This is a Request for Quotation (RFQ) for demolition and site restoration services at Northfield Brook Lake in Thomaston, Connecticut, issued by the U.S. Army Corps of Engineers, New England District.

The solicitation (W912WJ26QA130) requires contractor performance of three primary tasks: (1) demolition and removal of one wooden picnic shelter (approximately 40' x 23' x 15' height) including roofing materials, concrete pad, asphalt apron, and grill, with structurally sound posts and beams salvaged for Government reuse; (2) demolition and removal of seventeen concrete picnic tables and associated concrete pads; and (3) backfill and restoration of disturbed areas with topsoil and grass seed. The work must be completed within 120 calendar days of contract award. All work is classified under NAICS code 562119 (Waste Collection) with a firm fixed price arrangement. The project is set aside as a 100% women-owned small business (WOSB) with a small business size standard of USD 47,000,000. The offer due date is July 20, 2026, at 2:00 PM. Quotes must be submitted via email to Contract Specialist Alicia N. LaCrosse (Alicia.N.LaCrosse@usace.army.mil, 978-318-8902). Technical inquiries should be directed to Park Ranger Rachel Beach (Rachel.k.beach@usace.army.mil, 860-338-0178). Interested vendors must be registered in the System for Award Management (SAM) and may schedule site visits by contacting the technical point of contact. The solicitation incorporates standard FAR and DFARS clauses including service contract labor standards, payment by electronic funds transfer via WAWF, and various compliance and security requirements. A mandatory Accident Prevention Plan, Activity Hazard Analysis for each task, First Aid/CPR certifications, Site Safety and Health Officer designation, and equipment safety inspections must be submitted within 21 days of contract award before any field work commences. Evaluation will be based on technical capability, price, and past performance.

View the file

Other files

File Type Posted
Attachments 26QA130.pdf PDF
Solicitation Survey 26QA130.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WOMEN-OWNED SMALL

BUSINESS (WOSB)

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

1. REQUISITION NUMBER PAGE 1 OF

2. CONTRACT NUMBER 3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE

DATE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME b. TELEPHONE NUMBER (No collect 8. OFFER DUE DATE/

LOCAL TIME

9. ISSUED BY

13b. RATING

14. METHOD OF SOLICITATION

CODE

15. DELIVER TO 16. ADMINISTERED BY CODE

18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/

OFFEROR

CODE

FACILITY

CODE

CODE

TELEPHONE NUMBER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED

REQUEST

FOR QUOTE

(RFQ)

INVITATION

FOR BID

(IFB)

REQUEST

FOR

PROPOSAL

(RFP)

SEE ADDENDUM

19.

ITEM NUMBER

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH

AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND

ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS

SPECIFIED

29. AWARD OF CONTRACT: REFERENCE OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

10. THIS ACQUISITION IS UNRESTRICTED OR

NORTH AMERICAN

INDUSTRY CLASSIFICATION

STANDARD (NAICS):

SIZE STANDARD:

13a. THIS CONTRACT IS A

RATED ORDER UNDER

THE DEFENSE PRIORITIES

AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

SET ASIDE: % FOR:

11. DELIVERY FOR FREE ON

BOARD (FOB) DESTINATION

UNLESS BLOCK IS MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

ARE ARE NOT ATTACHED

ARE ARE NOT ATTACHED

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

8(A)

ECONOMICALLY

DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

HUBZONE SMALL

BUSINESS

SMALL BUSINESS

NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.

calls)

Solicitation/Contract Form Continuation

Picnic Shelter and Concrete Picnic Table Demolition, Northfield Brook Lake, Instrument Name:

Thomason, CT

Product Service Code : P500

W912WJ26QA130

Continuation of Supplies or Services and Prices/Costs

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price

Amount

0001 Contractor shall provide all labor, materials, equipment, and transportation to demolish and remove the existing picnic shelter and associated pad (posts and beams to be set aside for reuse) at Northfield Brook Lake, Thomaston, CT in accordance with the Performance Work Statement.

