This document appears to be a Sources Sought Market Survey for the "FY25 DHA SRM Facility Repairs, Building 1585, Yokota Air Base, Japan" project. The U.S. Army Corps of Engineers, Japan District (POJ) is conducting market research for this upcoming Design-Bid-Build (DBB) requirement. The purpose is to identify capable sources to assist with acquisition planning. This is not a solicitation, and the government will not pay for any information provided in response.
The project involves interior facility repairs to Building 1585 at Yokota Air Base in Japan. The work will be phased, with Phase 1 focused on mechanical upgrades including chiller and air handling unit replacements. Subsequent phases will involve architectural, mechanical, electrical, and fire protection work, primarily during non-clinic hours. The market survey is seeking information from firms capable of performing this type of work at the Yokota Air Base location.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought DHA 1585 Draft Drawings.pdf | ||
| Sources Sought DHA 1585 Draft Specs.pdf | ||
| Sources Sought W912HV25Z0002 DHA 1585.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W
W W W
GTV
W W
W
GTV
WWW
W
UG/P
UG/P
WP WP WP WP
U G
/S
E
FUEL TANK
EMH
EMH
EMH
EMH
EMH
EMH
EMH EMH
EMH
EMH
E
E
E
E
E
TMH
TMH
E
E
E
EMH
E
TMH
EMH
E
EHH
EHH
E
EHH
EHH
EHH
GI
CB
CB
CB
CB
CB
CBCB
CB
BLDG 1585
GI
GI
GI
GI
CB
CB
CB
CB
CB CB
CB
GIGI
GI
GI
GI
GI
GI
GI
GI
T
T
T
GI
GI
EHH
CB
GI
GI
CB
CB GI
T1584
GAZEBO
M cG
UIRE AVENUE
SE
R
VI
C
E/
FI
R E
AC
C
ES
S
R O
AD
US Army Corps of Engineers ®
IS
O
A
SHEET ID
SO
LI
C
IT
AT
IO
N N
O
D
ES
IG
N
ED
B
Y:
D
ES
C R
IP
TI
O N
M
AR
K
SI
ZE
SU
BM
IT
TE
D B
Y:
D
AT
E
C O
N
TR
AC
T
N O
C
H
EC
KE
D
B Y:
D R
AW
N
B Y:
IS
SU
E D
AT
E:
R
Q
P
N
M
L
K
J
H
G
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
YA
B1
5G
C
1.
dw g
FI
LE
N
AM
E
N
O
VE
M
BE
R
W
2H V-
-B
-0
A H
L- G
A E
JV
, L
LC
M ak ai
T ow er , S ui te
Bi sh op
S tre et H on ol ul u, H aw ai i 9
(8
)5
-9
R
TA
C
O N
TR
AC
T D
O C
U M
EN
TS
(C O
D E
6)
YO
KO
TA
A
IR
B
AS
E, F U
SS
A, J
AP
AN
IN
TE
R
IO
R
F
AC
IL
IT
Y R
EP
AI
R S, B U
IL
D
IN
G
U
S
AR
M Y
C O
R
PS
O F
EN
G
IN
EE
R S
J
AP
AN
D
IS
TR
IC
T
A
PO
A P
3-
GENERAL SEQUENCE OF WORK AND PHASING
PARAMETERS
PH-1 (PHASE 1)
MECHANICAL
· UPGRADES INCLUDING REPLACEMENT OF CHILLER, AND AHU 1,
3, 4, AND 5.
· INSTALL NEW AIR COOLED CHILLER AND ASSOCIATED PIPING
AND PUMPS
ELECTRICAL
· NEW CUBICLE TRANSFORMER AND UNDERGROUND
INFRASTRUCTURE
· NEW EQUIPMENT PAD FOR CUBICLE TRANSFORMER
STRUCTURAL
· NEW EXTERIOR CHILLER ENCLOSURE FOUNDATION.
CIVIL
· NEW EXTERIOR CHILLER ENCLOSURE
· NEW CONC SIDEWALK, STOOP AND CURB & GUTTER
· WATER LINE RE-ROUTING
· AC PAVEMENT AND SODDING RESTORATION
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED FOR HVAC EQUIPMENT
REPLACEMENT
NOTES
1. CONTRACTOR SHALL SCHEDULE WORK TO CAUSE THE LEAST AMOUNT
OF INTERFERENCE WITH ACTIVITY OPERATIONS.
