REAL ESTATE DIVISION

CLARE LUBICZ-NAWROCKI

ARMY CORPS OF ENGINEERS NEW ENGLAND DISTRICT

IA ROAD

CONCORD MA 01742-2751

TEL: 978-318-8029 FAX:

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W912WJ22Q0154 30-Aug-2022 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

14-Sep-2022(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

9783188255ANN M ADLEY

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Barnes Asbestos Abatement & Carpet Replc

FFP

The Contractor shall provide all labor, materials, equipment and transportation necessary for asbestos removal , carpet and base cove replacment in rooms 302-A, 302-B and 302-D (approx. 927 sf) at the Barnes Building, 3rd Floor, Boston, MA FOB: Destination

PSC CD: Y1QA

NET AMT

INSTRUCTIONS TO OFFERORS

PLEASE DIRECT QUESTIONS TO ANN MURPHY ADLEY AT (978) 318-8255 OR

ANN.M.ADLEY@USACE.ARMY.MIL. THE SOLICITATION AND RESULTING CONTRACT SHALL BE

THE GOVERNING DOCUMENT IN ALL CASES.

** QUOTES CAN BE E-MAILED TO ANN MURPHY ADLEY AT ANN.M.ADLEY@USACE.ARMY.MIL.

In accordance with FAR Part 52.204-7(b)(1) Contractors must be registered in the System for Award Management (SAM) database (www.SAM.gov) to submit an offer. (Formerly the Central Contractor Registration (CCR) database and the On-Line Representations and Certifications (ORCA).) Any reference to CCR or ORCA in any clause or provision is referring to the www.sam.gov website. Please note that Google and Google Chrome are not supported browsers for SAM registration. Mozilla FireFox, Safari, and Internet Explorer are supported browsers.

NOTE: SAM.gov registration takes approximately 3 weeks (DUNS registration 1-2 business days; CAGE code validation up to 10 business days; IRS validation and overall submission 7-10 business days). It is the contractor’s responsibility to track SAM.gov registration and follow-up with required tasks.

In addition, if you are registering a new entity in SAM.gov, you must provide an original, signed notarized letter stating that you are the authorized Entity Administrator. The Entity Administrator must establish a LOGIN.GOV account using the e-mail address that will be associated with the SAM registration. See https://www.gsa.gov/about-us/organization/federal-acquisition-service/office-of-systems-management/integrated-award-environment-iae/sam-update for additional information.

Provide DUNS number: ___________________________ (telephone 866-705-5711 for DUNS) Provide CAGE code: ____________________________ Provide TAX ID: __________________________ Per FAR Part 52.212-3 Alt I, the Contractor is required to complete the On-line Representations and Certifications Application (www.SAM.gov) and paragraph (b) if applicable, OR to complete paragraphs (c) thru (m) of this clause and return with quote.

POTENTIAL QUOTERS ARE NOTIFIED THAT THE BASIS ON WHICH AWARD WILL BE MADE IS PRICE

ALONE.

ALL RESPONSIBLE SOURCES MAY SUBMIT A RESPONSE WHICH, IF TIMELY RECEIVED, MUST BE

CONSIDERED BY THE AGENCY.

INVOICES SHALL BE SENT TO TECHNICAL POINT OF CONTACT.

Section C - Descriptions and Specifications

STATEMENT OF WORK

CARPET REPLACEMENT

WITH ASBESTOS ABATEMENT

U.S. ARMY CORPS OF ENGINEERS

NTAG NEW ENGLAND

BARNES BUILDING

495 SUMMER STREET

BOSTON, MA

Statement of Work

1. General

1. Scope of work

Perform asbestos abatement in rooms 302-A, 302-B and 302-D, as needed. All rooms total approximately 927 square feet of space.

Provide all materials, equipment and labor for all operations necessary to remove and replace 927 sq ft (nine hundred twenty-seven square feet) of carpet and base cove at the office located at the Barnes Building, 495 Summer Street, 3rd Floor, Boston, MA

2. Location

NTAG New England, Barnes Building, 495 Summer Street, 3rd Floor, Boston MA.