Product Service Code: P500 North American Industry Classification System (NAICS): 562119 Pricing Arrangement: Firm Fixed Price

1 Job

0002 Contractor shall provide all labor, materials, equipment, and transportation to remove and dispose of seventeen (17) concrete picnic tables and associated pads at Northfield Brook Lake, Thomaston, CT in accordance with the Performance Work Statement.

Product Service Code: P500 North American Industry Classification System (NAICS): 562119 Pricing Arrangement: Firm Fixed Price

1 Job

0003 Contractor shall provide all labor, materials, equipment, and transportation to backfill and restore all disturbed areas with topsoil and grass seed at Northfield Brook Lake, Thomaston, CT in accordance with the Performance Work Statement.

Product Service Code: P500 North American Industry Classification System (NAICS): 562119

1 Job

Pricing Arrangement: Firm Fixed Price

Continuation of Description

INTERESTED VENDORS SHALL REVIEW THE "ADDENDUM TO 52.212-1" AND "ADDENDUM

TO EVALUATION" FOR INSTRUCTIONS AND EVALUATION CRITERIA. VENDORS ARE

RESPONSIBLE FOR ENSURING THEIR QUOTE SUBMISSION MEETS ALL REQUIREMENTS.

FAILURE TO DO SO MAY RESULT IN QUOTES BEING DEEMED NON-RESPONSIVE AND

REMOVED FROM CONSIDERATION.

THE MANDATORY SOLICITATION SURVEY SHALL BE COMPLETED IN ITS ENTIRETY AND

RETURNED WITH QUOTES. FAILURE TO DO SO MAY RESULT IN QUOTES BEING DEEMED

NON-RESPONSIVE AND REMOVED FROM CONSIDERATION.

PERFORMANCE WORK STATEMENT:

PICNIC SHELTER AND CONCRETE PICNIC TABLE DEMOLITION

U.S. ARMY CORPS OF ENGINEERS

NORTHFIELD BROOK LAKE

THOMASTON, CT

PERFORMANCE WORK STATEMENT

I. GENERAL

1. Scope

Contractor will provide all equipment, materials, labor and transportation necessary to perform the following work:

a. Demolish and dispose of one (1) wooden shelter, including the associated roofing materials, concrete pad, asphalt apron and grill. Shelter and concrete pad footprint is approximately 40'x 23' and shelter is approximately 15' at peak height. All structurally sound post and beam materials shall be salvaged and set aside in a designated on-site area for Government re-use.

b. Demolish and dispose of seventeen (17) concrete picnic tables and all associated concrete pads.

c. Backfill and restore any disturbed areas with topsoil and grass seed.

2. Location

Northfield Brook Lake is located at 1550 Northfield Road in Thomaston, CT, 06787.

3. Technical Point of Contact

The Technical Point of Contact is Park Ranger Rachel Beach. The Technical Point of Contact can be reached by phone at 860-338-0178 or by email at: Rachel.k.beach@usace.army.mil.

4. Site Visit

Contact the Technical Point of Contact to arrange a site visit. Site visits are generally held between 7:00 am and 3:30 pm Monday through Friday.

5. Schedule

The work shall be completed no later than 120 days after Contract Award. The project area will be open to the contractor Monday through Friday 7:00 AM to 3:30 PM and all work must be done during those hours unless additional hours are approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays unless approved in advance by the Technical Point of Contact. Please note that the project may be subject to flooding as well as heightened security measures, which may require work to be re-scheduled. At least twenty-four

(24) hours' notice will be provided to the Contractor by the Technical Point of Contact in these instances.

6. Safety

a. General:

All work shall be conducted in accordance with the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1, most recent addition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements.

A copy of EM 385-1-1 can be accessed at the project office or electronically at the following link:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.

b. Accident Prevention Plan (APP):

The Contractor shall prepare a site-specific Accident Prevention Plan. The APP must be written by a Competent Person (CP) and document the specific work processes, equipment, materials to be used, hazards and applicable control measures.

The mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) must be submitted and accepted prior to beginning on site work:

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_2023Aug31.pdf

A preparatory meeting shall be conducted by the Prime Contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

c. Activity Hazard Analysis (AHA):

An AHA shall be submitted and accepted for each definable feature of work (DFOW) in accordance with EM 385-1-1, Chapter 2-6. A DFOW is defined as any task, which is separate and distinct from other tasks, has separate control requirements, or is identified as different trades or disciplines. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

For a non-mandatory formatted outline of an AHA, see ENG Form 6206 (Activity Hazard Analysis) https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf

d. Site Safety and Health Officer (SSHO) Requirements:

The Contractor shall employ a minimum of one person to function as a Level 3, SSHO. A Level 3 SSHO is a designated Qualified Person (QP) or Competent Person (CP) with Safety and Occupational Health (SOH) responsibility that meets the requirements of EM 385-1-1, Chapter 2-3.

b and 2-4.b.

Level 3 SSHOs must have training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.

The SSHO shall be present at the project site and be responsible for overseeing the implementation of the Prime Contractor's SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter)

e. First-Aid and CPR Personnel Requirements:

For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR. When employees work alone, they must be certified in First Aid and be provided an effective means of communication to call for assistance in the event of an emergency.

Minimum First Aid and CPR qualifications are outlined in EM 385-1-1, Chapter 3-3.

f. Additional Personnel Requirements:

Other Competent Person (CP) or Qualified Persons (QP) may be required per EM 385-1-1 and/or other sections of this Performance Work Statement, based on the Definable Features of Work (DFOW) for this project.

g. Accident Reporting:

All accidents and near misses shall be investigated by the Contractor and reported to the Technical Point of Contact in accordance with EM 385-1-1, Table 2-1.

The mandatory ENG Form 3394 shall be completed and submitted to the Technical Point of Contact within seven (7) days of an incident: https://www.publications.usace.army.mil/Portals/76 /Publications/EngineerForms/Eng_Form_3394_2021Aug.pdf

h. Employee Exposure Data:

The Contractor shall electronically report total employee work hours (including subcontractors) to the Technical Point of Contact by close of business on the 10th calendar day of the following month.

i. Crystalline Silica

a. General: All activities that create a crystalline silica exposure must be completed in accordance with 29 CFR 1926.1153; Occupational Exposure to Respirable Crystalline Silica. The 1926.1153 standard has been deemed more stringent than EM 385-1-1, Section 6-7. i and shall be used as the primary standard for activities involving crystalline silica.

b. Submittals: A Silica Exposure Control Plan in accordance with 1926.1153 shall be submitted as a component of the Accident Prevention Plan (APP). At a minimum the plan must address the following:

i. The tasks in the workplace that involve exposure to silica;

ii. The engineering controls, work practices, and respiratory protection used to limit employee exposure to silica for each task;

iii. The housekeeping measures used to limit employee exposure to silica;

iv. The procedures used to restrict access to work areas, when necessary, to minimize the number of employees exposed to silica and their level of exposure, including exposures generated by other employers or sole proprietors;

v. Employee Training;

vi. Medical Surveillance

c. Specified Exposure Control Methods: Reference the link below to "Table 1: Specified Exposure Control Methods when Working with Materials Containing Crystalline Silica." Compliance can be achieved by fully and properly implementing the engineering controls, work practices, and respiratory protection set forth for the relevant task on this table: https://www.osha.gov/sites/default /files/2018-12/fy16_sh-29650-sh6_ExposureTable.pdf

d. Additional resources and information on OSHA's Respirable Crystalline Silica standard can be found at: https://www.osha.gov/silica-crystalline/construction#constructionstandard

7. Pre-Work Conference

Prior to the start of any work, the Technical Point of Contact will schedule and conduct a pre-work conference. The Contractor's Project Manager and Quality Control Personnel will be physically present to attend this meeting. The Contractor shall directly oversee all work on the project and the Project Manager and Quality Control Personnel shall have the authority to act on behalf of the Contractor. This conference will be held at the time and location agreeable to the Government and Contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract and to discuss the performance that will be expected from the contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's administration and inspection of contract work or obtain other pertinent information that might be required. At the pre-work conference, the Contractor shall provide the name of the project superintendent with a telephone number for project coordination.

