This Scope of Services document outlines a contract for replacing heating oil tanks at four housing locations for the Bering Land Bridge National Preserve in Nome, Alaska. The project involves replacing heating oil tanks at the NPS Bunkhouse (1,100-gallon tank), Warren Residence (500-gallon tank), and two duplex locations (500-gallon tanks each). The contract requires the contractor to procure and install UL-listed double-wall secondary containment tanks, disconnect and dispose of existing tanks, and complete all installations by August 28, 2026. The work includes comprehensive project management, detailed submittals, daily construction reporting, and adherence to multiple technical standards from organizations like NFPA, ASME, and UL. The contract is structured with a base task for the Bunkhouse and three optional tasks for the other locations, with each task priced as a lump sum. Key deliverables include product submittals, shop drawings, monthly status reports, and full documentation of tank installations and disposals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Services

Replace Heating Oil Tanks at Four Housing Locations

Bering Land Bridge National Preserve

Nome, AK

9 September 2025

1.0 PROJECT OVERVIEW

1.1 SUMMARY OF WORK

1.2 PROJECT LOCATION

1.3 CONTRACT COMPLETION DATE

1.4 CONTRACT LINE ITEMS

1.5 POINTS OF CONTACT

2.0 SITE DESCRIPTION

3.0 EXECUTION

3.1 PROJECT MANAGEMENT

3.1.1 Post-Award Coordination Meeting

3.1.2 Monthly Status Reports

3.2 WORK PLANNING

3.2.1 Pre-Construction Submittals

3.2.2 Product Data and Product Selection

3.2.3 Shop Drawings

3.2.4 Procurement and Transportation

3.3 ON-SITE WORK

3.3.1 Daily Construction Reports

3.3.2 Contractor Use of Site

3.3.3 Building Occupancy

3.3.4 Disconnect Existing Tanks

3.3.5 Dispose of Removed Tanks

3.3.6 Install New Tanks

3.3.7 Closeout Requirements

4.0 SUBMITTALS

4.1 SUBMITTAL REQUIREMENTS

4.2 NPS REVIEW OF SUBMITTALS

4.3 GENERAL SCHEDULE FOR SUBMITTALS AND PROGRESS PAYMENTS

4.4 CONTRACTOR QUALITY CONTROL

5.0 PRODUCTS

5.1 GENERAL

5.2 FUEL OIL PIPING

5.3 UNIONS AND FLANGES

5.4 VALVES

5.4.1 Ball Valves

5.4.2 Check Valves

5.4.3 Relief Valves

5.5 HANGERS AND SUPPORTS

5.6 STRAINERS

5.7 FLEXIBLE CONNECTORS

5.8 DE-AERATOR FUEL FILTERS

5.9 ABOVE GROUND STORAGE TANKS

5.9.1 Product Description:

5.9.2 Accessories:

6.0 COORDINATING INSTRUCTIONS

6.1 CONTRACTING OFFICER’S AUTHORITY

6.2 PUBLIC AFFAIRS

7.0 ATTACHMENTS

8.0 REFERENCES

TABLES

Table 1: Tasks by Number Table 2: Submittals by Type Table 3: Submittal Planning and Invoicing Timeline

1.0 PROJECT OVERVIEW

1.1 Summary of Work

The primary objective of this project is to replace heating oil tanks and associated system components that provide heating to four housing units managed by Bering Land Bridge National Preserve (BELA), a unit of the National Park Service (NPS) in Nome, AK.

This work consists of the following major elements:

• Submission of product and planning data for NPS approval,

• Procurement of new heating oil tanks, including appropriate appurtenances and connections,

• Transportation of tanks and attachments to the Project Site,

• Removal of existing tanks on site,

• Final disposal of removed tanks,

• Installation of new heating oil tanks, including appropriate appurtenances and connections,

• Provision of appropriate manuals and warranties, and

• Overall project management.

