SolicitationAttachment1StatementOfWork_1232SA26Q0994.pdf

PDF 839 KB Posted

Attached to
Greenhouse Support Pipe Repair Federal contract opportunity
Solicitation number
1232SA26Q0994
Issued by
Department of Agriculture Agricultural Research Service

About this file

This is a Statement of Work (SOW) for greenhouse structural repair and gutter replacement work at the USDA Agricultural Research Service's Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center in Hilo, Hawaii.

The project scope involves repairing thirteen deteriorated galvanized steel support pipes along the greenhouse perimeter and installing a new metal guttering system. Work includes cutting and removing approximately fifty linear feet of corrugated polycarbonate wall paneling from the front wall and excavating approximately one hundred linear feet of insect screen from the side walls to access support pipe bases. The contractor must remove all deteriorated pipe sections and furnish new galvanized steel pipe of equivalent or larger diameter and wall thickness, welding replacement sections using industry-standard practices and applying zinc-rich galvanized repair coating to all field welds. Each support pipe requires installation of a hot-dip galvanized steel base plate (12" x 12" x ½" minimum thickness) welded to the pipe bottom and secured with four 7" x 5/8" hot-dip galvanized anchor bolts embedded in new concrete footings (24" minimum depth, 12" x 12" top dimensions, minimum 3,000 psi compressive strength). Additionally, the contractor must remove approximately 96 linear feet of existing gutter on the north side and install 96 linear feet of new metal gutter matching the existing width. The contract timeline is 90 calendar days from Notice to Proceed, with site access restricted to 7:30 a.m. to 4:00 p.m. Monday through Friday excluding federal holidays. The contractor is responsible for all labor, equipment, materials, permits, independent inspection and testing, Site Specific Safety Plan development, and quality control. A one-year warranty on workmanship is required prior to final payment.

View the file

Other files for this federal contract opportunity

Other files attached to Greenhouse Support Pipe Repair, newest first.
File Type Posted
Solicitation_1232SA26Q0994.pdf PDF
SolicitationAttachment3LimitationsOnSubcontracting_1232SA26Q0993.pdf PDF
SolicitationAttachment2WageDetermination_1232SA26Q0994 Service.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

GREENHOUSE SUPPORT PIPE

REPAIR AND GUTTER

REPLACEMENT

USDA ARS DKI PBARC TPGRDRU–Hilo Repository

HILO, HI, 96720

Date: June 1, 2026

STATEMENT OF WORK

1.0 CONTRACT PROJECT:

a. Project Number: TBD

b. Project Title: Greenhouse Support Pipe Repair

c. Project Location: USDA ARS DKI PBARC TPGRDRU – Hilo Repository 928 Stainback Highway, Hilo, HI

2.0 PROJECT CONTACT PERSONS:

a. CONTRACTING OFFICER (CO):

TBD

USDA-ARS-PWA

Email: Tel. No.:

b. RESEARCH LEADER (RL) Tracie Matsumoto USDA Agricultural Research Services Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center 64 Nowelo St. Hilo, HI, 96720 Email: Tracie.Matsumoto@usda.gov Tel. No: 808-959-4358

c. ADMINISTRATIVE OFFICER (AO)

Carlee Wehrsig USDA Agricultural Research Services Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center 64 Nowelo Street, Hilo, HI 96720 Email: Carlee.Wehrsig@usda.gov Tel. No.: 808-959-4312

d. LOCATION CONTRACTING OFFICER REPRESENTATIVE (COR)

Dustin Galapir USDA Agricultural Research Services Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center

Email: Dustin.Galapir@usda.gov Tel. No.: 808-333-0016

e. SAFETY OFFICER (CDSO) Matthew Siderhurst or Charles Mason USDA Agricultural Research Services Daniel K. Inouye U.S. Pacific Basin Agricultural Center

Email: Matthew.Siderhurst@usda.gov or Charles.Mason@usda.gov mailto:Tracie.Matsumoto@usda.gov mailto:Carlee.Wehrsig@usda.gov mailto:Dustin.Galapir@usda.gov mailto:Matthew.Siderhurst@usda.gov mailto:Charles.Mason@usda.gov

3.0 PROJECT DESCRIPTION:

This project consists of repairing thirteen (13) deteriorated greenhouse structural support pipes. Work includes replacing corroded pipe sections, installing new foot plates and concrete footings, and restoring greenhouse wall panels and associated components. The objective is to restore the structural integrity of the greenhouse and extend the service life of the facility. Install new metal gutting system on both sides of greenhouse.

4.0 PROJECT REQUIREMENTS:

a. Do not disturb hazardous materials and report condition immediately to the Location Monitor regarding potentially hazardous conditions that are uncovered. Stop work in the area of the questionable material or condition until identification and direction is provided.

b. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e., IBC, NEC, NSPC, NFPA, EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.

c. Access the site between 7:30 am and 4:00 pm Monday through Friday excluding federal holidays. Contractor staff must sign-in on the first day of arrival and then sign-out on the final day of the project, upon completion.