NOTE: Field work cannot begin until all pre-work submittals have been submitted and accepted by the Government.

The following is a general list of items for discussion during this pre-work conference:

i. Authority of the Technical Point of Contact and Quality Assurance Inspectors

ii. Contractor's Safety Program

iii. Accident Prevention Plan

iv. Weekly Safety Meetings (Documented on NED Form 251)

v. Accident Reporting (ENG Form 3394)

vi. Contractor's Quality Control Plan

vii. Contractor's Equipment (including a current written safety inspection)

viii. Correspondence Procedure

ix. Communications

x. Administrative Procedures

xi. Invoice and Payment

8. Permits

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

9. Security

The Contractor will comply with all established security policies at Northfield Brook Lake. If applicable, Contractor shall comply with Projects Key Control Management Program. Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to closures, which in turn may reduce or inhibit the Contractor's ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent work in an area. The Contractor shall be given at least 24-hour notice of any such closure.

10. Contractor's Personnel

a. Employee Conduct - The Contractor shall be responsible for ensuring that the Contractor's employees strictly comply with all Federal, State, and Municipal laws. Any personnel activity, which, in the opinion of the Government, is deemed detrimental to the performance of the contract may result in the removal of Contractor employee/employees.

Examples of unbecoming actions or conduct include, but are not limited to, the following:

i. Cursing, harassment, or discrimination of and/or unwarranted physical contact with visitors, USACE personnel, or other Contractors

ii. Recurring written and/or verbal complaints from visitors, USACE personnel, or other Contractors.

iii. Unsafe operation of vehicles or equipment while on USACE property.

b. Removal of Contractor's Employees - The Technical Point of Contact may require the Contractor to immediately remove from the work site any employee of the Contractor or subcontractor, who, in the opinion of the Technical Point of Contact, endangers persons or property, or whose physical or mental condition is such that it would impair the employee's ability to satisfactorily perform assigned work. Notification to the Contractor shall be promptly made in writing if time and circumstances permit. Otherwise, notification shall be verbal or by telephone, and shall be confirmed in writing as soon as possible. No such removal, however, will reduce the Contractor's obligation to perform all work required under this contract, and immediate replacement will be made as required. This requirement shall not be made the basis of any claim for compensation or damages against the United States or any of its officers or agents.

Note: At least one of the Contractor employees on site shall be able to communicate effectively and efficiently with all project staff.

11. Payment

After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. The invoice must also include the company letterhead and this must match the data that is registered in the System for Award Management (SAM) registry. For jobs greater than 30 days the contractor may request multiple payments.

All invoices may be mailed to:

U.S. Army Corps of Engineers

331 Hill Rd.

Thomaston, CT 06787

Or emailed to Rachel.k.beach@usace.army.mil (preferred)

II. TECHNICAL REQUIREMENTS

1. Summary

Furnish all labor, material and equipment necessary to perform the following work:

a. Demolish and dispose of one (1) wooden shelter, including the associated roofing materials, concrete pad, asphalt apron and grill. Shelter and concrete pad footprint is approximately 40'L x 23'W and shelter is approximately 15'H at peak height. Please note: All structurally sound post and beam materials shall be salvaged and set aside in a designated on-site area for Government reuse. The bottom one foot of the main posts that are rotted, can be cut and disposed of.

b. Demolish and dispose of seventeen (17) concrete picnic tables and all associated concrete pads.

c. Backfill and restore any disturbed areas with topsoil and grass seed.

d. Signage and Warnings - The contractor must set up proper signage, traffic cones, and caution tape to cordon off the work area and limit the risk of entry by the public.

