Sources Sought DHA 1585 Draft Phasing Plan.pdf

PDF 3 MB Posted

Attached to
FY25 DHA SRM Facility Repairs, Building 1585, Yokota Air Base, Japan
Solicitation number
W912HV25Z0002
Issued by

About this file

This document appears to be a Sources Sought Market Survey for the "FY25 DHA SRM Facility Repairs, Building 1585, Yokota Air Base, Japan" project. The U.S. Army Corps of Engineers, Japan District (POJ) is conducting market research for this upcoming Design-Bid-Build (DBB) requirement. The purpose is to identify capable sources to assist with acquisition planning. This is not a solicitation, and the government will not pay for any information provided in response.

The project involves interior facility repairs to Building 1585 at Yokota Air Base in Japan. The work will be phased, with Phase 1 focused on mechanical upgrades including chiller and air handling unit replacements. Subsequent phases will involve architectural, mechanical, electrical, and fire protection work, primarily during non-clinic hours. The market survey is seeking information from firms capable of performing this type of work at the Yokota Air Base location.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W

W W W

GTV

W W

W

GTV

WWW

W

UG/P

UG/P

WP WP WP WP

U G

/S

E

FUEL TANK

EMH

EMH

EMH

EMH

EMH

EMH

EMH EMH

EMH

EMH

E

E

E

E

E

TMH

TMH

E

E

E

EMH

E

TMH

EMH

E

EHH

EHH

E

EHH

EHH

EHH

GI

CB

CB

CB

CB

CB

CBCB

CB

BLDG 1585

GI

GI

GI

GI

CB

CB

CB

CB

CB CB

CB

GIGI

GI

GI

GI

GI

GI

GI

GI

T

T

T

GI

GI

EHH

CB

GI

GI

CB

CB GI

T1584

GAZEBO

M cG

UIRE AVENUE

SE

R

VI

C

E/

FI

R E

AC

C

ES

S

R O

AD

US Army Corps of Engineers ®

IS

O

A

SHEET ID

SO

LI

C

IT

AT

IO

N N

O

D

ES

IG

N

ED

B

Y:

D

ES

C R

IP

TI

O N

M

AR

K

SI

ZE

SU

BM

IT

TE

D B

Y:

D

AT

E

C O

N

TR

AC

T

N O

C

H

EC

KE

D

B Y:

D R

AW

N

B Y:

IS

SU

E D

AT

E:

R

Q

P

N

M

L

K

J

H

G

F

E

D

C

B

A

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

YA

B1

5G

C

1.

dw g

FI

LE

N

AM

E

N

O

VE

M

BE

R

W

2H V-

-B

-0

A H

L- G

A E

JV

, L

LC

M ak ai

T ow er , S ui te

Bi sh op

S tre et H on ol ul u, H aw ai i 9

(8

)5

-9

R

TA

C

O N

TR

AC

T D

O C

U M

EN

TS

(C O

D E

6)

YO

KO

TA

A

IR

B

AS

E, F U

SS

A, J

AP

AN

IN

TE

R

IO

R

F

AC

IL

IT

Y R

EP

AI

R S, B U

IL

D

IN

G

U

S

AR

M Y

C O

R

PS

O F

EN

G

IN

EE

R S

J

AP

AN

D

IS

TR

IC

T

A

PO

A P

3-

GENERAL SEQUENCE OF WORK AND PHASING

PARAMETERS

PH-1 (PHASE 1)

MECHANICAL

· UPGRADES INCLUDING REPLACEMENT OF CHILLER, AND AHU 1,

3, 4, AND 5.

· INSTALL NEW AIR COOLED CHILLER AND ASSOCIATED PIPING

AND PUMPS

ELECTRICAL

· NEW CUBICLE TRANSFORMER AND UNDERGROUND

INFRASTRUCTURE

· NEW EQUIPMENT PAD FOR CUBICLE TRANSFORMER

STRUCTURAL

· NEW EXTERIOR CHILLER ENCLOSURE FOUNDATION.

CIVIL

· NEW EXTERIOR CHILLER ENCLOSURE

· NEW CONC SIDEWALK, STOOP AND CURB & GUTTER

· WATER LINE RE-ROUTING

· AC PAVEMENT AND SODDING RESTORATION

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED FOR HVAC EQUIPMENT

REPLACEMENT

NOTES

1. CONTRACTOR SHALL SCHEDULE WORK TO CAUSE THE LEAST AMOUNT

OF INTERFERENCE WITH ACTIVITY OPERATIONS.