2. CONSTRUCTION SEQUENCING PLAN SUMMARIZES THE GENERAL
SEQUENCE OF WORK TO ACCOMMODATE THE BUILDING PLANNING AND
OPERATIONAL REQUIREMENTS DURING CONSTRUCTION. CONTRACTOR
SHALL PLAN THE CONSTRUCTION WORK TO ACCOMMODATE THE
CONSTRUCTION SEQUENCES SHOWN. THE CONTRACTOR MAY PROPOSE
VARIATIONS TO THE WORK SEQUENCES TO ACCOMMODATE
CONSTRUCTION EFFICIENCIES. ANY PROPOSED DEVIATION FROM THE
PHASING PLAN SHALL BE SUBMITTED TO THE CONTRACTING OFFICER
FOR CONSIDERATION AND APPROVAL.
3. CONTRACTOR'S CONSTRUCTION LAYDOWN AREAS (STAGING AREAS)
AND ON-SITE CONSTRUCTION OFFICE SHALL BE LIMITED TO THE
GENERAL AREAS SHOWN ON THE CONTRACTOR STAGING, FENCING, AND
FIRE EGRESS SITE PLAN ON SHEET C-001. CONFIRM ACTUAL LIMITATIONS
OF THE STAGING AREA WITH THE CONTRACTING OFFICER. DEVIATIONS
FROM THE SELECTED AREA SHALL BE COORDINATED WITH THE
CONTRACTING OFFICER.
4. HAULING OF CONSTRUCTION MATERIALS SHALL BE LIMITED TO THE
ROUTES DESIGNATED ON THE HAUL ROUTE PLAN. ENTRY TO THE BASE
SHALL BE LIMITED TO THE SUPPLY ENTRY GATE. DEVIATIONS FROM THE
HAUL ROUTE PLAN TO ACCOMMODATE CONSTRUCTION MEANS AND
METHODS AND/OR DELIVERY AND TRANSFERRING OF MATERIALS SHALL
BE COORDINATED WITH AND APPROVED BY THE CONTRACTING OFFICER.
5. REFER TO SPECIFICATION 01 32 01.00 10 FOR COLORED PHASING PLANS
PLAN
NORTH
1050 25m15 20
SCALE: 1:150
SITE PHASING PLANA1
M .N
AK
AI
M A
L.
M
O R
AD
A
C .M
AR
TI
N
AH
L-
G
AE
J V, L
LC
SI
TE
P H
AS
IN
G P
LA
N
GC101
B1585
W912HV-24-B-0002 Attachment 01 32 01.00 10-A Page 2 (AM-0001)
The exterior work will likely be renamed to PH-0 (Phase 0) as it is not necessarily associated with the PH-1 (Phase 1) work at the interior of the building. The work shown on this sheet may be conducted independent of the work at the interior, although the installation of the AHUs must occur in the winter or early spring seasons, between NOVEMBER - MARCH
DRAFT
ANTEROOM
ANTEROOMCONTRACTORS ACCESS
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINAK-2031GREENWICHLAVATORYVITREOUS CHINA K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICH LAVATORY VITREOUS CHINA K-2031GREENWICHLAVATORYVITREOUS CHINA
ABCDEFGHIJKL
G.1 E.1
CON
TRA
CTO
RS
AC
CES
S
CONTRACTORS ACCESS
CON
TRA
CTO
RS
AC
CES
S
CON
TRA
CTO
RS
AC
CES
S
CONTRACTORS ACCESS
LD12LD12
LD13LD13
LDC07LDC07
LD46LD46
LD49LD49
LD50LD50
LD51LD51
LD14LD14
LD
C0
LD
C0
LD52LD52 LD48LD48 LD45LD45
LD47LD47
LD08LD08LD09LD09LD10LD10
EX
IT
F R
O M
2F A
C C
ES
S
EX
IT
F R
O M
2F A
C C
ES
S C
O N
TR
AC
TO
R
S A
C C
ES
S
CONTRACTORS ACCESS
C O
N
TR
AC
TO
R S
A C
C
ES
S
C O
N
TR
AC
TO
R S
A C
C
ES
S
LD10 LD09 LD08 LD07 LD06
LD05
LD04
LD47
LD43
LD44
LD45LD48LD52LD
C0
LD14
LD51
LD50
LD49
LDC05
LD16 LD15
LD17
LD18 LD19
LD20