2. Existing Conditions

a. Northfield Brook Lake is a remote site; therefore, no restroom facilities are available on-site.

Access to site is restricted to vehicles by a locked gate. Contractors will be given access to the site as needed once contract is awarded.

b. For Site Details, See Figures 1-7.

c. Existing Picnic Shelter is primarily wood construction and includes asphalt shingle roof. Shelter measures approximately 40'L x 23'W.

d. Picnic tables each measure approximately 8'L x 6'W, and each is assumed to contain either rebar and/or wire mesh.

e. Associated concrete pads measure approximately 10'L x 10'W and are assumed to contain either rebar and/or wire mesh.

3. Submittals

Although the Government reviews submissions required by this Performance Work Statement, it is emphasized that the Contractor's work must be completed using proper internal controls and review procedures. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall resubmit to the Government in acceptable form within 14 days of the Government's response, unless additional time is granted by the Government in writing.

The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and accepted by the Government.

Pre-Work Submittals: Submitted within 21 days of Contract Award. Submittals must be accepted prior to the commencement of any field work.

a. Mandatory ENG Form 6293 (Accident Prevention Plan Worksheet)

b. Activity Hazard Analysis for each Definable Feature of Work (DFOW)

c. First Aid /CPR Certifications

d. Mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter)

e. Safety Data Sheet (SDS) for applicable materials.

f. Safety Inspection for all Heavy Equipment: The Contractor shall submit a current written safety inspection for all heavy equipment proposed for use on this contract.

g. Work Site Plan: Prior to the start of on-site work, the Contractor shall submit a site plan.

h. Work Plan and Schedule: The Contractor shall submit a written Work Plan describing the methods and equipment required to accomplish the work and provide the required environmental and worker protection; this plan will include a schedule of work.

4. Clean Up and Waste Disposal

The contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any designated storage areas free from accumulation of waste materials. Upon completing work in an area, the contractor shall remove any tools, equipment, and materials that are not the property of the Government. All disturbed areas resulting from contractor activities shall be restored by the contractor to the satisfaction of the Technical Point of Contact. All waste material will be disposed of offsite in accordance with all Federal, State, and Local regulations.

5. Environmental Protection

Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the contractor at the site, and the site will be inspected/ cleaned on a daily basis when working onsite. No burning is permissible. Water, air, and land resources shall not be adversely impacted during the course of the work. The contractor will take necessary steps to ensure all Federal, State, and Local environmental regulatory requirements are met at no additional cost to the Government.

Assurance of compliance with this section by subcontractors shall be the responsibility of the contractor.

6. Personal Protective Equipment

It is the contractor's responsibility to furnish and supply personnel with the proper personal protective equipment necessary for performing the work.

7. Government Resources

The Contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, water, electricity, telephone services or other resources.

8. Damage to Government and Private Property

The Contractor shall be responsible for restoring any Government facilities or structures damaged because of the Contractor's actions. The Contractor shall also be responsible for any damage to private property or injury to any person because of the firm's operations. The Contractor shall notify the Technical Point of Contact immediately of damage to Government and private property and injury to any person resulting from the Contractors' operation. Also, the Contractor shall notify the Technical Point of Contact of damage to Government facilities due to vandalism or other causes on the day such damage is first noticed. Trucks and/or trailers will be driven on existing roads only and not across or through park areas to facilities. The Contractor shall also restore landscape features (shrubs, flowers, grasses, etc.), which are damaged or destroyed by the firm's operation. Damaged or destroyed grass areas shall be re-planted as directed by the Technical Point of Contact, and shrubs and flowers which are damaged or destroyed shall be replaced from nursery stock of like size and kind.

9. Omissions

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

10. Quality Assurance

The contractor is responsible for the quality control of the contract work. The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

11. Other Contracts

The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other contractors and Government employees. The Contractor shall not commit or permit any act, which will interfere with the performance of work by another Contractor or by Government employees.

12. Receiving and Storing Materials

The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive materials or supplies for the contractor and will not be responsible for damage to the contractor's equipment or materials.