2. CONSTRUCTION SEQUENCING PLAN SUMMARIZES THE GENERAL

SEQUENCE OF WORK TO ACCOMMODATE THE BUILDING PLANNING AND

OPERATIONAL REQUIREMENTS DURING CONSTRUCTION. CONTRACTOR

SHALL PLAN THE CONSTRUCTION WORK TO ACCOMMODATE THE

CONSTRUCTION SEQUENCES SHOWN. THE CONTRACTOR MAY PROPOSE

VARIATIONS TO THE WORK SEQUENCES TO ACCOMMODATE

CONSTRUCTION EFFICIENCIES. ANY PROPOSED DEVIATION FROM THE

PHASING PLAN SHALL BE SUBMITTED TO THE CONTRACTING OFFICER

FOR CONSIDERATION AND APPROVAL.

3. CONTRACTOR'S CONSTRUCTION LAYDOWN AREAS (STAGING AREAS)

AND ON-SITE CONSTRUCTION OFFICE SHALL BE LIMITED TO THE

GENERAL AREAS SHOWN ON THE CONTRACTOR STAGING, FENCING, AND

FIRE EGRESS SITE PLAN ON SHEET C-001. CONFIRM ACTUAL LIMITATIONS

OF THE STAGING AREA WITH THE CONTRACTING OFFICER. DEVIATIONS

FROM THE SELECTED AREA SHALL BE COORDINATED WITH THE

CONTRACTING OFFICER.

4. HAULING OF CONSTRUCTION MATERIALS SHALL BE LIMITED TO THE

ROUTES DESIGNATED ON THE HAUL ROUTE PLAN. ENTRY TO THE BASE

SHALL BE LIMITED TO THE SUPPLY ENTRY GATE. DEVIATIONS FROM THE

HAUL ROUTE PLAN TO ACCOMMODATE CONSTRUCTION MEANS AND

METHODS AND/OR DELIVERY AND TRANSFERRING OF MATERIALS SHALL

BE COORDINATED WITH AND APPROVED BY THE CONTRACTING OFFICER.

5. REFER TO SPECIFICATION 01 32 01.00 10 FOR COLORED PHASING PLANS

PLAN

NORTH

1050 25m15 20

SCALE: 1:150

SITE PHASING PLANA1

M .N

AK

AI

M A

L.

M

O R

AD

A

C .M

AR

TI

N

AH

L-

G

AE

J V, L

LC

SI

TE

P H

AS

IN

G P

LA

N

GC101

B1585

W912HV-24-B-0002 Attachment 01 32 01.00 10-A Page 2 (AM-0001)

The exterior work will likely be renamed to PH-0 (Phase 0) as it is not necessarily associated with the PH-1 (Phase 1) work at the interior of the building. The work shown on this sheet may be conducted independent of the work at the interior, although the installation of the AHUs must occur in the winter or early spring seasons, between NOVEMBER - MARCH

DRAFT

ANTEROOM

ANTEROOMCONTRACTORS ACCESS

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINAK-2031GREENWICHLAVATORYVITREOUS CHINA K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICH LAVATORY VITREOUS CHINA K-2031GREENWICHLAVATORYVITREOUS CHINA