1.2 Project Location

Bering Land Bridge National Preserve (BELA) is located on the Seward Peninsula on the western coastline of Alaska. The Preserve is headquartered in Nome, AK, located approximately 540 miles northwest of Anchorage, AK and accessible via commercial jet flight.

All four facilities requiring heating oil tank replacement are in Nome. They are:

• NPS Bunkhouse, located at 507 W 4th Avenue. This two-story bunkhouse is served by one tank on the north side of the building. The fuel tank is guarded by two bollards.

• Warren Residence, located at 500 W C Street. This single-family home is served by one tank on the east side of the building. There are two bollards protecting the fuel tank.

• Duplex 205, located at 205 E 5th Avenue. This duplex is served by one tank located on the northwest corner of the building. The fuel tank is surrounded by a fence on two sides.

• Duplex 203, located at 203 E 5th Avenue. This duplex is served by one tank located on the northwest corner of the building. The fuel tank is surrounded by a fence on two sides.

Review the attached photograph package to see existing conditions.

1.3 Contract Completion Date

All base tasks shall be completed with final deliverables approved no later than 28 AUG 2026.

If an Option Item is exercised, the Contract Completion Date may be extended at the CO’s discretion.

1.4 Definition of Contract Line Items

CLIN Task No. Task Name Pricing 0010 Base Bunkhouse Tank Replacement Lump Sum 0020 OPTION A Warren House Tank Replacement Lump Sum 0030 OPTION B 203 Duplex Tank Replacement Lump Sum 0040 OPTION C 205 Duplex Tank Replacement Lump Sum

Table 1: Contract Line Items

1.5 Points of Contact

The following individuals are identified as points of contact for the NPS during the performance of this contract.

Contracting Officer’s Representative

(COR)

Zachary Taylor 240 W. 5th Avenue Anchorage, AK 99501 P: 907-644-3387 Email: Zachary_Taylor@nps.gov

Contracting Officer (CO) Francisco Velasco 240 W. 5th Avenue Anchorage, AK 99501 P: 907-644-3313 Email: francisco_velasco@nps.gov

BELA Facilities POC Dylan Wozniak 214 Front St, Nome, AK 99762 Email: dylan_wozniak@nps.gov

2.0 SITE DESCRIPTION

3.0 EXECUTION

All tasks shall be performed in accordance with applicable guidance and regulations from NPS.

Nothing in this contract shall exempt the Contractor from Federal, State, or local laws or regulations unless a specific exemption has been acquired. Table 1 provides a summary of the tasks in this Scope of Work (SOS). The Contracting Officer may unilaterally exercise the identified option(s) at any time within 60 days after award.

3.1 Project Management

The Contractor shall conduct coordination of project activities to ensure that all stakeholders are kept informed of the project status, existing or potential problems, and any changes required to prudently manage the project and meet the needs of the project stakeholders and decision-makers. The Contractor shall be responsible for project management, project planning, and meeting activities.

3.1.1 Post-Award Coordination Meeting

Within fifteen (15) days of award of this contract, the Contractor shall organize and execute a Post- Award Coordination Meeting with NPS to discuss, at a minimum: Park backgrounds; travel logistics/recommendations; the scope of this project; work to be conducted; the project schedule; and any Contractor questions. The location of the meeting will be at a time and location acceptable to the mailto:Zachary_Taylor@nps.gov mailto:francisco_velasco@nps.gov mailto:dylan_wozniak@nps.gov government. A virtual meeting is acceptable for this requirement. This meeting is expected to last no more than two hours.

3.1.2 Monthly Status Reports

The Contractor shall prepare monthly status reports (MSRs) consisting of a brief summary of work that has been performed over the past month, work currently underway, work planned for the upcoming month, communications from NPS, and other pertinent project information. Each status report shall include the most recent published schedule and state whether current work is adhering to the schedule. If the work is not on schedule, the Contractor shall state what actions to rectify the delay. MSRs shall be submitted to the NPS Contracting Officer’s Representative (COR) electronically, by the 10th calendar day of the following month.