13. Requests for information

After Contract award, requests for information concerning the work of this project should be directed to the Technical Point of Contact, Park Ranger Rachel Beach, by phone at 860-338-0178 or by email at: Rachel.k.beach@usace.army.mil

III. Execution

1. Demolition of Picnic Shelter

a. For Site Details, See Figures 1-7.

b. The Contractor will safely demolish and remove the existing picnic shelter, including all roofing materials and associated concrete and asphalt aprons in accordance with Federal, State, and Local laws, regulations and codes. All structurally sound post and beam posts shall be set aside in a designated on-site area that will be coordinated with the Technical Point of Contact. The bottom one foot of the main posts (portion that is rotted) can be cut and disposed of.

c. The concrete base is assumed to contain either rebar and/or wire mesh

d. All debris and waste must be disposed of in accordance with State, Federal and Local law.

Material suitable for recycling such as the asphalt shingle roof, shall be separated and recycled when possible.

2. Demolition of Seventeen (17) Picnic Tables and Associated Concrete Pads

a. For Site Details, See Figures 1-7.

b. Demolition and removal of seventeen (17) concrete tables and associated concrete pads.

c. Each picnic table measures approximately 8'L x 6'W and are assumed to contain either rebar and/or wire mesh.

d. Associated concrete pads measure approximately 10'L x 10'W and are assumed to contain either rebar and/or wire mesh.

3. Site Restoration

a. Upon completion of demolition activities, all disturbed areas shall be properly backfilled and compacted with clean fill dirt, before finishing with minimum two inches (2") of screened topsoil, graded to match grade of the existing fine lawn.

i. Backfill may be a combination of screened fill dirt and imported topsoil. Soil with a high concentration of clay or silt shall not be used. All fill shall be compacted to 95% dry density.

b. Areas disturbed by picnic shelter removal will be seeded with a sun/shade mix tall fescue grass seed mixture applied in accordance with manufacturer recommended application rate for new lawn establishment.

c. Areas disturbed by picnic table removal will be seeded with a sun/shade tolerant tall fescue grass seed mixture applied in accordance with manufacturer recommended application rate for new lawn establishment.

*** END OF NARRATIVE ***

Requirements Picnic Shelter and Concrete Picnic Table Demolition, Northfield Brook Lake, Thomason, CT

Continuation of Deliveries or Performance

0001 Delivery Schedule From date of lead time event to completion of performance 120 Calendar Days

Date of Award 1 JobQuantity

Address and POC Place of Performance DoDAAC: 961113 CountryCode: USA

CORPS OF ENGINEERS NEW ENGLAND DIST

NORTHFIELD BROOK LAKE, 1550 NORTHFIELD ROAD, RT. 254 THOMASTON, CT

06787 UNITED STATES

RACHEL K BEACH, DELIVER_TO_EMP_ID_NO

0002 Delivery Schedule From date of lead time event to completion of performance 120 Calendar Days

Date of Award 1 JobQuantity

Address and POC Place of Performance DoDAAC: 961113 CountryCode: USA

CORPS OF ENGINEERS NEW ENGLAND DIST

NORTHFIELD BROOK LAKE, 1550 NORTHFIELD ROAD, RT. 254 THOMASTON, CT

06787 UNITED STATES

RACHEL K BEACH, DELIVER_TO_EMP_ID_NO

0003 Delivery Schedule From date of lead time event to completion of performance 120 Calendar Days

Date of Award 1 JobQuantity

Address and POC Place of Performance DoDAAC: 961113 CountryCode: USA

CORPS OF ENGINEERS NEW ENGLAND DIST

NORTHFIELD BROOK LAKE, 1550 NORTHFIELD ROAD, RT. 254 THOMASTON, CT

06787 UNITED STATES

RACHEL K BEACH, DELIVER_TO_EMP_ID_NO

Contract Clauses

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.