ABCDEFGHIJKL

G.1 E.1

CON

TRA

CTO

RS

AC

CES

S

CONTRACTORS ACCESS

CON

TRA

CTO

RS

AC

CES

S

CON

TRA

CTO

RS

AC

CES

S

CONTRACTORS ACCESS

LD12LD12

LD13LD13

LDC07LDC07

LD46LD46

LD49LD49

LD50LD50

LD51LD51

LD14LD14

LD

C0

LD

C0

LD52LD52 LD48LD48 LD45LD45

LD47LD47

LD08LD08LD09LD09LD10LD10

EX

IT

F R

O M

2F A

C C

ES

S

EX

IT

F R

O M

2F A

C C

ES

S C

O N

TR

AC

TO

R

S A

C C

ES

S

CONTRACTORS ACCESS

C O

N

TR

AC

TO

R S

A C

C

ES

S

C O

N

TR

AC

TO

R S

A C

C

ES

S

LD10 LD09 LD08 LD07 LD06

LD05

LD04

LD47

LD43

LD44

LD45LD48LD52LD

C0

LD14

LD51

LD50

LD49

LDC05

LD16 LD15

LD17

LD18 LD19

LD20

LD

C0

LD35

LD36

LD34

LD22LD21 LD23 LD24

LDC03

LD33 LD32 LD31 LD29

LD25

LD26 LD27

LD28

LD

C0

LD30

LD38LD39

LD40 LD37

LD41

LD42 LD02

LD01

LE08 LE

LE09

LE

C0

LE07 LE03

LE01

LE04

LE11

LE06

LE05

LA22

LA20

LA13 LA12

LAC03

LA03

LA02

LA04

LA06

LA

C0

LA15

LA14

LAC02

LA08

LA07

LA11

LA09 LB04

LA10

LC06

LC05

LC04

LB

C0

LC08

LC07

LC03 LC02 LC01

LB01

LC09 LB03

LBC07

LB02 LB05

LB09

LB10

LB

C0

2 LB07

LB08

LB06

LA16

LA17

LD03LD46

LDC07 LD

C0

LD13

LD12

LA01A

LA01

LDC01

ST-C1

US Army Corps of Engineers ®

IS

O

A

SHEET ID

SO

LI

C

IT

AT

IO

N N

O

D

ES

IG

N

ED

B

Y:

D

ES

C R

IP

TI

O N

M

AR

K

SI

ZE

SU

BM

IT

TE

D B

Y:

D

AT

E

C O

N

TR

AC

T

N O

C

H

EC

KE

D

B Y:

D R

AW

N

B Y:

IS

SU

E D

AT

E:

R

Q

P

N

M

L

K

J

H

G

F

E

D

C

B

A

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

YA

B1

5G

C

2.

dw g

FI

LE

N

AM

E

N

O

VE

M

BE

R

W

2H V-

-B

-0

A H

L- G

A E

JV

, L

LC

M ak ai

T ow er , S ui te

Bi sh op

S tre et H on ol ul u, H aw ai i 9

(8

)5

-9

R

TA

C

O N

TR

AC

T D

O C

U M

EN

TS

(C O

D

TA

A

IR

B

AS

E, F U

SS

A, J

AP

AN

IN

TE

R

IO

R

F

AC

IL

IT

Y R

EP

AI

R S, B U

IL

D

IN

G

U

S

AR

M Y

C O

R

PS

O F

EN

G

IN

EE

AN

D

IS

TR

A P

3-

GENERAL SEQUENCE OF WORK AND PHASING PARAMETERS

PH-2 (PHASE 2) - NON-CLINIC HOURS

ALL WORK IN THIS PHASE SHALL BE

PERFORMED WITHIN THE FOLLOWING TIMES:

WEEKDAYS: 1700-0530 (FOLLOWING DAY,

INCLUDING CLEANUP)

WEEKENDS AND HOLIDAYS: 24HRS

ARCHITECTURAL

· REMOVAL AND REPLACEMENT OF CEILING.

MECHANICAL

· VAV REPLACEMENT

· NEW HYDRONIC HEATING DISTRIBUTION

LINES.

ELECTRICAL / COMMUNICATION

· REMOVAL AND REINSTALLATION OF CEILING

DEVICES

· ELECTRICAL WORK REQUIRED FOR THE NEW

VAV

FIRE PROTECTION

· REMOVAL AND REINSTALLATION OF CEILING

INSTALL FIRE SPRINKLER HEADS TO

ACCOMMODATE CEILING REMOVAL AND

REINSTALLATION

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED FOR

HVAC EQUIPMENT REPLACEMENT

PH-4 (PHASE 4) - NON-CLINIC HOURS

ALL WORK IN THIS PHASE SHALL BE

PERFORMED WITHIN THE FOLLOWING TIMES:

WEEKDAYS: 1700-0530 (FOLLOWING DAY,

INCLUDING CLEANUP)

WEEKENDS AND HOLIDAYS: 24HRS

ARCHITECTURAL

· REMOVAL AND REPLACEMENT OF CEILING.

MECHANICAL

· VAV REPLACEMENT

· NEW HYDRONIC HEATING DISTRIBUTION

LINES.

ELECTRICAL / COMMUNICATION

· REMOVAL AND REINSTALLATION OF CEILING

DEVICES

· ELECTRICAL WORK REQUIRED FOR THE NEW

VAV

FIRE PROTECTION

· REMOVAL AND REINSTALLATION OF CEILING

INSTALL FIRE SPRINKLER HEADS TO

ACCOMMODATE CEILING REMOVAL AND

REINSTALLATION

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED FOR

HVAC EQUIPMENT REPLACEMENT

PH-3 (PHASE 3) - NON-CLINIC HOURS

ALL WORK IN THIS PHASE SHALL BE

PERFORMED WITHIN THE FOLLOWING TIMES:

WEEKDAYS: 1700-0530 (FOLLOWING DAY,

INCLUDING CLEANUP)

WEEKENDS AND HOLIDAYS: 24HRS

ARCHITECTURAL

· REMOVAL AND REPLACEMENT OF CEILING.

