SOO Atch G. Schedule of Material Submittals.xlsx

XLSX spreadsheet 29 KB Posted

Attached to
Marina Covered Storage Facility
Solicitation number
FA309925R0001
Issued by

About this file

This is a Schedule of Material Submittals spreadsheet for a Marina Covered Storage Facility construction project at Laughlin AFB (Project MXPX 24-5000). The document outlines required submissions across three phases: pre-construction, construction, and close-out.

Pre-construction submittals, due within 10-14 days after Notice to Proceed (NTP), include construction site plans, work clearance requests, project schedules, health and safety plans, quality control plans, and shop drawings. Construction phase submittals require bi-weekly progress reports and meeting minutes. Close-out documentation includes recycling disposal reports, hazardous waste documentation, completion inspection records, O&M manuals, DD Form 1354, as-built drawings, and warranty information. Most submittals require digital copies, with select items requiring additional paper copies. All submissions must go through contracting and civil engineering review processes, with specific tracking of approval/disapproval dates.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXPX 24-5000 PROJECT TITLE CONSTRUCT COVERED STORAGE FACILITY, MARINA SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALSTATEMENT OF OBJECTIVES REFERENCELAUGHLIN DIV 01 SPECS REFERENCEENVIRONMENTAL QUALITY CONSTRUCTION SPECIFICATIONS LAFBNUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS

APPR

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

DIS

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Pre-Construction Submittals
1Construction Site Plan, Laydown area2.6.1012.13.3.11 DigitalNLT 10 Days after NTP 1
2Work Clearance Request, AF Form 1032.6.73.3.11 DigitalNLT 10 Days after NTP 1
3Project Schedule Form3.26.1.11 DigitalNLT 14 Days after NTP 1
4Contract Progress Report3.26.1.21 DigitalNLT 14 Days after NTP 1
5Contractor Health and Safety Plan3.2.21 DigitalNLT 14 Days after NTP 1
6Worker/Area Protection Plan3.5.21 DigitalNLT 14 Days after NTP 1
7QC Plan4.2.41 DigitalNLT 14 Days after NTP 1
8QC Manager Qualifications4.2.31 DigitalNLT 14 Days after NTP 1
9Safety Data Sheets10.4.63.2.11 DigitalNLT 14 Days after NTP 1
11Solid Waste Management Plan5.11 DigitalNLT 14 Days after NTP 1
12Records of Existing Conditions1.5/7.1.11 DigitalNLT 14 Days after NTP 1
13Shop Level Drawings2.1/10.41 Paper copies, 1 DigitalNLT 14 Days after NTP 1
13aSite Plan3.11 DigitalNLT 14 Days after NTP 1
13eDetails3.11 DigitalNLT 14 Days after NTP 1
14Product Data10.4.51 DigitalNLT 14 Days after NTP 1
14eConcrete2.6.210.4.51 DigitalNLT 14 Days after NTP 1
15OPSEC/IP/ATFP Training6.22.41 DigitalNLT 14 Days after NTP 1
Construction Submittals
19Progress Report3.26.1.21 DigitalBi-Weekly
20Meeting Minutes6.2.11 DigitalNLT 3 Days after meeting
Materials
21Test Reports2.6.27.11 DigitalAs noted below
21aConcrete2.6.27.1N/ANLT 14 Days after placement
22Certifications and License Requirements3.17.11 DigitalAs noted below
22aTesting Laboratory3.17.11 DigitalNLT 14 Days after placement
Close-Out
23Recycling Disposal Report5.11 DigitalAt the Final Inspection
24Hazardous Waste Disposal Documentation3.2.21 DigitalNLT 30 Days after NTP 1
25Completion Inspection (QC Manager Punchlist)13.41 DigitalBy Pre-Final Inspection
26O&M Data (Manuals)1.2/10.41 Paper copy, 1 DigitalNLT 2 weeks after Final Inspection
27Draft DD Form 135410.4.141 DigitalNLT 3 weeks Prior to Pre-Final Inspection
28Final DD Form 135410.4.141 Paper copy, 1 DigitalAt the Final Inspection
29As Built Drawings/CAD Files10.4.141 Paper copy, 1 DigitalNLT 2 weeks after Final Inspection
30Warranty10.4.141 Paper copy, 1 DigitalNLT 2 weeks after Final Inspection
Schedule of Submittals Template, Feb 05 (SAF/AQCP)