LD
C0
LD35
LD36
LD34
LD22LD21 LD23 LD24
LDC03
LD33 LD32 LD31 LD29
LD25
LD26 LD27
LD28
LD
C0
LD30
LD38LD39
LD40 LD37
LD41
LD42 LD02
LD01
LE08 LE
LE09
LE
C0
LE07 LE03
LE01
LE04
LE11
LE06
LE05
LA22
LA20
LA13 LA12
LAC03
LA03
LA02
LA04
LA06
LA
C0
LA15
LA14
LAC02
LA08
LA07
LA11
LA09 LB04
LA10
LC06
LC05
LC04
LB
C0
LC08
LC07
LC03 LC02 LC01
LB01
LC09 LB03
LBC07
LB02 LB05
LB09
LB10
LB
C0
2 LB07
LB08
LB06
LA16
LA17
LD03LD46
LDC07 LD
C0
LD13
LD12
LA01A
LA01
LDC01
ST-C1
US Army Corps of Engineers ®
IS
O
A
SHEET ID
SO
LI
C
IT
AT
IO
N N
O
D
ES
IG
N
ED
B
Y:
D
ES
C R
IP
TI
O N
M
AR
K
SI
ZE
SU
BM
IT
TE
D B
Y:
D
AT
E
C O
N
TR
AC
T
N O
C
H
EC
KE
D
B Y:
D R
AW
N
B Y:
IS
SU
E D
AT
E:
R
Q
P
N
M
L
K
J
H
G
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
YA
B1
5G
C
2.
dw g
FI
LE
N
AM
E
N
O
VE
M
BE
R
W
2H V-
-B
-0
A H
L- G
A E
JV
, L
LC
M ak ai
T ow er , S ui te
Bi sh op
S tre et H on ol ul u, H aw ai i 9
(8
)5
-9
R
TA
C
O N
TR
AC
T D
O C
U M
EN
TS
(C O
D
TA
A
IR
B
AS
E, F U
SS
A, J
AP
AN
IN
TE
R
IO
R
F
AC
IL
IT
Y R
EP
AI
R S, B U
IL
D
IN
G
U
S
AR
M Y
C O
R
PS
O F
EN
G
IN
EE
AN
D
IS
TR
A P
3-
GENERAL SEQUENCE OF WORK AND PHASING PARAMETERS
PH-2 (PHASE 2) - NON-CLINIC HOURS
ALL WORK IN THIS PHASE SHALL BE
PERFORMED WITHIN THE FOLLOWING TIMES:
WEEKDAYS: 1700-0530 (FOLLOWING DAY,
INCLUDING CLEANUP)
WEEKENDS AND HOLIDAYS: 24HRS
ARCHITECTURAL
· REMOVAL AND REPLACEMENT OF CEILING.
MECHANICAL
· VAV REPLACEMENT
· NEW HYDRONIC HEATING DISTRIBUTION
LINES.
ELECTRICAL / COMMUNICATION
· REMOVAL AND REINSTALLATION OF CEILING
DEVICES
· ELECTRICAL WORK REQUIRED FOR THE NEW
VAV
FIRE PROTECTION
· REMOVAL AND REINSTALLATION OF CEILING
INSTALL FIRE SPRINKLER HEADS TO
ACCOMMODATE CEILING REMOVAL AND
REINSTALLATION
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED FOR
HVAC EQUIPMENT REPLACEMENT
PH-4 (PHASE 4) - NON-CLINIC HOURS
ALL WORK IN THIS PHASE SHALL BE
PERFORMED WITHIN THE FOLLOWING TIMES:
WEEKDAYS: 1700-0530 (FOLLOWING DAY,
INCLUDING CLEANUP)
WEEKENDS AND HOLIDAYS: 24HRS
ARCHITECTURAL
· REMOVAL AND REPLACEMENT OF CEILING.
MECHANICAL
· VAV REPLACEMENT
· NEW HYDRONIC HEATING DISTRIBUTION
LINES.
ELECTRICAL / COMMUNICATION
· REMOVAL AND REINSTALLATION OF CEILING
DEVICES
· ELECTRICAL WORK REQUIRED FOR THE NEW
VAV
FIRE PROTECTION
· REMOVAL AND REINSTALLATION OF CEILING
INSTALL FIRE SPRINKLER HEADS TO
ACCOMMODATE CEILING REMOVAL AND
REINSTALLATION
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED FOR
HVAC EQUIPMENT REPLACEMENT
PH-3 (PHASE 3) - NON-CLINIC HOURS
ALL WORK IN THIS PHASE SHALL BE
PERFORMED WITHIN THE FOLLOWING TIMES:
WEEKDAYS: 1700-0530 (FOLLOWING DAY,
INCLUDING CLEANUP)
WEEKENDS AND HOLIDAYS: 24HRS
ARCHITECTURAL
· REMOVAL AND REPLACEMENT OF CEILING.