MECHANICAL

· VAV REPLACEMENT

· NEW HYDRONIC HEATING DISTRIBUTION

LINES.

ELECTRICAL / COMMUNICATION

· REMOVAL AND REINSTALLATION OF CEILING

DEVICES

· ELECTRICAL WORK REQUIRED FOR THE NEW

VAV

FIRE PROTECTION

· REMOVAL AND REINSTALLATION OF CEILING

INSTALL FIRE SPRINKLER HEADS TO

ACCOMMODATE CEILING REMOVAL AND

REINSTALLATION

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED FOR

HVAC EQUIPMENT REPLACEMENT

PH-5 (PHASE 5) - NON-CLINIC HOURS

ALL WORK IN THIS PHASE SHALL BE

PERFORMED WITHIN THE FOLLOWING TIMES:

WEEKDAYS: 1700-0530 (FOLLOWING DAY,

INCLUDING CLEANUP)

WEEKENDS AND HOLIDAYS: 24HRS

ARCHITECTURAL

· REMOVAL AND REPLACEMENT OF CEILING.

MECHANICAL

· VAV REPLACEMENT

· NEW HYDRONIC HEATING DISTRIBUTION

LINES.

ELECTRICAL / COMMUNICATION

· REMOVAL AND REINSTALLATION OF CEILING

DEVICES

· ELECTRICAL WORK REQUIRED FOR THE NEW

VAV

FIRE PROTECTION

· REMOVAL AND REINSTALLATION OF CEILING

INSTALL FIRE SPRINKLER HEADS TO

ACCOMMODATE CEILING REMOVAL AND

REINSTALLATION

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED FOR

HVAC EQUIPMENT REPLACEMENT

ARCHITECTURAL

· WINDOW REMOVAL

· CEILING REPLACEMENT

· MODIFIED ROOM LAYOUT (NEW DIPC)

MECHANICAL

· REMOVE AND REPLACE DUCTWORK AND

VAV BOXES

· PLUMBING REMOVAL AND NEW WORK

· DENTAL GAS WORK

· NEW HYDRONIC HEATING DISTRIBUTION

LINES.

ELECTRICAL / COMMUNICATION

· ELECTRICAL / COMMUNICATION WORK

REQUIRED FOR NEW DIPC AREA

· REMOVAL CEILING DEVICES

· MODIFIED CEILING DEVICES

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED

FOR HVAC EQUIPMENT REPLACEMENT

FIRE PROTECTION

· INSTALL DUCT DETECTORS AND

CONNECT TO FIRE ALARM SYSTEM

· MODIFY FIRE SPRINKLER PIPING AND FS

HEAD LAYOUT.

· NEW FIRE ALARM DEVICES

STRUCTURAL

· CLOSING-OUT EXISTING WINDOW

OPENINGS.

PH-1 (PHASE 1)

LEGENDS

CONTRACTOR'S ACCESS

DAYTIME ACCESS

(NIGHTTIME ACCESS OPTIONAL)

NIGHTTIME ACCESS

EMERGENCY EGRESS ONLY

(CONTRACTOR'S USE)

ROOM NO. ROOM NAME

LD01

LD02

LD03

LD04

LD05 - LD10

LD12

LD13

LD14

LD15

LD16

LD17

LD18

LD19

LD20 - LD27

LD28

LD29

LD30

LD31

LD32

LD33

LD34

LD35

LD36

LD37

LD38

LD39

LD40

LD41

LD42

LD43

DTR (DENTAL TREATMENT ROOM)

DTR (DENTAL TREATMENT ROOM)

LD44

LD45

LD46

LD47

LD48

LD49

LD50

RECORDS

RECEPTION

OFFICE

OFFICE

INST DECON

INST STER

STER STORAGE

TOILET

X-RAY ROOM

X-RAY ROOM

PYXIS MEDSTATION

OFFICE

X-RAY ROOM

CRASH

WAITING AREA

WAITING AREA

CYLINDER STORAGE

FEMALE TOILET

FEMALE LOCKER

MALE LOCKER

MALE TOILET

WAITING AREA

LOUNGE

STAFF UTILITY ROOM

STAFF TOILET

OFFICE

STAFF UTILITY ROOM

OFFICE

OFFICE

OFFICE

OFFICE

DTR (DENTAL TREATMENT ROOM)

