance with the contract plans and specifications.

Bid Item No. 13 – 10-inch x 6-inch reducer

Payment. Payment will be made as a unit price for the installation of each (EA) 10-inch x 6-inch reducer as shown on the South Grandview Avenue – Internation Speedway Boulevard to Harvey

Avenue Utilities Upgrade plan. Payment will be full compensation for all materials, labor, equipment, and work necessary to provide the appropriately sized reducer in accordance with the contract plans and specifications.

Bid Item No. 14 – 10-inch x 2-inch reducer

Payment. Payment will be made as a unit price for the installation of each (EA) 10-inch x 2-inch reducer as shown on the South Grandview Avenue – Internation Speedway Boulevard to Harvey

Avenue Utilities Upgrade plan. Payment will be full compensation for all materials, labor, MEASUREMENT AND PAYMENT 01025-7 equipment, and work necessary to provide the appropriately sized reducer in accordance with the contract plans and specifications.

Bid Item No. 15 – 2-inch Type SP-9.5 Asphalt

Payment. Payment shall be made at the applicable unit price square yard for the actual quantity of 2-inch Type SP-9.5 Asphalt satisfactorily installed. This type of asphalt shall be installed per the City of Daytona Beach Standards. Such price and payment shall be full compensation for furnishing all plant, labor, materials and equipment necessary to provide the required 2-inch

Type SP-9.5 Asphalt called out in the Specifications and as shown on the Detail Drawings of this set.

Bid Item No. 16 – 6-inch Stabilized Subgrade of 6-inch stabilized subgrade satisfactorily installed. This stabilized subgrade shall be installed per the City of Daytona Beach Standards. Such price and payment shall be full compensation for furnishing all plant, labor, materials and equipment necessary to provide the required 6-inch stabilized subgrade called out in the Specifications and as shown on the Detail Drawings of this set.

Bid Item No. 17 – 8-inch Crushed Concrete of 8-inch Crushed Concrete satisfactorily installed. This crushed concrete shall be installed per the City of Daytona Beach Standards. Such price and payment shall be full compensation for furnishing all plant, labor, materials and equipment necessary to provide the required 8-inch crushed concrete called out in the Specifications and as shown on the Detail Drawings of this set.

Limerock cannot be substituted in this instance due to the high-water table at the project location.

Bid Item No. 18 – 10-inch DIP Water Main Installation

Payment. Payment shall be made at the applicable unit price Linear Foot (LF) for the furnishing and installing of the 10-inch DIP water main as shown on the South Grandview Avenue –

Internation Speedway Boulevard to Harvey Avenue Utilities Upgrade plan. The payment shall be full compensation for furnishing all plant, labor, materials and equipment necessary to install the

10-inch DIP water main per the City of Daytona Beach Standards and specifications.

Bid Item No. 19 – 6-inch DIP Water Main Installation and installing of the 6-inch DIP water main as shown on the South Grandview Avenue –

Internation Speedway Boulevard to Harvey Avenue Utilities Upgrade plan. The payment shall be

MEASUREMENT AND PAYMENT 01025-8

6-inch DIP water main per the City of Daytona Beach Standards and specifications.

Bid Item No. 20 – 2-inch DIP Water Main Installation and installing of the 2-inch DIP water main as shown on the South Grandview Avenue –

Internation Speedway Boulevard to Harvey Avenue Utilities Upgrade plan. The payment shall be

2-inch DIP water main per the City of Daytona Beach Standards and specifications.

Bid Item No. 21 – 1-inch Polytube and installing of the 1-inch polytube main as shown on the South Grandview Avenue – Internation

Speedway Boulevard to Harvey Avenue Utilities Upgrade plan. The payment shall be full compensation for furnishing all plant, labor, materials and equipment necessary to install the 1-inch polytube per the City of Daytona Beach Standards and specifications.

Bid Item No. 22 – Installation of ¾” Water Meters (meters provided by City of Daytona

Beach)

Payment. Payment will be made as a unit price for the installation of each (EA) ¾” Water Meters as shown on the South Grandview Avenue – Internation Speedway Boulevard to Harvey Avenue

Utilities Upgrade plan. Payment will be full compensation for all labor, equipment, and work necessary to provide the installation of the ¾” Water Meters supplied by the City of Daytona

Beach in accordance with the contract plans and specifications.