MECHANICAL
· VAV REPLACEMENT
· NEW HYDRONIC HEATING DISTRIBUTION
LINES.
ELECTRICAL / COMMUNICATION
· REMOVAL AND REINSTALLATION OF CEILING
DEVICES
· ELECTRICAL WORK REQUIRED FOR THE NEW
VAV
FIRE PROTECTION
· REMOVAL AND REINSTALLATION OF CEILING
INSTALL FIRE SPRINKLER HEADS TO
ACCOMMODATE CEILING REMOVAL AND
REINSTALLATION
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED FOR
HVAC EQUIPMENT REPLACEMENT
PH-5 (PHASE 5) - NON-CLINIC HOURS
ALL WORK IN THIS PHASE SHALL BE
PERFORMED WITHIN THE FOLLOWING TIMES:
WEEKDAYS: 1700-0530 (FOLLOWING DAY,
INCLUDING CLEANUP)
WEEKENDS AND HOLIDAYS: 24HRS
ARCHITECTURAL
· REMOVAL AND REPLACEMENT OF CEILING.
MECHANICAL
· VAV REPLACEMENT
· NEW HYDRONIC HEATING DISTRIBUTION
LINES.
ELECTRICAL / COMMUNICATION
· REMOVAL AND REINSTALLATION OF CEILING
DEVICES
· ELECTRICAL WORK REQUIRED FOR THE NEW
VAV
FIRE PROTECTION
· REMOVAL AND REINSTALLATION OF CEILING
INSTALL FIRE SPRINKLER HEADS TO
ACCOMMODATE CEILING REMOVAL AND
REINSTALLATION
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED FOR
HVAC EQUIPMENT REPLACEMENT
ARCHITECTURAL
· WINDOW REMOVAL
· CEILING REPLACEMENT
· MODIFIED ROOM LAYOUT (NEW DIPC)
MECHANICAL
· REMOVE AND REPLACE DUCTWORK AND
VAV BOXES
· PLUMBING REMOVAL AND NEW WORK
· DENTAL GAS WORK
· NEW HYDRONIC HEATING DISTRIBUTION
LINES.
ELECTRICAL / COMMUNICATION
· ELECTRICAL / COMMUNICATION WORK
REQUIRED FOR NEW DIPC AREA
· REMOVAL CEILING DEVICES
· MODIFIED CEILING DEVICES
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED
FOR HVAC EQUIPMENT REPLACEMENT
FIRE PROTECTION
· INSTALL DUCT DETECTORS AND
CONNECT TO FIRE ALARM SYSTEM
· MODIFY FIRE SPRINKLER PIPING AND FS
HEAD LAYOUT.
· NEW FIRE ALARM DEVICES
STRUCTURAL
· CLOSING-OUT EXISTING WINDOW
OPENINGS.
PH-1 (PHASE 1)
LEGENDS
CONTRACTOR'S ACCESS
DAYTIME ACCESS
(NIGHTTIME ACCESS OPTIONAL)
NIGHTTIME ACCESS
EMERGENCY EGRESS ONLY
(CONTRACTOR'S USE)
ROOM NO. ROOM NAME
LD01
LD02
LD03
LD04
LD05 - LD10
LD12
LD13
LD14
LD15
LD16
LD17
LD18
LD19
LD20 - LD27
LD28
LD29
LD30
LD31
LD32
LD33
LD34
LD35
LD36
LD37
LD38
LD39
LD40
LD41
LD42
LD43
DTR (DENTAL TREATMENT ROOM)
DTR (DENTAL TREATMENT ROOM)
LD44
LD45
LD46
LD47
LD48
LD49
LD50
RECORDS
RECEPTION
OFFICE
OFFICE
INST DECON
INST STER
STER STORAGE
TOILET
X-RAY ROOM
X-RAY ROOM
PYXIS MEDSTATION
OFFICE
X-RAY ROOM
CRASH
WAITING AREA
WAITING AREA
CYLINDER STORAGE
FEMALE TOILET
FEMALE LOCKER
MALE LOCKER
MALE TOILET
WAITING AREA
LOUNGE
STAFF UTILITY ROOM
STAFF TOILET
OFFICE
STAFF UTILITY ROOM
OFFICE
OFFICE
OFFICE
OFFICE
DTR (DENTAL TREATMENT ROOM)
COMM ROOM
DTR (DENTAL TREATMENT ROOM)
OFFICE
LD51 C/LINEN
LD52 C/UTILITY ROOM
LE01 VESTIBULE
LE03 MALE TOILET
LE04
LE05
ELEVATOR
JANITOR
LE06 LOBBY
LE07 FEMALE TOILET
LE08 MECHANICAL ROOM
LE09 GENERATOR ROOM
NOTES
1. INTERIM LIFE SAFETY MEASURES (ILSM) SHALL BE
THE RESPONSIBILITY OF THE CONSTRUCTION
CONTRACTOR DURING OR PRIOR TO EACH PHASE
OF CONSTRUCTION TO ENSURE LIFE SAFETY AND
FIRE PROTECTION FEATURES ARE MAINTAINED.