COMM ROOM

DTR (DENTAL TREATMENT ROOM)

OFFICE

LD51 C/LINEN

LD52 C/UTILITY ROOM

LE01 VESTIBULE

LE03 MALE TOILET

LE04

LE05

ELEVATOR

JANITOR

LE06 LOBBY

LE07 FEMALE TOILET

LE08 MECHANICAL ROOM

LE09 GENERATOR ROOM

NOTES

1. INTERIM LIFE SAFETY MEASURES (ILSM) SHALL BE

THE RESPONSIBILITY OF THE CONSTRUCTION

CONTRACTOR DURING OR PRIOR TO EACH PHASE

OF CONSTRUCTION TO ENSURE LIFE SAFETY AND

FIRE PROTECTION FEATURES ARE MAINTAINED.

2. REFER TO SPECIFICATION 01 32 01.00 10 FOR

COLORED PHASING PLANS

LC01 - LC06

LC07

LC08

LC09

OFFICE

LOUNGE

COMM ROOM

EQUIPMENT STORAGE

LB05 - LB08

LB02, LB09

OFFICE

LAB ROOM

LB01

LB03

OFFICE

CONFERENCE

LB10 OFFICE

LA02 - LA04, LA06

LA07

LB04 STORAGE

LA01A - LA01 PLAYROOM

OFFICE

CONFERENCE

LA08 COMM/STOR

LA09 - LA10 STORAGE

OFFICE

LA14 SUPPLY ROOM

LA15 FEMALE TOILET

LA16 MALE TOILET

LA11 - LA13

LA17 MALE LOCKER

LA20 FEMALE LOCKER

LE10 - LE11 VESTIBULE

LA22 MECHANICAL ROOM

LAC01 - LAC03

LBC01,LBC02,LBC07

LDC01 - LDC06

LEC01

CORRIDOR

DAYTIME ANTEROOM

NIGHTTIME ANTEROOM

PH-6 (PHASE 6)

· SECOND FLOOR ONLY ARCHITECTURAL

· RENOVATION OF ROOM

LA22 AND LA21 TO

MECHANICAL ROOM

· REMOVAL OF WALL

PARTITION

· CEILING REPLACEMENT

· NEW EXTERIOR DOOR

MECHANICAL

· REPLACE AHU-1, 3, 4, AND 5

· REMOVE AND REPLACE

DUCTWORK AND VAV

BOXES

· PLUMBING REMOVAL AND

NEW WORK

· NEW HYDRONIC HEATING

DISTRIBUTION LINES.

ELECTRICAL / COMMUNICATION

· REQUIRED ELECTRICAL

WORK FOR THE NEW AHU.

· REMOVAL CEILING DEVICES

· MODIFIED CEILING DEVICES

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE

REQUIRED FOR HVAC

EQUIPMENT REPLACEMENT

FIRE PROTECTION

· INSTALL DUCT DETECTORS

AND CONNECT TO FIRE

ALARM SYSTEM

· MODIFY FIRE SPRINKLER

PIPING AND FS HEAD

LAYOUT.

· NEW FIRE ALARM DEVICES

STRUCTURAL

· REMOVAL OF RC WALL &

WINDOW TO GIVE WAY FOR

THE INSTALLATION OF

DOUBLE DOOR ACCESS

(LA22).

· REMOVAL OF EXISTING

SLAB-ON-GRADE TO GIVE

WAY FOR THE

INSTALLATION OF NEW AHU

PAD (LA22).

· REMOVAL OF EXISTING

CEILING AND EXTENSION

OF DRY WALL UP TO THE

SLAB SOFFIT INCLUDE

INSTALLATION OF SOUND

PROOFING FINISH (LA22).

· CLOSING-OUT EXISTING

WINDOW OPENINGS.

PH-7 (PHASE 7)

SCALE: 1:150

FIRST FLOOR PHASING PLANF1

M .N

AK

AI

M A

L.

M

O R

AD

A

C .M

AR

TI

N

AH

L-

G

AE

J V, L

LC

FI

R

ST

F

LO

O

R P

H

AS

IN

G

P

LA

N

GC102

B1585

W912HV-24-B-0002 Attachment 01 32 01.00 10-A Page 3 (AM-0001)

DIPC

PRIORITIZE TO RETURN TO

SERVICE FIRST AMONG

PHASE 4 SPACES

MECHANICAL

ROOMS CAN BE

DONE ON ANY

PHASE

Phase 1

Previous day/time restrictions no longer applicable

Phase 2A

Phase 2B

Phase 3A

Phase 4

The access routes are no longer divided into daytime, nighttime access, but these paths may change as the re-phasing coordination is finalized.