3.2 Work Planning

3.2.1 Pre-Construction Submittals

No later than the Post-Award Coordination meeting, the Contractor shall submit the following:

• Letter designating Project Manager/Superintendent

• Project Schedule

• A comprehensive breakdown of the Schedule of Values

• Accident Prevention Plan

• A list of Subcontractors for this project

• Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).

3.2.2 Product Data and Product Selection

Based on the products outlined in Section 5.0, the Contractor shall provide cut sheets for products intended to be used in the fulfillment of this work as submittals for NPS review and approval.

3.2.3 Shop Drawings

The Contractor shall provide a drawing package for each location showing a profile view and plan view of the tank with dimensions, the intended tank location, and marked connections to the housing units as a submittal for NPS review and approval.

3.2.4 Procurement and Transportation

After NPS approval of product submission, the Contractor shall procure, stage, and ensure transportation of materials to Nome, AK.

3.3 On-Site Work

3.3.1 Daily Construction Reports

During the period of work in Nome, the Contractor shall provide daily construction logs (dailies) consisting of a summary of work for the day, pictures of actions taken by the on-site team, work planned for the next day, significant events including milestones reached and delays encountered, and an updated project schedule. Submit dailies as a single document attached to email to the NPS Points of Contact.

3.3.2 Contractor Use of Site

Contractors may stage materials on NPS property. Confine storage of materials to the fenced laydown yard referred to as the “Dog Lot” at 243 E 5th Avenue, Nome, AK until prior to placement.

Contractors may park in areas immediately adjacent to NPS facilities at which work is occurring.

Use of NPS utilities may be available. Coordinate with the BELA representative to determine appropriate connection points and if use will be metered.

3.3.3 Building Occupancy

NPS buildings will be occupied by residents during execution. Ensure that all building entrances are accessible by residents and that activities do not interfere with day-to-day operations.

3.3.4 Disconnect Existing Tanks

The Contractor shall safely disconnect existing heating oil tanks and connecting lines from each structure and remove all materials such as to allow the installation of new equipment.

3.3.5 Dispose of Removed Tanks

The Contractor shall fully dispose of removed fuel tanks according to all appropriate local laws and regulations at an appropriate waste collection facility. Upon disposal, the Contractor shall submit a certification that the tanks are at an appropriate waste collection facility for NPS review.

3.3.6 Install New Tanks

The Contractor shall install new fuel tanks at prescribed locations. Installation shall include connection to housing and verification of operation.

3.3.7 Closeout Requirements

Prior to demobilization, NPS shall inspect all installed tanks for operability and conformance to NPS specifications. The Contractor shall provide the NPS BELA representative all manufacturer’s operation and maintenance documentation for installed equipment.

Prior to the submission of a final invoice, the Contractor shall complete any remaining punch list items identified by NPS.

4.0 SUBMITTALS

4.1 Submittal Requirements

The Contractor shall be responsible for electronic delivery of submittals. All submittals shall be accompanied by a coversheet listing the material being submitted with each submission, use either the Denver Service Center CM-16 or similar. Submit documents in native and PDF file formats. PDF files shall be unlocked to allow printing and saving. See DBB Submittal Requirements, Contractor names and logos are not authorized on submittal covers or in headers/footers with the submittals.

4.2 NPS Review of Submittals

Draft submittals will be reviewed by the NPS PM/COR, by Park Facility Management staff, and by NPS code compliance staff. NPS must receive a complete submission before a review will be undertaken. Partial submissions will not be accepted without prior approval from the Contracting Officer. Review periods will culminate with delivery of comments on the document to the Contractor. It is anticipated all NPS comments for each document will be provided to the Contractor in a single electronic submission from the NPS PM/COR. However, if clarifications of comments are required, Contractor responses to comments are not acceptable, or other circumstances warrant additional comments by NPS, additional comments may be provided to the Contractor in writing via e-mail.

After receiving comments on a Draft design submission, the contractor will plan, resource, and execute an expected one-hour comment resolution meeting with the NPS team to discuss and resolve comments. Comment resolution meetings must be at a time and location acceptable to NPS.