2. REFER TO SPECIFICATION 01 32 01.00 10 FOR
COLORED PHASING PLANS
LC01 - LC06
LC07
LC08
LC09
OFFICE
LOUNGE
COMM ROOM
EQUIPMENT STORAGE
LB05 - LB08
LB02, LB09
OFFICE
LAB ROOM
LB01
LB03
OFFICE
CONFERENCE
LB10 OFFICE
LA02 - LA04, LA06
LA07
LB04 STORAGE
LA01A - LA01 PLAYROOM
OFFICE
CONFERENCE
LA08 COMM/STOR
LA09 - LA10 STORAGE
OFFICE
LA14 SUPPLY ROOM
LA15 FEMALE TOILET
LA16 MALE TOILET
LA11 - LA13
LA17 MALE LOCKER
LA20 FEMALE LOCKER
LE10 - LE11 VESTIBULE
LA22 MECHANICAL ROOM
LAC01 - LAC03
LBC01,LBC02,LBC07
LDC01 - LDC06
LEC01
CORRIDOR
DAYTIME ANTEROOM
NIGHTTIME ANTEROOM
PH-6 (PHASE 6)
· SECOND FLOOR ONLY ARCHITECTURAL
· RENOVATION OF ROOM
LA22 AND LA21 TO
MECHANICAL ROOM
· REMOVAL OF WALL
PARTITION
· CEILING REPLACEMENT
· NEW EXTERIOR DOOR
MECHANICAL
· REPLACE AHU-1, 3, 4, AND 5
· REMOVE AND REPLACE
DUCTWORK AND VAV
BOXES
· PLUMBING REMOVAL AND
NEW WORK
· NEW HYDRONIC HEATING
DISTRIBUTION LINES.
ELECTRICAL / COMMUNICATION
· REQUIRED ELECTRICAL
WORK FOR THE NEW AHU.
· REMOVAL CEILING DEVICES
· MODIFIED CEILING DEVICES
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE
REQUIRED FOR HVAC
EQUIPMENT REPLACEMENT
FIRE PROTECTION
· INSTALL DUCT DETECTORS
AND CONNECT TO FIRE
ALARM SYSTEM
· MODIFY FIRE SPRINKLER
PIPING AND FS HEAD
LAYOUT.
· NEW FIRE ALARM DEVICES
STRUCTURAL
· REMOVAL OF RC WALL &
WINDOW TO GIVE WAY FOR
THE INSTALLATION OF
DOUBLE DOOR ACCESS
(LA22).
· REMOVAL OF EXISTING
SLAB-ON-GRADE TO GIVE
WAY FOR THE
INSTALLATION OF NEW AHU
PAD (LA22).
· REMOVAL OF EXISTING
CEILING AND EXTENSION
OF DRY WALL UP TO THE
SLAB SOFFIT INCLUDE
INSTALLATION OF SOUND
PROOFING FINISH (LA22).
· CLOSING-OUT EXISTING
WINDOW OPENINGS.
PH-7 (PHASE 7)
SCALE: 1:150
FIRST FLOOR PHASING PLANF1
M .N
AK
AI
M A
L.
M
O R
AD
A
C .M
AR
TI
N
AH
L-
G
AE
J V, L
LC
FI
R
ST
F
LO
O
R P
H
AS
IN
G
P
LA
N
GC102
B1585
W912HV-24-B-0002 Attachment 01 32 01.00 10-A Page 3 (AM-0001)
DIPC
PRIORITIZE TO RETURN TO
SERVICE FIRST AMONG
PHASE 4 SPACES
MECHANICAL
ROOMS CAN BE
DONE ON ANY
PHASE
Phase 1
Previous day/time restrictions no longer applicable
Phase 2A
Phase 2B
Phase 3A
Phase 4
The access routes are no longer divided into daytime, nighttime access, but these paths may change as the re-phasing coordination is finalized.