Bid Item No. 23 – Installation of 1” Water Meters (meters provided by City of Daytona

Beach)

Payment. Payment will be made as a unit price for the installation of each (EA) 1” Water Meters as shown on the South Grandview Avenue – Internation Speedway Boulevard to Harvey Avenue

Utilities Upgrade plan. Payment will be full compensation for all labor, equipment, and work necessary to provide the installation of the 1” Water Meters supplied by the City of Daytona Beach in accordance with the contract plans and specifications.

Bid Item No. 24 – Installation of Meter Boxes (Contractor to Provide)

Payment. Payment will be made as a unit price for the installation of each (EA) Meter Box as shown on the South Grandview Avenue – Internation Speedway Boulevard to Harvey Avenue

Utilities Upgrade plan. Payment will be full compensation for all labor, equipment, and work necessary to provide the installation of the Meter Box in accordance with the contract plans and specifications.

MEASUREMENT AND PAYMENT 01025-9

Bid Item No. 25 – Removal of Existing DIP Water Main all labor, materials and equipment necessary to provide the removal of the existing water mains as shown on the South Grandview Avenue – Internation Speedway Boulevard to Harvey Avenue

Utilities Upgrade plan. The removal of the water main system shall be removed per City of

Daytona Beach standards.

Bid Alternate #1 – 10-inch PVC Water Main and installing of the 10-inch PVC water main as shown on the South Grandview Avenue –

Internation Speedway Boulevard to Harvey Avenue Utilities Upgrade plan. This shall be bid as an alternate which the City has a right to include or not to include in the project at the time of bid opening review. The payment shall be full compensation for furnishing all plant, labor, materials and equipment necessary to install the 10-inch DIP water main per the City of Daytona Beach

Standards and specifications.

SCHEDULE OF VALUES & PAYMENT APPLICATIONS 01026-1

SECTION 01026

SCHEDULE OF VALUES & PAYMENT APPLICATIONS

PART 1 – GENERAL

1.01 DESCRIPTION

A. Scope of Work: Submit Application for Payment to the CITY in accordance with schedule established by Contract Documents.

B. Related Requirements Described Elsewhere:

1. Contract Documents

2. Application for Payment Form

3. Schedule of Values

4. Contract Closeout

5. Project Record Documents

1.02 FORMAT AND DATA REQUIRED

A. Submit applications typed on form provided by the CITY, “Project Payment Authorization Form”, with itemized data typed on 8-1/2 inch x 11 inch or 8-1/2 inch x 14 inch white paper continuation sheets. This sheet will be used as a cover sheet for all payment applications.

B. Provide itemized data on Continuation Sheets, submittals schedule and monthly progress schedule.

C. Where Work is separated into phases requiring separate payment, provide sub-schedules showing values correlated with each project phase.

1.03 PREPARATION OF APPLICATION FOR EACH PROGRESS PAYMENT

A. Application Form:

1. Fill in required information, including that for Change Orders executed prior to date of submittal of application.

2. Fill in summary of dollar values to agree with respective totals indicated on continuation sheets.

3. Execute certification with signature of a responsible officer of Contract firm.

B. Continuation Sheets:

SCHEDULE OF VALUES & PAYMENT APPLICATIONS 01026-2

1. Fill in total list of all scheduled component items of work, with item number and scheduled dollar value for each item.

2. Fill in dollar value in each column for each scheduled line item when work has been performed or products stored. Round off values to nearest $0.01, or as specified for Schedule of Values.

3. List each Change Order executed prior to date of submission, at the end of the Continuation Sheets. List by Change Order Number and description, as for an original component item of work.

4. To receive approval for payment on component material stored on site, submit copies of the original invoices with the Application for Payment.

1.04 SUBSTANTIATING DATA FOR PROGRESS PAYMENTS

A. When the CITY requires substantiating data, CONTRACTOR shall submit suitable information, with a cover letter identifying:

1. Project

2. Application number and date

3. Detailed list of enclosures

4. For stored products:

a. Item number and identification as shown on application

b. Description of specific material

B. Submit one (1) copy of data and cover letter for each copy of application.

C. Submit requisite number of photographs with each application.

D. List the name and address of all Subcontractors and Suppliers who have performed work or provided supplies or material for each application.