Comment resolution meetings may be conducted in person or virtually and will follow the schedule guidance as described in Section 4.3 of this SOW.

4.3 General Schedule for Submittals and Progress Payments

Guidelines for the schedule of submittals are as follows. Days specified in the schedule below are calendar days, not business days. Where the schedule below requires submittals to be due on weekend or federal holiday dates, the submittal due date shall become the first business day following the weekend or holiday.

It is not required that submittals for both parks are submitted at once. They may be submitted individually in accordance with the planning timeline shown in Table 2. Review Attachment C for the full Submittal List.

The Contractor may request progress payments up to the authorized amounts for each billing milestone listed below. The Contractor shall email a draft itemized invoice with relevant supporting documentation to the Contracting Officer and COR and upload it to IPP only after receiving NPS concurrence on format and amount.

https://www.nps.gov/dscw/upload/TransmittalForm-CM16_10-7-20_v508_101420.pdf

Product/Event Planning Time/Due Date Authorized Invoice Amount

Pre-Con Submittals NLT Post-Award Coordination Meeting 5% of CLIN price

Post-Award Coordination Meeting NLT 15 days after Contract Award -- Monthly Status Reports NLT 10th of each month -- Equipment Cut Sheets & Drawings NLT 60 days after Contract Award 10% of CLIN price NPS Review Period 15 days after receipt of draft --

Revisions NLT 15 days after receipt of NPS comments

15% of CLIN price

Materials On Order NLT 7 days after NPS acceptance of Final Construction Drawings

60% of CLIN price

Materials Arrive in Nome IAW Project Schedule -- Mobilization/Installation Begins NLT 30JUN2026 -- Daily Reports Daily during the installation period -- All Tanks Installed & Tested IAW Project Schedule 95% of CLIN price Certification of Disposal NLT 60 days after tanks are removed 100% of CLIN price

Table 2- Submittal Planning and Invoicing Timeline

4.4 Contractor Quality Control

The Contractor shall ensure that appropriate internal quality control practices are employed throughout the performance of this contract. The Contractor’s quality control practices shall be internal, meaning that the Contractor shall not use the NPS technical review and comment procedure as a substitute for the appropriate internal quality checks and corrections. The objectives of the Contractor’s quality control practices shall be to ensure that submittals are complete, internally consistent, technically accurate, in compliance with accepted industry practices, and generally free from copy errors such as misspellings, grammatical errors, formatting problems, etc. Documents and procedures that are incomplete, internally inconsistent, technically inaccurate, out of compliance with accepted industry practices, affected by large numbers of copy errors, or otherwise not submitted in accordance with the requirements specified in this SOS will be rejected.

5.0 PRODUCTS

5.1 General

Section 5.0 provides guidance on appropriate materials, manufacturers, and compliance standards for components in the tank systems. For all named products, submit material/manufacturer data showing performance description and compliance with named standards. In the case that the Contractor would like to use a different product or manufacturer, substitutions may be approved by the CO following the submission of written justification.

5.2 Fuel Oil Piping

Steel Pipe: ASTM A53/A53M or ASME B36.10M Schedule 40 black.

Fittings: ASME B16.3, malleable iron, or ASTM A234/A234M wrought carbon steel and alloy steel welding type.

Joints Exterior: Welded or Viega MegaPress.

5.3 Unions and Flanges

Ferrous Piping: Class 150, malleable iron, threaded.

Dielectric Connections: Union with galvanized or plated steel threaded end, copper solder end, water impervious isolation barrier.

5.4 Valves

5.4.1 Ball Valves

1/4 inch to 1 inch: MSS SP 110, Class 125, two piece, threaded ends, bronze body; chrome plated bronze ball, reinforced Teflon seats, blow-out proof stem, lever handle, UL 842 listed for flammable liquids and LPG, full port.

5.4.2 Check Valves

Swing Check Valves 2 inches and Smaller shall be MSS SP 80, Class 150, bronze body and cap, bronze seat, Buna-N disc, threaded ends.