Phase 5
Phase 7
Phase 7
Phase 3B
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
K-2031GREENWICHLAVATORYVITREOUS CHINA
ABCDEFGHIJKL
G.1 E.1
CONTRACTORS ACCESS
CONTRACTORS ACCESS
C O
N
TR
AC
TO
R S
A C
C
ES
S
TH
R O
U G
H T
EM
P
ST
AI
R S
C O
N
TR
AC
TO
R S
A C
C
ES
S
CONTRACTORS ACCESS CONTRACTORS ACCESS
CONTRACTORS ACCESS
ANTEROOM
AN
TE
R O
O M
ANTEROOM
UD21 UD22 UD23 UD24 UD25 UD26
UD27
UD28UD31
UD32UD19
UD18
UD17
UD
C0
UD16
UD35
UD36
UDC03
ST-N2
UD15 UD14 UD13
UD37 UD38
UD12
UD10
UD11
UD09 UD08
UDC02
UD41 UD42
UD06 UD05 UD43
UDC01
UD43UD04
UD02
UD40
UD
C0
6 UD03
UD01
UC06 UC02
UC07
UC05
UC01
UC03
ST-C2
UEC06
UE21
UE20
UE17
UE16A
UE16 UE15
UEC04
UE23 UE24
UE
C0
UE13
UE14
UE11
UA07
UA01
UE06 UE05
UE01
UE02
UE07
UE07AUA02
UAC01
UA
C0
2UA03
UA04
UA08A
UE08
UE
C0
1 UE04
UE03
UE
C0
5 UE09
UA09
UA10
UEC03
UE10
ST-S2
UDC05
UD33UD34
UD39
UD20
UA08
UD30
UD29
US Army Corps of Engineers ®
IS
O
A
SHEET ID
SO
LI
C
IT
AT
IO
N N
O
D
ES
IG
N
ED
B
Y:
D
ES
C R
IP
TI
O N
M
AR
K
SI
ZE
SU
BM
IT
TE
D B
Y:
D
AT
E
C O
N
TR
AC
T
N O
C
H
EC
KE
D
B Y:
D R
AW
N
B Y:
IS
SU
E D
AT
E:
R
Q
P
N
M
L
K
J
H
G
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
YA
B1
5G
C
3.
dw g
FI
LE
N
AM
E
N
O
VE
M
BE
R
W
2H V-
-B
-0
A H
L- G
A E
JV
, L
LC
M ak ai
T ow er , S ui te
Bi sh op
S tre et H on ol ul u, H aw ai i 9
(8
)5
-9
R
TA
C
O N
TR
AC
T D
O C
U M
EN
TS
(C O
D
TA
A
IR
B
AS
E, F U
SS
A, J
AP
AN
IN
TE
R
IO
R
F
AC
IL
IT
Y R
EP
AI
R S, B U
IL
D
IN
G
U
S
AR
M Y
C O
R
PS
O F
EN
G
IN
EE
AN
D
IS
TR
A P
3-
SCALEF8 SECOND FLOOR PHASING PLAN
1:150
PH-1 (PHASE 1)
ONLY ON FIRST FLOOR
PH-3 (PHASE 3) - NON-CLINIC HOURS
ALL WORK IN THIS PHASE SHALL BE
PERFORMED WITHIN THE FOLLOWING TIMES:
WEEKDAYS: 1700-0530 (FOLLOWING DAY,
INCLUDING CLEANUP)
WEEKENDS AND HOLIDAYS: 24HRS
ARCHITECTURAL
· REMOVAL AND REPLACEMENT OF CEILING.
MECHANICAL
· VAV REPLACEMENT
· NEW HYDRONIC HEATING DISTRIBUTION LINE
ELECTRICAL / COMMUNICATION
· REMOVAL AND REINSTALLATION OF CEILING
DEVICES.
· ELECTRICAL WORK REQUIRED FOR THE NEW
VAV.