E. Submit certified payroll sheets for CONTRACTOR’s forces and all Subcontractors for the month preceding the submitted application as required.

F. Submit revised monthly progress schedules with each month’s Application for Payment, including cash flow projections.

G. The CONTRACTOR shall maintain an updated set of drawings to be used as record drawings in accordance with the Contract Documents. AS A PREREQUISITE FOR

SCHEDULE OF VALUES & PAYMENT APPLICATIONS 01026-3

PAYMENT OF MONTHLY PROGRESS PAYMENTS, THE CONTRACTOR IS

TO EXHIBIT THE UPDATED RECORD DRAWINGS FOR REVIEW BY THE

CITY.

1.05 PREPARATION OF APPLICATION FOR FINAL PAYMENT

A. Fill in Application Form as specified for progress payments.

1.06 SUBMITTAL PROCEDURE

A. Submit Applications for Payment to the CITY on average once per 30 day period.

Review the percents complete with the CITY to resolve any conflicts or discrepancies.

1. Prior to submittal to the CITY, pay application quantities shall be reviewed and approved by City Inspectors.

B. Submit Applications for Payment in electronic format (PDF).

C. When the CITY finds Application properly completed and correct, the CITY will process for payment.

PART 2 – PRODUCTS (NOT USED)

COORDINATION 01040-1

SECTION 01040

COORDINATION

PART 1 – GENERAL

1.01 PROJECT COORDINATION

A. The CONTRACTOR will provide for the complete coordination of the construction efforts. This will include, but not necessarily be limited to, coordination of the following:

1. The work of subcontractors.

2. The flow of material and equipment from suppliers.

3. The effort of equipment manufacturers during test and checkout.

4. Interrelated work with public utilities companies.

5. The interrelated work with the CITY where tie-ins to existing facilities are required.

6. The effort of independent testing agencies.

7. Maintain operation of the existing facilities during tie-ins to piping/equipment.

1.02 DEWATERING AND INSPECTION SURVEY/PLAN

A. Prior to starting fieldwork and within seven calendar days after the Notice to Proceed date, the CONTRACTOR’S Project Coordinator will provide the City’s Project Manager with the Dewatering and Inspection/Survey Plan. The Plan will include, but not be limited to, the sequence of dewatering, entry/exit ports to be used for pipe marking and field evaluation, the direction that the pipeline will be inspected/surveyed, the locations where ventilation will be introduced, and dates and times in which field work will be performed. This Plan will also include the names of the inspection/surveying crew and the company that they work for, the projected start and finish dates, times and progression of each inspection/survey, the number of persons involved in each inspection/survey, and the entry/exit ports that will be used by each inspection/survey crew. The CONTRACTOR will coordinate his field activities with the City’s Project Manager to ensure efficient and coordinated progress.

2.01 REFERENCE

A. Section 02240: Dewatering (During Construction)

PART 2 – PRODUCTS (NOT USED)

CUTTING AND PATCHING 01045-1

SECTION 01045

CUTTING AND PATCHING

PART 1 – GENERAL

1.01 DESCRIPTION OF WORK

A. This Section establishes general requirements pertaining to cutting (including excavating), fitting and patching of the Work required to:

1. Uncover Work to provide for installation

2. Remove and replace Work not conforming to requirements of the Contract

Documents

3. Rework existing items to provide for new construction

1.02 QUALITY ASSURANCE

A. Perform all cutting and patching in strict accordance with pertinent requirements of these Specifications and, in the event no such requirements are determined, in conformance with the ENGINEER's written direction.

B. Codes and standards for work of this Section will be the same as for the pertinent sections of this Specification.

1.03 SUBMITTALS

A. Request for ENGINEER's Consent

1. Prior to cutting any item which affects structural safety, submit written request to the ENGINEER for permission to proceed with cutting.

2. Should conditions of the Work, or schedule, indicate a required change of materials or methods for cutting and patching, so notify the ENGINEER and secure his written permission prior to proceeding.

B. Notice to the ENGINEER.

1. Submit written notice to the ENGINEER designating time the Work will be uncovered to provide for the Engineer's observation.

