Sources_Sought_-_Survey_Questions_-_CAHA_Trail_1.docx
DOCX document 26 KB Posted
- Attached to
- CAHA 158701 Lighthouse Road Trail Federal contract opportunity
- Solicitation number
- 140P2023R0038
About this file
This document is a Sources Sought Questionnaire for a proposed 1.25 mile multiuse trail project located in Cape Hatteras, North Carolina. The National Park Service is seeking information from contractors to determine the appropriate solicitation method for the project. Responses are due by January 25, 2023.
The trail will have a 10 to 12 foot paved surface with some sections reduced to 8 feet to accommodate natural resources. It will start at the intersection of NC Highway 12 and run parallel to Lighthouse Road before continuing along a boardwalk path toward the Cape Hatteras Lighthouse and visitor center. Five locations for rest areas will be integrated along the alignment. The project requires compliance with accessibility standards and protection of adjacent wetlands. Insurance, performance and payment bonds, and a construction warranty will be required. Respondents are asked to provide details of relevant past project experience, bonding and insurance capacity, and commitment to submitting a proposal if a design-bid-build solicitation is issued in June 2023 for completion by May 2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A12_SSN_CAHA_TRAIL_vF_1.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sources Sought Questionnaire – Design Bid-Build
Project Description and PMIS: CAHA 158701 This proposed multiuse trail is approximately 1.25 miles with a 10 to 12-foot multipurpose paved trail with sections reduced to 8-feet, if required, to accommodate natural resources and other site/budgetary constraints. The trail starts from the intersection of NC Highway 12 and runs parallel to Lighthouse Road up to Forest Road and then along the move path toward the Cape Hatteras Lighthouse and Cape Hatteras visitor center. A 5-feet wide grass shoulder separates the trail from the road. The trail’s cross section, slopes, alignment, and surface must meet the Architectural Barriers Act (ABA) requirements. The adjacent road will need to allow single lane tracking with maintenance of traffic during the construction period. Wetlands adjacent to the proposed trail will need to be protected. The project will integrate approximately five locations for wayside exhibits/rest areas along the trail alignment.
Survey Questions:
We are interested in knowing the depth of your company’s interest in this project to help us determine the appropriate solicitation method. Your company must complete this survey and submit it on time to be considered in the market research being conducted, and in the making of any small business set-aside determination for this requirement.
1. What is your experience as the Prime contractor for Federal Government constructions contracts?
1. What is your experience as a Subcontractor for Federal Government constructions contracts?
1. How does your firm intend on complying with local construction building licensing and permitting for North Carolina?
1. This project will require insurance and Performance and Payment Bonds. What is your firms *stated bonding capacity (no letters required)?
1. This project will contain Division 1 submittal requirements that must be completed prior to receiving the Notice to Proceed. How is your firm prepared for this requirement?
1. What is your company’s recent experience with concrete and asphalt paved trail construction (please list the last 5 projects, location, year construction finished, pavement material, and length)?
1. What is your company’s experience using concrete slipform paving techniques? (Please list the last 5 projects, location, year construction finished, pavement material, and length)?
1. What is your company’s experience protecting wetlands during construction?
1. This project will contain clauses for Construction Warranty and Liquidated damages. How is your firm prepared for this requirement?
1. What estimated percent of this work will your company self-perform?
9. ☐100%
9. ☐about 75%
9. ☐about 50%
9. ☐about 25%
9. ☐about 15%
1. What is your company’s commitment to submit a proposal for this project if and when a Design-Bid Build solicitation is posted?
10. ☐100%
10. ☐50%
10. ☐Less than 50%
1. What will influence your company’s commitment for submitting a proposal for this project? *Please check all applicable boxes.
11. ☐Solicitation posting (approximately June 2023)?
11. ☐Schedule completion date for all construction by May 2024.
11. ☐Details of the specs and drawings for the Request for Proposal?
11. ☐Other commitments/contracts?
11. ☐Other?
1. Under the listed NAICS 237310, Small Business Administration (SBA) is your company certified as the following *Please check all applicable boxes:
12. ☐Historically Underutilized Business Zone (HUBZone),
12. ☐Veteran-Owned Small Businesses (VOSB),
12. ☐Service-Disabled Veteran-Owned Small Businesses (SDVOSB),
12. ☐SBA certified Woman Owned Small Business (WOSB),
12. ☐Economically Disadvantaged Woman Owned Small Business (EDWOSB)
12. ☐Other:
1. What is your company’s cage code?
1. Who is your point of contact and what is the telephone number and email address?
1. Did you include information demonstrating experience and capability on projects of same or similar size, scope and magnitude, and constructed under similar conditions?
Submittal Due Date/Time: Noon Mountain Time, 01/25/2023
Submit To: Zaira_Lupidi@NPS.Gov, Michael_Stanard@NPS.Gov