Phase 5

Phase 7

Phase 7

Phase 3B

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

K-2031GREENWICHLAVATORYVITREOUS CHINA

ABCDEFGHIJKL

G.1 E.1

CONTRACTORS ACCESS

CONTRACTORS ACCESS

C O

N

TR

AC

TO

R S

A C

C

ES

S

TH

R O

U G

H T

EM

P

ST

AI

R S

C O

N

TR

AC

TO

R S

A C

C

ES

S

CONTRACTORS ACCESS CONTRACTORS ACCESS

CONTRACTORS ACCESS

ANTEROOM

AN

TE

R O

O M

ANTEROOM

UD21 UD22 UD23 UD24 UD25 UD26

UD27

UD28UD31

UD32UD19

UD18

UD17

UD

C0

UD16

UD35

UD36

UDC03

ST-N2

UD15 UD14 UD13

UD37 UD38

UD12

UD10

UD11

UD09 UD08

UDC02

UD41 UD42

UD06 UD05 UD43

UDC01

UD43UD04

UD02

UD40

UD

C0

6 UD03

UD01

UC06 UC02

UC07

UC05

UC01

UC03

ST-C2

UEC06

UE21

UE20

UE17

UE16A

UE16 UE15

UEC04

UE23 UE24

UE

C0

UE13

UE14

UE11

UA07

UA01

UE06 UE05

UE01

UE02

UE07

UE07AUA02

UAC01

UA

C0

2UA03

UA04

UA08A

UE08

UE

C0

1 UE04

UE03

UE

C0

5 UE09

UA09

UA10

UEC03

UE10

ST-S2

UDC05

UD33UD34

UD39

UD20

UA08

UD30

UD29

US Army Corps of Engineers ®

IS

O

A

SHEET ID

SO

LI

C

IT

AT

IO

N N

O

D

ES

IG

N

ED

B

Y:

D

ES

C R

IP

TI

O N

M

AR

K

SI

ZE

SU

BM

IT

TE

D B

Y:

D

AT

E

C O

N

TR

AC

T

N O

C

H

EC

KE

D

B Y:

D R

AW

N

B Y:

IS

SU

E D

AT

E:

R

Q

P

N

M

L

K

J

H

G

F

E

D

C

B

A

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

YA

B1

5G

C

3.

dw g

FI

LE

N

AM

E

N

O

VE

M

BE

R

W

2H V-

-B

-0

A H

L- G

A E

JV

, L

LC

M ak ai

T ow er , S ui te

Bi sh op

S tre et H on ol ul u, H aw ai i 9

(8

)5

-9

R

TA

C

O N

TR

AC

T D

O C

U M

EN

TS

(C O

D

TA

A

IR

B

AS

E, F U

SS

A, J

AP

AN

IN

TE

R

IO

R

F

AC

IL

IT

Y R

EP

AI

R S, B U

IL

D

IN

G

U

S

AR

M Y

C O

R

PS

O F

EN

G

IN

EE

AN

D

IS

TR

A P

3-

SCALEF8 SECOND FLOOR PHASING PLAN

1:150

PH-1 (PHASE 1)

ONLY ON FIRST FLOOR

PH-3 (PHASE 3) - NON-CLINIC HOURS

ALL WORK IN THIS PHASE SHALL BE

PERFORMED WITHIN THE FOLLOWING TIMES:

WEEKDAYS: 1700-0530 (FOLLOWING DAY,

INCLUDING CLEANUP)

WEEKENDS AND HOLIDAYS: 24HRS

ARCHITECTURAL

· REMOVAL AND REPLACEMENT OF CEILING.

MECHANICAL

· VAV REPLACEMENT

· NEW HYDRONIC HEATING DISTRIBUTION LINE

ELECTRICAL / COMMUNICATION

· REMOVAL AND REINSTALLATION OF CEILING

DEVICES.

· ELECTRICAL WORK REQUIRED FOR THE NEW

VAV.