Spring Loaded Check Valves 2 inches and Smaller shall be MSS SP 80, Class 150 bronze body, in-line spring lift check, silent closing, Buna-N disc, integral seat, threaded ends.

5.4.3 Relief Valves

Shall be ASME certified and labeled. Maximum working temperature: 450 degrees F. Body: Bronze.

Seat: Viton or Monel. Stem and Springs: Stainless steel. Threaded ends. Automatic type, direct pressure actuated at maximum 60psi.

5.5 Hangers and Supports

Hangers for Pipe Sizes 1/2 to 1-1/2 inch shall be of Malleable iron or Carbon steel, adjustable swivel, split ring and shall conform to NFPA 31.

5.6 Strainers

Strainers shall be Y pattern, bronze body, threaded ends, Class 150, 1/32 inch stainless steel perforated screen. Acceptable manufacturers include:

• Mueller Steam Specialty.

• O.C. Keckley Company.

• Spirax Sarco, Inc.

5.7 Flexible Connectors

Connectors shall be of corrugated Type 304 stainless steel inner hose with single layer of Type 304 stainless steel exterior braiding. Maximum working pressure 200 psig. Acceptable manufacturers include:

• Flex-Hose Co., Inc.

• Flex-Weld, Inc.

• The Metraflex Company.

5.8 De-Aerator Fuel Filters

UL listed fuel oil de-aerator, converts single pipe supply to two-pipe system complete with fusible valve and integral fuel filter. Acceptable manufacturer is: Tigerholm Tigerloop Combi.

5.9 Above Ground Storage Tanks

5.9.1 Product Description:

Provide UL Listed above ground double-wall secondary containment tank. The tank shall consist of an inner and outer steel tank; the tank shall be a UL 142 listed and meet the standards of NFPA 30 and 30A. The entire tank system, including the skid and secondary containment, shall be listed by Underwriters Laboratories under UL® 142 Standard for Safety as a complete, indivisible unit. The skid mounted tank assembly shall bear the UL® listing mark.

Capacity: Tanks shall be of the following capacities for locations specified:

• Bunkhouse: 1,100-gal

• Warren House: 500-gal

• 203 Duplex: 500-gal

• 205 Duplex: 500-gal

Primary Tank: Single wall steel tank constructed in accordance with UL 142 not less than 3/16 inch thick.

Outer Tank: Single wall steel tank constructed in accordance with UL 142 not less than 3/16 inch thick.

Lifting Lugs: shall be attached at the top of the tank ends. Each eye shall be capable of supporting the empty weight of tank and skids without permanent distortion.

Tank skids: Tank skids shall be constructed according to UL standards. Skids shall be constructed to allow lifting of empty tank end or skidding of tank without distortion. The skid rails shall be constructed of structural steel beam and shall be listed as an integral part of the tank. Skid supports shall be constructed of plate steel, equal in thickness to the inner tank, with a 90 degree bent edge 1" wide on each side for structural support. Supports shall be placed directly under the inner tank heads and thereafter, evenly spaced along the tank, provided however, that such spacing shall not exceed 69". The skid supports shall be attached to a 12" wide saddle pad attached to the outer tank shell which is of sufficient length to encompass its bottom 120 degrees. A capped length of Schedule 80 pipe shall be attached to each end of the skid to function as a towbar when the tank is empty. The full 360 degrees of the towbar shall be encircled by the beam members.

Tank Saddles: Provide UL Listed horizontal tank saddles meeting the requirements of UL 142.

Saddles shall be constructed on top of the skids. Any portion of the saddle or supporting beam that is recessed into the skids shall not extend more than one-half the depth of the skid from the top flange.

Weld Joints: All joints on the inner and outer shell and the tank heads shall be that required by UL 142 listing. In addition, all non-structural external seams shall be seal welded before painting. All weld spatter shall be removed and all sharp edges shall be rounded and smoothed by grinding. Flat unflanged heads are not permitted on either the inner or outer tank.