FIRE PROTECTION
· REMOVAL AND REINSTALLATION OF CEILING
INSTALL FIRE SPRINKLER HEADS TO
ACCOMMODATE CEILING REMOVAL AND
REINSTALLATION
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED FOR
HVAC EQUIPMENT REPLACEMENT
PH-6 (PHASE 6)
ARCHITECTURAL
· REMOVAL AND REPLACEMENT OF CEILING.
· DEMOLITION OF DIPC (RM UD28).
MECHANICAL
· VAV REPLACEMENT
· NEW HYDRONIC HEATING DISTRIBUTION LINE
ELECTRICAL / COMMUNICATION
· REMOVAL AND REINSTALLATION OF CEILING
DEVICES
· ELECTRICAL WORK REQUIRED FOR THE NEW
VAV
· ELECTRICAL / COMMUNICATION WORK
REQUIRED FOR NEWLY CREATED SPACES
(RM UD28, UD39, & UD40).
FIRE PROTECTION
· REMOVAL AND REINSTALLATION OF CEILING
INSTALL FIRE SPRINKLER HEADS TO
ACCOMMODATE CEILING REMOVAL AND
REINSTALLATION
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED FOR
HVAC EQUIPMENT REPLACEMENT
GENERAL SEQUENCE OF WORK AND PHASING PARAMETERS
PH-4 (PHASE 4) - NON-CLINIC HOURS
ALL WORK IN THIS PHASE SHALL BE
PERFORMED WITHIN THE FOLLOWING TIMES:
WEEKDAYS: 1700-0530 (FOLLOWING DAY,
INCLUDING CLEANUP)
WEEKENDS AND HOLIDAYS: 24HRS
ARCHITECTURAL
· REMOVAL AND REPLACEMENT OF CEILING.
MECHANICAL
· VAV REPLACEMENT
· NEW HYDRONIC HEATING DISTRIBUTION LINE
ELECTRICAL / COMMUNICATION
· REMOVAL AND REINSTALLATION OF CEILING
DEVICES.
· ELECTRICAL WORK REQUIRED FOR THE NEW
VAV.
FIRE PROTECTION
· REMOVAL AND REINSTALLATION OF CEILING
INSTALL FIRE SPRINKLER HEADS TO
ACCOMMODATE CEILING REMOVAL AND
REINSTALLATION
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED FOR
HVAC EQUIPMENT REPLACEMENT
PH-5 (PHASE 5) - NON-CLINIC HOURS
ALL WORK IN THIS PHASE SHALL BE
PERFORMED WITHIN THE FOLLOWING TIMES:
WEEKDAYS: 1700-0530 (FOLLOWING DAY,
INCLUDING CLEANUP)
WEEKENDS AND HOLIDAYS: 24HRS
ARCHITECTURAL
· REMOVAL AND REPLACEMENT OF CEILING.
MECHANICAL
· VAV REPLACEMENT
· NEW HYDRONIC HEATING DISTRIBUTION LINE
ELECTRICAL / COMMUNICATION
· REMOVAL AND REINSTALLATION OF CEILING
DEVICES
· ELECTRICAL WORK REQUIRED FOR THE NEW
VAV
FIRE PROTECTION
· REMOVAL AND REINSTALLATION OF CEILING
INSTALL FIRE SPRINKLER HEADS TO
ACCOMMODATE CEILING REMOVAL AND
REINSTALLATION
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED FOR
HVAC EQUIPMENT REPLACEMENT
PH-7 (PHASE 7)
ARCHITECTURAL
· CONCRETE PAD
STRUCTURAL
· MODIFICATION OF EXISTING EQUIPMENT PAD
TO FIT NEW AHU
MECHANICAL
· UPGRADE CHILLER PLANT INCLUDING
REPLACEMENT OF CHILLER, PUMPS, AND
HYDRONIC HEATING SYSTEM
ELECTRICAL
INCIDENTAL WORKS DUE TO AHU UPGRADE
FIRE PROTECTION
· INSTALL NEW DUCT DETECTORS FOR AHU-3, 4,
AND 5 AND CONNECT TO FIRE ALARM SYSTEM
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED FOR
HVAC EQUIPMENT REPLACEMENT
2.10M
ROOM NO. ROOM NAME
UD40
UD43
UD41 - UD42
CONFERENCE
OFFICE
WAITING AREA
UD36, UD38
UD37
UD39
STORAGE
SUPPLY ROOM
INST CLEAN
LIBRARY
WORKROOM
DARKROOM