PART 2 – PRODUCTS

2.01 MATERIALS

CUTTING AND PATCHING 01045-2

A. Materials used in the replacement of existing work and the construction of work in conjunction with cutting and patching will be new unless prior approval from the ENGINEER has been obtained to re-use existing materials.

2.02 FABRICATION

A. The materials and methods used in the fabrication of items required under this Section will comply with the individual sections of this Specification that have to do with new construction.

2.03 PAINTING

A. Painting provided under this Section will comply with Sections 09900.

PART 3 – EXECUTION

3.01 CONDITIONS

A. Examination

1. Examine existing conditions, including elements subject to movement or damage during cutting, excavating, backfilling, and patching.

2. After uncovering the Work, inspect conditions affecting installation of the new Work.

B. Discrepancies

1. If uncovered conditions are not as anticipated, immediately notify the ENGINEER and secure needed directions.

2. Do not proceed in areas of discrepancy until all such discrepancies have been fully resolved.

3.02 PREPARATION PRIOR TO CUTTING

A. Provide all required protection including, but not necessarily limited to, shoring, bracing, and support to maintain structural integrity of the Work.

3.03 PERFORMANCE

A. Perform all required excavating and backfilling as required under pertinent Sections of these Specifications. Perform cutting and demolition by methods which will prevent damage to other portions of the Work and will provide proper surfaces to receive installation or repair and new work. Perform fitting and adjustment of products to provide finished installation complying with the specified tolerances and finishes.

FIELD ENGINEERING 01050-1

SECTION 01050

FIELD ENGINEERING

PART 1 – GENERAL

1.01 SECTION INCLUDES

A. Provide field engineering service for project as indicated on Drawings and specified in this Section.

1.02 QUALIFICATIONS OF SURVEYOR OR ENGINEER

A. Florida Registered Engineer or Land Surveyor.

1.03 SURVEY REFERENCE POINTS

A. All elevations are referred to NGVD 1988. Establish all vertical and horizontal controls required for construction.

B. Locate and protect control points prior to starting site work, and preserve permanent reference points during construction.

1. Make no changes or relocations of such points without prior written notice to

ENGINEER.

2. Report to ENGINEER when any reference point is lost or destroyed, or requires relocation because of necessary changes in grades or locations.

3. Require surveyor to replace control points which may be lost or destroyed.

Establish replacements based on original survey control.

1.04 PROJECT SURVEY REQUIREMENTS

A. Establish a minimum of two (2) permanent bench marks on the project site, all referenced to data established by survey control points. Record locations, with horizontal and vertical data, on Project Record Documents.

B. Establish lines and levels, locate and lay out, by instrument and similar appropriate means.

1. Site improvements

2. Building foundation, column locations, floor levels and roof levels

3. Controlling lines and levels required for mechanical and electrical trades

C. Verify layouts by same methods from time to time

1.05 RECORDS

FIELD ENGINEERING 01050-2

A. Maintain a complete, accurate log of control and survey work as it progresses.

B. On completion of foundations and major site improvements, prepare a certified survey showing finished dimensions, locations, angles and elevations of construction.

1.06 SUBMITTALS

A. Submit name and address of surveyor or professional engineer to ENGINEER.

B. On request of ENGINEER, submit documentation to verify accuracy of field survey work.

C. Submit certificate signed and sealed by a State of Florida Registered Engineer or Land Surveyor certifying that elevations and locations of improvements are in conformance with Contract Documents. Refer to Section 01720 – As Built Record Documents.

PART 2 – PRODUCTS (NOT USED)

SCHEDULE OF VALUES & PAYMENT APPLICATIONS 01200-1

SECTION 01200

PROJECT MEETINGS AND VIDEO

PART 1 – GENERAL

1.01 DESCRIPTION

A. Scope of Work: The CONTRACTOR is responsible for conducting project meetings and videoing the project area to document pre-construction conditions.

1.02 PRE-CONSTRUCTION CONFERENCE

A. A pre-construction conference will be held prior to beginning any work under the Contract. The ENGINEER will schedule the conference in consultation with the CITY and the CONTRACTOR.

B. The CONTRACTOR shall submit an anticipated progress schedule, a preliminary schedule of shop drawing submittals and a preliminary schedule of values at the pre-construction conference.

C. Attendees shall…