4.1 Background & Site Description:

Government has a need to repair and prevent further deterioration and maintain structural integrity of the greenhouse. The greenhouse structure is supported by galvanized steel pipe located along the perimeter of the facility. Over time, the lower sections of several support pipes have deteriorated due to prolonged exposure to moisture and environmental conditions. Inspection of several pipe identified thirteen (13) support pipes need to be repaired.

The work site consists of an existing greenhouse facility. The greenhouse is enclosed with corrugated polycarbonate wall panels, aluminum trim, and insect screen. The support pipes requiring repair are located along the perimeter walls and are partially concealed by existing corrugated polycarbonate wall panels and insect screen. Contractor access will require temporary removal of portions of the lower wall panels, insect screen and associated trim.

Refer to Figure 1

4.2 Bid Schedule:

Provide all labor, equipment and materials to perform this Statement of Work and Schedule of Items.

4.3 Description of Work:

a. Front Wall Access

a. Cut and remove approximately fifty (50) linear feet of existing corrugated polycarbonate wall paneling from 1st support beam down to the bottom support channel.

b. Remove all associated fasteners and lower corrugated polycarbonate wall panel sections as required to provide adequate access for repairs

c. Exercise care to prevent damage to adjacent greenhouse components that are not scheduled for replacement.

d. Refer to Figure 2

b. Side Wall Access

a. Remove all associated fasteners and trim sections as required to provide adequate access for repairs.

b. Excavate and temporarily remove or secure approximately one hundred (100) linear feet of insect screen and associated materials as required to expose support pipe bases and concrete footings.

c. Store removed materials in a manner that prevents damage and allows for reinstallation.

c. Support Pipe Repairs

a. Cut and remove all deteriorated structurally compromised sections of the existing 4-inch support pipes.

b. Furnish and install new galvanized steel pipe section of equivalent or slightly larger diameter and wall thickness to match existing structural members.

c. Weld replacement pipe sections with the existing support pipes using industry-standard welding practices.

d. Grind and finish all welds to provide smooth, structurally sound connection.

e. Apply a zinc-rich galvanized repair coating to all field welds and areas where galvanization has been damaged during construction.

d. Foot Plate

a. Requirements

i. Base plate must be hot-dip galvanized steel

ii. Minimum plate thickness must be half (1/2”) inch

iii. Plate dimensions must be twelve (12”) inches by twelve (12”) inches

b. Installation

i. Base plate must be welded to the bottom of the replacement pipe sections on support pipe using industry-standard welding practices.

ii. Each base plate shall be secured to the concrete footing using four (4) 7” x 5/8” hot-dip galvanized anchor bolts.

iii. Install moisture barrier or approved non-corrosive isolation material between the concrete footer and steel base plate to minimize future corrosion.

c. Refer to Figure 3

e. Concrete Footing

i. Footing Depth: twenty (24”) inches minimum

ii. Top dimensions: twelve (12”) x twelve (12”) inches minimum

iii. Concrete must achieve a minimum compressive strength of 3,000 psi.

b. Installation

i. Embed four (4) 7”x 5/8” anchor bolts within each footing to secure the base plate.

ii. Anchor bolts placement shall align with base plate bolt holes.

c. Refer to Figure 3

f. Gutter Replacement

i. Must match existing gutter width

ii. Replace all hardware and hangers needed to install new gutter

b. Installation

i. Remove approximately 96’ of existing gutter system on north side of greenhouse

ii. Install approximately 96’ of new metal gutter and gutter system

4.4 Government Furnished Equipment\Services

a. Government will furnish a reasonable amount of electricity and water for the project.

5.0 GENERAL REQUIREMENTS:

5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Government. All disturbances of existing systems shall be thoroughly coordinated with the Government to prevent disturbances that might jeopardize on-going operations and research. Government reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Government prior to starting demolition operations.

Contractor shall legally dispose all any materials removed that will not be retained.

5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.

5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the Location Monitor for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.

5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the Location Monitor. Quality control is the exclusive responsibility of the Contractor. The Contractor shall retain and pay for the services of an independent inspector or testing laboratory to perform all tests expressly required by this contract.

5.6 Protection of Work and Property/Safety Requirements:

a. Contractor shall furnish a Site Specific Safety Plan (SSSP) or Accident Prevention Plan (APP) ten days after contract award. SSSP / APP shall be approved by the Government before construction work commences.

b. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the Location Monitor.

c. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.

d. Contractor is responsible for verifying location of any underground utilities and is responsible for any damage caused to such utilities.

5.7 Temporary Facilities:

a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.

b. Should the Contractor require any power or utility shutdowns during construction, the

Contractor shall obtain approval for such shutdown from the Location Monitor fourteen

(14) calendar days prior to the need.

5.8 Materials and Equipment:

a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.

b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/Location Monitor.

c. Government will not furnish any labor or equipment to unload or move materials or supplies.

5.9 Cleanup: The construction site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the Location Monitor.

5.10 Warranty:

a. Submit data concerning the standard one-year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.

5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO

FINAL PAYMENT (other documents may also be required):

a. General contractor’s minimum one (1) year warranty on work.

b. Release of liens

c. Final Invoice

6.0 Project Schedule:

The Contract time for this project is 90 calendar days from Notice to Proceed.

7.0 Figures

Figure 1

Figure 2

Figure 3

File details come from the government source that posted it. Updated .