UD29
UD30
OFFICE
DENTAL PORCELAIN / CERAMICS
X-RAY ROOM
UD04
UD05 - UD06
UD31 OFFICE
UD01 - UD03 OFFICE
COMM ROOM
DTR (DENTAL TREATMENT ROOM)
UD08 OFFICE
VESTIBULE
LAB ROOM
UD13 STORAGE
UD14 - UD17 DTR (DENTAL TREATMENT ROOM)
UD18 STAFF TOILET
UD10 - UD12
UD19 - UD23 DTR (DENTAL TREATMENT ROOM)
UD24 OFFICE
DTR (DENTAL TREATMENT ROOM)
UD28 STORAGE
UD09
UD24 - UD27
UD32
UD33
UD34
UD35
UC01 LOBBY
UC02
UC03
UC05
UC06
UC07
MALE TOILET
ELEVATOR
JANITOR
FEMALE TOILET
MECHANICAL ROOM
OFFICE
UA04
UA07
UA08A
UA09
EXAM ROOM
STORAGE
CONFERENCE
OFFICE
FEMALE TOILET
UA01
UA02 - UA03
UA10 MALE TOILET
UE01 - UE08 OFFICE
UE09 LOUNGE
UE10 CONFERENCE
OFFICE
UE16A, UE20-UE21 STORAGE
UE11, UE13 - UE17
UAC01 - UAC02
UDC01 - UDC06
UEC01 - UEC06
CORRIDOR
LEGENDS
CONTRACTOR'S ACCESS
DAYTIME ACCESS
(NIGHTTIME ACCESS OPTIONAL)
NIGHTTIME ACCESS
EMERGENCY EGRESS ONLY
(CONTRACTOR'S USE)
DAYTIME ANTEROOM
NIGHTTIME ANTEROOM
NOTES
1. INTERIM LIFE SAFETY MEASURES (ILSM) SHALL
BE THE RESPONSIBILITY OF THE
CONSTRUCTION CONTRACTOR DURING OR
PRIOR TO EACH PHASE OF CONSTRUCTION TO
ENSURE LIFE SAFETY AND FIRE PROTECTION
FEATURES ARE MAINTAINED
2. REFER TO SPECIFICATION 01 32 01.00 10 FOR
COLORED PHASING PLANS
PH-2 (PHASE 2) - NON-CLINIC HOURS
ALL WORK IN THIS PHASE SHALL BE
PERFORMED WITHIN THE FOLLOWING TIMES:
WEEKDAYS: 1700-0530 (FOLLOWING DAY,
INCLUDING CLEANUP)
WEEKENDS AND HOLIDAYS: 24HRS
ARCHITECTURAL
· REMOVAL AND REPLACEMENT OF CEILING.
MECHANICAL
· VAV REPLACEMENT
· NEW HYDRONIC HEATING DISTRIBUTION LINES.
ELECTRICAL / COMMUNICATION
· REMOVAL AND REINSTALLATION OF CEILING
DEVICES
· ELECTRICAL WORK REQUIRED FOR THE NEW
VAV
FIRE PROTECTION
· REMOVAL AND REINSTALLATION OF CEILING
INSTALL FIRE SPRINKLER HEADS TO
ACCOMMODATE CEILING REMOVAL AND
REINSTALLATION
HAZARDOUS MATERIAL
· ABATEMENT WORK MAY BE REQUIRED FOR
HVAC EQUIPMENT REPLACEMENT
PLAN
NORTH
0 10m5m 15m
M .N
AK
AI
M A
L.
M
O R
AD
A
C .M
AR
TI
N
AH
L-
G
AE
J V, L
LC
SE
C
O N
D F
LO
O
R P
H
AS
IN
G
P
LA
N
GC103
B1585
W912HV-24-B-0002 Attachment 01 32 01.00 10-A Page 4 (AM-0001)
Phase 4
The access routes are no longer divided into daytime, nighttime access, but these paths may change as the re-phasing coordination is finalized.
Previous day/time restrictions no longer applicable
Phase 2A
Phase 2C
Phase 2BPhase 2A
Phase 3B
Phase 3A
Phase 7
Phase 6A
Phase 6B
Phase 6C
Phase 5A
Phase 5B
Phase 8 will replace the chillers.
Phase 9 will replace the five AHU's. Each AHU will be replaced sequentially with AHU-3 to be replaced last. While AHU-1, AHU-2, AHU-4 and AHU-5 are being replaced, one of the new AHU's will be used to provide temporary cooling/ heating to the affected spaces. A temporary tie in to the ducting from the roof will be required.
New AHU will be located either on the roof or at ground level.