This is a Statement of Qualifications (SOQ) evaluation document for Phase I prequalification standards for the City of Atlanta's Hemphill Water Treatment Plant Programmable Logic Controllers (PLC) and Supervisory Control and Data Acquisition (SCADA) Security Improvement Project. The project encompasses upgrades to control systems, network architecture migration from ControlNet to Ethernet/IP, conversion from iFix to AVEVA SCADA platforms, and implementation of cybersecurity enhancements while maintaining continuous plant operations. The City will conduct a competitive solicitation for qualified firms to deliver these integration services, with a Pre-Solicitation Conference to be noticed and held to clarify scope and address vendor questions.
Offerors must meet mandatory minimum qualification requirements to advance beyond Phase I prequalification, including submission of a project approach narrative, demonstration of at least five years of experience completing comparable end-to-end integration projects with at least five similar contracts completed within the past five years, proven ability to meet project schedules with evidence of at least two on-schedule projects, minimum ten years in business with qualified key personnel including a Project Manager with seven years of industrial controls experience and two years leading SCADA upgrades, and a Lead Programmer/Controls Engineer with seven years of ControlLogix PLC programming and AVEVA/similar SCADA development experience. Additionally, offerors must demonstrate satisfactory performance on at least three prior Allen-Bradley ControlLogix PLC and SCADA upgrades at water or wastewater treatment facilities within five years, including direct experience with AVEVA System Platform migration, and provide three verifiable references with performance documentation. The City reserves the right to verify all submitted experience and references, and any firm failing to meet one or more requirements will be deemed non-responsive and will not advance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Hemphill WTP PLC Network Drawing_Rev0.pdf | ||
| PSC_Draft_SOW _ Hemphill PLC Upgrade _ 4_21_2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hemphill Water Treatment Plant
Programmable Logic Controllers (PLC) &
Supervisory Control and Data Acquisition and Security Improvement Project (SCADA) Upgrades
Standards for Prequalification (Phase I)
Statement of Qualifications
Offerors must submit a comprehensive Statement of Qualifications that clearly demonstrates their technical expertise, organizational capacity, relevant experience, and ability to meet all requirements outlined in this solicitation. Firms must meet all minimum qualification requirements to be deemed responsive. The City will not score or rank submissions. Any firm failing to meet one or more requirements will be deemed non-responsive and will not advance.
The City reserves the right to verify all submitted project experience and references. Failure to substantiate qualifications may result in disqualification. Submissions must include all requested documentation, narrative responses, certifications, and supporting materials necessary for the City to assess the Offerors’ qualifications as outlined below:
• Project Approach Narrative:
Minimum Qualification Requirement – Offeror must submit a project-specific narrative addressing their approach to ControlNet → Ethernet/IP migration, iFix →
AVEVA conversion, cybersecurity, and strategy to maintain plant operations during upgrades.
• Firm Experience and Technical Capability:
Minimum Qualification Requirement - Offeror must demonstrate a minimum of five
(5) years of experience completing end-to-end integration projects of similar type, size, and complexity as described in this solicitation. Offeror must have successfully completed at least five (5) comparable contracts or projects within the past five (5) years.
Offeror must confirm ability to directly manage PLC programming and upgrades;
SCADA/HMI migration (iFix → AVEVA); Network architecture upgrades (ControlNet
→ Ethernet/IP), Factory Acceptance Testing (FAT), commissioning, live operational testing, and startup.
• Ability to Meet Schedule and Deliver Services on Time:
Minimum Qualification Requirement - Offeror must demonstrate a proven history of performing projects within required timeframes without material delays or service interruptions. Offeror must provide evidence of at least two (2) projects completed on schedule within the past five (5) years.
• Company Background and Management Capacity:
Minimum Qualification Requirement - Offeror must demonstrate a minimum of ten
(10) years in business providing services or supplies similar in scope and complexity.
Offeror must identify key management and operational personnel with relevant experience supporting the proposed services. The offeror must demonstrate that the
Project Manager has at least seven (7) years of experience in industrial controls projects and at least two (2) years of experience in a leadership role for SCADA upgrade projects.
The Lead Programmer/Controls Engineer should possess seven (7) years of demonstrated experience with PLC programming (ControlLogix) and SCADA/HMI development
(AVEVA or similar). Offeror must confirm that background checks will be conducted for all employees and that they will remain in compliance with City of Atlanta standards and coordination requirements.
• Past Performance on Similar Contracts:
Minimum Qualification Requirement - Offeror must demonstrate satisfactory performance on at least three (3) prior projects completing Allen-Bradley ControlLogix
PLC and SCADA upgrades at water or wastewater treatment facilities or of similar scope and complexity within the past five (5) years. Experience must demonstrate network migration to include HMI/SCADA platform migration. Firm must demonstrate direct experience working with AVEVA System Platform (Wonderware) and at least one completed migration to the AVEVA System Platform (Wonderware). Offeror must provide three (3) verifiable references and performance documentation verifying successful project completion.