FIRE PROTECTION

· REMOVAL AND REINSTALLATION OF CEILING

INSTALL FIRE SPRINKLER HEADS TO

ACCOMMODATE CEILING REMOVAL AND

REINSTALLATION

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED FOR

HVAC EQUIPMENT REPLACEMENT

PH-6 (PHASE 6)

ARCHITECTURAL

· REMOVAL AND REPLACEMENT OF CEILING.

· DEMOLITION OF DIPC (RM UD28).

MECHANICAL

· VAV REPLACEMENT

· NEW HYDRONIC HEATING DISTRIBUTION LINE

ELECTRICAL / COMMUNICATION

· REMOVAL AND REINSTALLATION OF CEILING

DEVICES

· ELECTRICAL WORK REQUIRED FOR THE NEW

VAV

· ELECTRICAL / COMMUNICATION WORK

REQUIRED FOR NEWLY CREATED SPACES

(RM UD28, UD39, & UD40).

FIRE PROTECTION

· REMOVAL AND REINSTALLATION OF CEILING

INSTALL FIRE SPRINKLER HEADS TO

ACCOMMODATE CEILING REMOVAL AND

REINSTALLATION

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED FOR

HVAC EQUIPMENT REPLACEMENT

GENERAL SEQUENCE OF WORK AND PHASING PARAMETERS

PH-4 (PHASE 4) - NON-CLINIC HOURS

ALL WORK IN THIS PHASE SHALL BE

PERFORMED WITHIN THE FOLLOWING TIMES:

WEEKDAYS: 1700-0530 (FOLLOWING DAY,

INCLUDING CLEANUP)

WEEKENDS AND HOLIDAYS: 24HRS

ARCHITECTURAL

· REMOVAL AND REPLACEMENT OF CEILING.

MECHANICAL

· VAV REPLACEMENT

· NEW HYDRONIC HEATING DISTRIBUTION LINE

ELECTRICAL / COMMUNICATION

· REMOVAL AND REINSTALLATION OF CEILING

DEVICES.

· ELECTRICAL WORK REQUIRED FOR THE NEW

VAV.

FIRE PROTECTION

· REMOVAL AND REINSTALLATION OF CEILING

INSTALL FIRE SPRINKLER HEADS TO

ACCOMMODATE CEILING REMOVAL AND

REINSTALLATION

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED FOR

HVAC EQUIPMENT REPLACEMENT

PH-5 (PHASE 5) - NON-CLINIC HOURS

ALL WORK IN THIS PHASE SHALL BE

PERFORMED WITHIN THE FOLLOWING TIMES:

WEEKDAYS: 1700-0530 (FOLLOWING DAY,

INCLUDING CLEANUP)

WEEKENDS AND HOLIDAYS: 24HRS

ARCHITECTURAL

· REMOVAL AND REPLACEMENT OF CEILING.

MECHANICAL

· VAV REPLACEMENT

· NEW HYDRONIC HEATING DISTRIBUTION LINE

ELECTRICAL / COMMUNICATION

· REMOVAL AND REINSTALLATION OF CEILING

DEVICES

· ELECTRICAL WORK REQUIRED FOR THE NEW

VAV

FIRE PROTECTION

· REMOVAL AND REINSTALLATION OF CEILING

INSTALL FIRE SPRINKLER HEADS TO

ACCOMMODATE CEILING REMOVAL AND

REINSTALLATION

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED FOR

HVAC EQUIPMENT REPLACEMENT

PH-7 (PHASE 7)

ARCHITECTURAL

· CONCRETE PAD

STRUCTURAL

· MODIFICATION OF EXISTING EQUIPMENT PAD

TO FIT NEW AHU

MECHANICAL

· UPGRADE CHILLER PLANT INCLUDING

REPLACEMENT OF CHILLER, PUMPS, AND

HYDRONIC HEATING SYSTEM

ELECTRICAL

INCIDENTAL WORKS DUE TO AHU UPGRADE

FIRE PROTECTION

· INSTALL NEW DUCT DETECTORS FOR AHU-3, 4,

AND 5 AND CONNECT TO FIRE ALARM SYSTEM

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED FOR

HVAC EQUIPMENT REPLACEMENT

2.10M

ROOM NO. ROOM NAME

UD40

UD43

UD41 - UD42

CONFERENCE

OFFICE

WAITING AREA

UD36, UD38

UD37

UD39

STORAGE

SUPPLY ROOM

INST CLEAN

LIBRARY

WORKROOM

DARKROOM

UD29

UD30

OFFICE

DENTAL PORCELAIN / CERAMICS

X-RAY ROOM

UD04

UD05 - UD06

UD31 OFFICE

UD01 - UD03 OFFICE

COMM ROOM

DTR (DENTAL TREATMENT ROOM)