2017-01

52.204-13 System for Award Management- Maintenance. (Deviation 2026- O0038)

2026-02

52.212-4 Terms and Conditions- Commercial Products and Commercial Services. (Deviation 2026-O0038)

2026-02

52.219-6 Notice of Total Small Business Set-Aside. (Deviation 2026- O0038)

2026-02

52.222-36 Equal Opportunity for Workers with Disabilities. (Deviation 2026- O0038)

2026-02

52.222-41 Service Contract Labor Standards. (Deviation 2026- O0038)

2026-02

52.222-50 Combating Trafficking in Persons. (Deviation 2026-O0038)

2026-02

52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. (Deviation 2026-O0038)

2026-02

52.222-62 Paid Sick Leave Under Executive Order 13706. (Deviation 2026- O0038)

2026-02

52.222-90 Addressing DEI Discrimination by Federal Contractors.

(Deviation 2026-O0040, Revision 1)

2026-04

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving.

2024-05

52.232-33 Payment by Electronic Funds Transfer-System for Award Management.

2018-10

52.232-40 Providing Accelerated Payments to Small Business Subcontractors.

2023-03

52.233-3 Protest after Award. (Deviation 2026-O0038)

2026-02

52.233-4 Applicable Law for Breach of Contract Claim. (Deviation 2026- O0038)

2026-02

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.203-7000 Requirements Relating to Compensation of Former DoD Officials.

2011-09

252.203-7002 Requirement to Inform Employees of Whistleblower Rights.

2022-12

252.204-7004 Antiterrorism Awareness Training for Contractors.

2023-01

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. (DEVIATION 2024-

O0013 REVISION 1)

2024-05 Deviation 2024- O0013

2024-05

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.

2023-01

252.204-7020 NIST SP 800-171 DoD Assessment Requirements.

2023-11

252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime.

2023-01

252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region.

2023-06

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.

2018-12

252.232-7010 Levies on Contract Payments. 2006-12

252.247-7023 Transportation of Supplies by Sea.

2024-10

FAR Clauses Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

52.219-28 Postaward Small Business Program Rerepresentation.

(Deviation 2026-O0038)

2026-02

Postaward Small Business Program Rerepresentation (Feb 2026) (Deviation 2026-O0038)

(a) . As used in this clause-Definitions

Long-term contract means a contract of more than five years in duration, including options.

However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern-

(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.

(2) , as used in this definition, means business concerns, one of whom directly or Affiliates indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.

(b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts-

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov/document /support--table-size-standards.

(d) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition-

(1) Was set aside for small business and has a value above the simplified acquisition threshold;

(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or

(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation(s) required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting officer in writing within the timeframes specified in paragraph (b) of this clause, that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

(1) The Contractor represents that it is, is not a small business concern under NAICS 562119 Code assigned to contract number.W912WJ26PXXXX

(2) [Complete only if the Contractor represented itself as a small business concern in paragraph .] The Contractor represents that it is, is not, a small disadvantaged (g)(1) of this clause business concern as defined in .13 CFR 124.1001

(3) . The Women-owned small business (WOSB) joint venture eligible under the WOSB Program Contractor represents that it is, is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique entity ____ identifier of each party to the joint venture: __.]

(4) . The Economically disadvantaged women-owned small business (EDWOSB) joint venture Contractor represents that it is, is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique entity ____ identifier of each party to the joint venture: __ .]

(5) Service-disabled veteran-owned small business (SDVOSB) joint venture eligible under the . The Contractor represents that it is, is not an SDVOSB joint venture eligible SDVOSB Program under the SDVOSB Program that complies with the requirements of 13 CFR 128.402. [ The ____ Contractor shall enter the name and unique entity identifier of each party to the joint venture:

(6) [ HUBZone joint venture eligible under the HUBZone Program. Complete only if the offeror is ] The offeror represents, as part of its offer, that It is, is not a HUBZone small business concern.

a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c).