Tank Attachments and Penetrations: Piping penetrations shall be made through the top of the tank only. The secondary containment shall allow for the full recovery of a release into the annular space.

An additional fitting shall be incorporated into the tank (typically located on the top of the opposite end of the tank from the monitor port) to allow for flushing of any product which may accumulate as the result of a release or accidental fill of the annular space. Each tank shall be equipped with lifting lugs adequate for the safe handling of the tank during installation. Each lifting lug must be designed to support the total weight of the dual wall tank. A minimum of two lifting lugs shall be provided on tanks having a rated capacity of more than 1100 gallons.

Finish: Factory painted with marine grade epoxy. A two coat system shall be applied according to the manufacturer's recommendations. The first coat shall be a minimum 2 mil dry film thickness primer coat. A second coat shall be applied to a given total of 6 mils minimum dry film thickness. All exterior surfaces shall be cleaned and prepared by sandblasting in accordance with Steel Structures Painting SSPC-3 and thereafter, coated per the coating manufacturer's recommendations.

Material for all steel construction shall conform to ASTM-36. All pipe and fittings shall conform to schedule 40, seamless iron pipe. All pipe connections shall be screwed or welded except for the final connection to the tank which shall be an approved welded fitting.

Normal Vent: Furnish each compartment of primary tank with 2 inch updraft venting device exhausting upward at elevation of at least 12 feet aboveground. Size vent in accordance with NFPA 30.

Vent Cap: Upward "V" design, steel cap and body, removable 30 mesh brass screen. Slip on style with set screw. Grooved drain lip extended beyond base.

Emergency Vents: Furnish each compartment of primary tank with emergency vents sized in accordance with NFPA 30. Do not use access openings for emergency venting purposes. OPW 301.

Monitor Port: Minimum 2 inch steel pipe with locking cap to be used for detecting leaks between primary and outer tanks.

Provide two spare 4" tappings on tank.

Drop Tube: Lightweight aluminum tube, buna gasket and adaptors as necessary for fill box or sufficient length to extend to six inches above tank bottom.

Signage: All tanks shall be labeled in accordance with the International Fire Code. Provide standard manufactured adhesive labels.

5.9.2 Accessories:

Level Gage: Mechanical float activated level gage capable of indicating approximate fluid level in tank reading in feet and inches. Gauge to be readable up to 20 feet away within 1/8". Gauge to be able to be rotated 360 deg after mounting. Standard float to pass through a 2" opening. Body to be aluminum with stainless steel float and cable. Morrison Bros. Co. Fig 818.

Tank Decals: Furnish warning and tank identification signs located prominently on tank following fire code requirements.

Fill Alarm: Whistles type alarm to whistle while tank is filled. Stops whistling when fuel has reached capacity level. Cast iron with corrosion resistant finish. King fill alarm model 4516.

Overfill prevention valve complete with tank adapter valve terminates flow of product when the liquid level reaches a preset warning level (90-95%). Valves to have built in bleed hole to provide anti-syphoning protection. Valve to be rated for a maximum pressure of 100 psi. OPW 61fSTOP.

Tank Ladders: Provide Federal OSHA compliant tank ladders as indicated. Provide ladders complete with full height side rails. Ladders to be hot-dip galvanized and shall have bolted connections to tanks so they can be removed for shipping. Hot dip galvanizing to be in accordance with ASTM A123.

6.0 COORDINATING INSTRUCTIONS

6.1 Contracting Officer’s Authority

The Contracting Officer (CO) is the only person with the authority to act as agent of the Government under this contract. Only the CO has authority to direct or negotiate any changes in the Statement of Work or specifications; modify or extend the period of performance; change the delivery schedule; or otherwise change any terms and conditions of this contract.

The CO is the only person authorized to make or approve any changes in any of the requirements of this contract and not withstanding any provisions contained elsewhere in this contract, the said authority remains solely in the CO. In the event the Contractor makes any changes at the direction of any person other than the CO, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.