UD08 OFFICE

VESTIBULE

LAB ROOM

UD13 STORAGE

UD14 - UD17 DTR (DENTAL TREATMENT ROOM)

UD18 STAFF TOILET

UD10 - UD12

UD19 - UD23 DTR (DENTAL TREATMENT ROOM)

UD24 OFFICE

DTR (DENTAL TREATMENT ROOM)

UD28 STORAGE

UD09

UD24 - UD27

UD32

UD33

UD34

UD35

UC01 LOBBY

UC02

UC03

UC05

UC06

UC07

MALE TOILET

ELEVATOR

JANITOR

FEMALE TOILET

MECHANICAL ROOM

OFFICE

UA04

UA07

UA08A

UA09

EXAM ROOM

STORAGE

CONFERENCE

OFFICE

FEMALE TOILET

UA01

UA02 - UA03

UA10 MALE TOILET

UE01 - UE08 OFFICE

UE09 LOUNGE

UE10 CONFERENCE

OFFICE

UE16A, UE20-UE21 STORAGE

UE11, UE13 - UE17

UAC01 - UAC02

UDC01 - UDC06

UEC01 - UEC06

CORRIDOR

LEGENDS

CONTRACTOR'S ACCESS

DAYTIME ACCESS

(NIGHTTIME ACCESS OPTIONAL)

NIGHTTIME ACCESS

EMERGENCY EGRESS ONLY

(CONTRACTOR'S USE)

DAYTIME ANTEROOM

NIGHTTIME ANTEROOM

NOTES

1. INTERIM LIFE SAFETY MEASURES (ILSM) SHALL

BE THE RESPONSIBILITY OF THE

CONSTRUCTION CONTRACTOR DURING OR

PRIOR TO EACH PHASE OF CONSTRUCTION TO

ENSURE LIFE SAFETY AND FIRE PROTECTION

FEATURES ARE MAINTAINED

2. REFER TO SPECIFICATION 01 32 01.00 10 FOR

COLORED PHASING PLANS

PH-2 (PHASE 2) - NON-CLINIC HOURS

ALL WORK IN THIS PHASE SHALL BE

PERFORMED WITHIN THE FOLLOWING TIMES:

WEEKDAYS: 1700-0530 (FOLLOWING DAY,

INCLUDING CLEANUP)

WEEKENDS AND HOLIDAYS: 24HRS

ARCHITECTURAL

· REMOVAL AND REPLACEMENT OF CEILING.

MECHANICAL

· VAV REPLACEMENT

· NEW HYDRONIC HEATING DISTRIBUTION LINES.

ELECTRICAL / COMMUNICATION

· REMOVAL AND REINSTALLATION OF CEILING

DEVICES

· ELECTRICAL WORK REQUIRED FOR THE NEW

VAV

FIRE PROTECTION

· REMOVAL AND REINSTALLATION OF CEILING

INSTALL FIRE SPRINKLER HEADS TO

ACCOMMODATE CEILING REMOVAL AND

REINSTALLATION

HAZARDOUS MATERIAL

· ABATEMENT WORK MAY BE REQUIRED FOR

HVAC EQUIPMENT REPLACEMENT

PLAN

NORTH

0 10m5m 15m

M .N

AK

AI

M A

L.

M

O R

AD

A

C .M

AR

TI

N

AH

L-

G

AE

J V, L

LC

SE

C

O N

D F

LO

O

R P

H

AS

IN

G

P

LA

N

GC103

B1585

W912HV-24-B-0002 Attachment 01 32 01.00 10-A Page 4 (AM-0001)

Phase 4

The access routes are no longer divided into daytime, nighttime access, but these paths may change as the re-phasing coordination is finalized.

Previous day/time restrictions no longer applicable

Phase 2A

Phase 2C

Phase 2BPhase 2A

Phase 3B

Phase 3A

Phase 7

Phase 6A

Phase 6B

Phase 6C

Phase 5A

Phase 5B

Phase 8 will replace the chillers.

Phase 9 will replace the five AHU's. Each AHU will be replaced sequentially with AHU-3 to be replaced last. While AHU-1, AHU-2, AHU-4 and AHU-5 are being replaced, one of the new AHU's will be used to provide temporary cooling/ heating to the affected spaces. A temporary tie in to the ducting from the roof will be required.

New AHU will be located either on the roof or at ground level.

File details come from the government source that posted it. Updated .