[ The Contractor shall enter the name and unique entity identifier of each party to the joint ____ venture: .] Each HUBZone small business concern participating in the HUBZone joint venture must be certified as a HUBZone concern. [ Contractor to sign and date and insert ____ authorized signer's name and title.]

(End of clause)

52.222-42 Statement of Equivalent Rates for Federal Hires.

2014-05

Statement of Equivalent Rates for Federal Hires (May 2014)

In compliance with the Service Contract Labor Standards statute and the regulations of the Secretary of Labor ( 29 CFR Part 4), this clause identifies the classes of service employees expected to be employed under the contract and states the wages and fringe benefits payable to each if they were employed by the contracting agency subject to the provisions of 5 U.S.C.

5341 or 5332.

This Statement is for Information Only: It is not a Wage Determination

Employee Class Monetary Wage-Fringe Benefits (End of clause)

DFARS Clauses Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

252.232-7006 Wide Area WorkFlow Payment Instructions.

2023-01

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause-

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall-

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web- Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC ____ Issue By DoDAAC ____ Admin DoDAAC ____

Inspect By DoDAAC ____ Ship To Code ____ Ship From Code ____ Mark For Code ____ Service Approver (DoDAAC) ____ Service Acceptor (DoDAAC) ____ Accept at Other DoDAAC ____ LPO DoDAAC ____ DCAA Auditor DoDAAC ____ Other DoDAAC(s) ____ (*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

(Contracting Officer: Insert applicable information or "Not applicable.")

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

Addendum to Contract Clauses

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.204-9 Personal Identity Verification of Contractor Personnel.

2011-01

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations.

(Deviation 2026-O0038)

2026-02

52.222-3 Convict Labor. (Deviation 2026- O0038)

2026-02

52.223-5 Pollution Prevention and Right-to- Know Information.

2024-05

52.223-23 Sustainable Products. (Deviation 2026-O0038)

2026-02

52.233-1 Disputes. (Deviation 2026- O0038)

2026-02

52.240-91 Security Prohibitions and Exclusions. (Deviation 2026- O0038)

2026-02

52.244-6 Subcontracts for Commercial Products and Commercial Services. (Deviation 2026-O0038)

2026-04

DFARS Clauses Incorporated by Reference

Number Title Effective Alternate Variation

Date Deviation Effective Date

252.204-7003 Control of Government Personnel Work Product.

1992-04

252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel.

2023-01

252.243-7001 Pricing of Contract Modifications. 1991-12

252.244-7999 Subcontracts for Commercial Products or Commercial Services. (DEVIATION 2026- O0015)

2026-02 Deviation 2026- O0015

2026-01

FAR Clauses Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

52.252-2 Clauses Incorporated by Reference.

1998-02

Clauses Incorporated By Reference (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://www.acquisition.gov/

(End of clause)

52.252-6 Authorized Deviations in Clauses. 2020-11

Authorized Deviations in Clauses (Nov 2020)

The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR (a) Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

The use in this solicitation or contract of any (48 CFR ) clause with an (b) DFARS Chapter 2 authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

List of Contract Documents, Exhibits, or Attachments

ATTACHMENTS:

PLEASE SEE ATTACHMENTS INCLUDED SEPARATELY FOR ADDITIONAL INFORMATION.

SECURITY REQUIREMENTS:

General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (eg., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures -this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clauses of this contract, should FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

WAGE DETERMINATIONS:

The Wage Determination for this project can be found at:

https://sam.gov/wage-determination/2015-6131/4

Wage Determination No.: 2015-6131

Revision No.: 4

Revised Date: 25 June 2026

*** END OF NARRATIVE ***

W912WJ26QA130

https://sam.gov/wage-determination/2015-6131/4

Solicitation Provisions

FAR Provisions Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.204-7 System for Award Management- Registration. (Deviation 2026- O0038)

2026-02

52.212-1 Instructions to Offerors- Commercial Products and Commercial Services. (Deviation 2026-O0038)

2026-02

DFARS Provisions Incorporated by Reference

Date

Alternate Deviation

Variation…