The Government shall conduct periodic inspections of the Contractor’s work to determine compliance with the requirements of this contract. The NPS CO shall notify the Contractor of any work that is determined to be noncompliant with the contract requirements. The Contractor shall take immediate corrective action after receipt of such notice. The NPS CO may issue an order stopping all or part of the work until satisfactory corrective actions have been taken.

6.2 Public Affairs

All data and reports generated under this contract shall become the property of the Government.

Distribution of data or reports to any other source is prohibited. The Contractor shall not make available to the news media or publicly disclose any data generated or reviewed under this contract unless otherwise authorized in writing by the CO or the NPS PM. If approached by the news media or other public entities, the Contractor shall refer them to the CO for response.

7.0 ATTACHMENTS

Attachment A- Site Photographs

Attachment B- As-Constructed Documents for Existing Housing

Attachment C- Submittal List

Attachment D- NPS CM-16 Submittal Coversheet

8.0 REFERENCES

American Society of Mechanical Engineers:

• ASME B16.3 - Malleable Iron Threaded Fittings.

• ASME B31.1 - Power Piping.

• ASME B31.9 - Building Services Piping.

• ASME B36.10M - Welded and Seamless Wrought Steel Pipe.

• ASME Section IX - Boiler and Pressure Vessel Code - Welding and Brazing Qualifications.

ASTM International:

• ASTM A53/A53M - Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc- Coated, Welded and Seamless.

• ASTM F708 - Standard Practice for Design and Installation of Rigid Pipe Hangers.

American Welding Society:

• AWS A5.8 - Specification for Filler Metals for Brazing and Braze Welding.

• AWS D1.1 - Structural Welding Code - Steel.

International Mechanical Code - IMC, latest adopted edition.

National Fire Protection Association:

• NFPA 30 - Flammable and Combustible Liquids Code.

• NFPA 31 - Standard for the Installation of Oil-Burning Equipment.

Underwriters Laboratories Inc.:

• UL 567 - Pipe Connectors for Flammable Liquids and Combustible Liquids and LP-Gas.

• UL 842 - Valves for Flammable Fluids.

• UL 913 - Intrinsically Safe Apparatus and Associated Apparatus for Use in Class I, II, and III, Division 1, Hazardous Locations.

1.0 PROJECT OVERVIEW
1.1 Summary of Work
1.2 Project Location
1.3 Contract Completion Date
1.4 Definition of Contract Line Items
1.5 Points of Contact
2.0 SITE DESCRIPTION
3.0 EXECUTION
3.1 Project Management
3.1.1 Post-Award Coordination Meeting
3.1.2 Monthly Status Reports
3.2 Work Planning
3.2.1 Pre-Construction Submittals
3.2.2 Product Data and Product Selection
3.2.3 Shop Drawings
3.2.4 Procurement and Transportation
3.3 On-Site Work
3.3.1 Daily Construction Reports
3.3.2 Contractor Use of Site
3.3.3 Building Occupancy
3.3.4 Disconnect Existing Tanks
3.3.5 Dispose of Removed Tanks
3.3.6 Install New Tanks
3.3.7 Closeout Requirements
4.0 SUBMITTALS
4.1 Submittal Requirements
4.2 NPS Review of Submittals
4.3 General Schedule for Submittals and Progress Payments
4.4 Contractor Quality Control
5.0 PRODUCTS
5.1 General
5.2 Fuel Oil Piping
5.3 Unions and Flanges
5.4 Valves
5.4.1 Ball Valves
5.4.2 Check Valves
5.4.3 Relief Valves
5.5 Hangers and Supports
5.6 Strainers
5.7 Flexible Connectors
5.8 De-Aerator Fuel Filters
5.9 Above Ground Storage Tanks
5.9.1 Product Description:
5.9.2 Accessories:
6.0 COORDINATING INSTRUCTIONS
6.1 Contracting Officer’s Authority
6.2 Public Affairs
7.0 ATTACHMENTS
8.0 REFERENCES