3. Site Visit

Contact the Technical Point of Contact to arrange a site visit. The Technical Point of Contact for the project is Clare Lubicz-Nawrocki (978-318-8029 or clare.c.lubicz- nawrocki@usace.army.mil).

4. Schedule Upon award the contractor with coordinate with the Technical Point of Contact to schedule the start date of work. The entire work shall be completed and ready for use no later than 90 days after the Contractor receives the Award. The project area will be open to the contractor Monday through Friday 7:00 AM to 3:30 PM and all work must be done during those hours unless additional hours are approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.

5. Safety Requirements

The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include an Activity Hazard Analysis (AHA) as described in 2 below. All work shall be conducted in accordance with the APP, the U.S. Army Corps of Engineers Safety and Health requirements Manual (EM 385-1-1, most recent edition), and all applicable federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at Headquarters USACE website under publications using the following link:

https://www.publications.usace.army.mil/Portals/76/Publications/EngineerMa nuals/EM_3 85-1-1.pdf

The APP shall detail how safety and health will be managed during the project.

The APP shall address the requirements of applicable Federal, State and local safety and health laws, rules, and regulations. The Contractor shall comply with Federal Acquisition Regulation Clause No. 52.236-13 for Accident Prevention, which is added by reference.

Special attention shall focus on the requirements of EM 385-1-1, specifically Chapter 1, Sections 01.A.12 through 01.A.17, Figure 1-2 AHA, and Appendix A, (Minimum Basic Outline for Accident Prevention Plan). The APP shall be developed by a qualified person. The contractor shall be responsible for documenting the qualified person’s credentials.

Work shall not proceed until the APP has been reviewed by the Government Designated Authority (GDA) and deemed acceptable for use on the project.

The APP shall interface with the Contractor's overall safety and health program.

Any portions of the Contractor's overall safety and health program referenced in the APP shall be included in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the "controlling authority" for safety and health of the subcontractors.

Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

The contractor shall provide on-going evaluations of the APP throughout the life of the project. Changes to the accepted APP must be made with the knowledge and concurrence of the GDA. For projects that exceed 12 months in duration, the APP shall be reviewed annually with a signed copy submitted to the GDA.

1) APP Appendices:

A. Activity Hazard Analysis. An Activity Hazard Analysis (AHA) shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work. The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. Work shall not proceed on a phase of work until the AHA has been accepted by the GDA. A preparatory meeting shall be conducted by the contractor to discuss the AHA contents with all engaged in the activity. The preparatory meeting shall be conducted by the prime contractor and shall include all subcontractors and Government on-site representatives. The AHA shall be continuously reviewed and revised to address changing site conditions or operations as appropriate.

B. Asbestos Hazard Abatement Plan. A site-specific Asbestos Hazard Abatement Plan shall include the requirements as defined in the OSHA classification system for asbestos construction work in order to protect employees from asbestos hazards while performing work that will disturb ACM.

The plan must be developed by a Certified Industrial Hygienist who is also a certified Project Designer in the state applicable to the work being performed. This individual and the asbestos abatement contractor must not have an employee/employer relationship or financial relationship which could constitute a conflict of interest. Documentation of qualifications shall include knowledge of building construction as well as the design and development of abatement projects. The Asbestos Hazard Abatement Plan shall include, but is not limited to, the procedures set forth in EM 385-1-1, Chapter 6, Section 06.C.03 and must be submitted for acceptance by the GDA prior to starting any asbestos work.

The asbestos abatement work must be performed by a certified asbestos contractor in the state of Massachusetts. The contractor shall maintain a daily log of the certified Asbestos Workers and Supervisors who conducted asbestos abatement on the project. The Contractor shall designate a competent person to perform personal exposure monitoring of workers as required by OSHA Title 29 CFR, Part 1926.1101.

The Asbestos Hazard Abatement Plan must include a detailed Asbestos Air Monitoring Plan and Respiratory Protection Plan that meet the requirements set forth in 29 CFR

1926.1101. Background, perimeter/area, and final clearance sampling shall be performed only by a certified Asbestos Project Monitor who is currently listed on the Asbestos Analysts Registry (AAR) that is maintained by the American Industrial Hygiene Association (AIHA) or Certified Industrial Hygienist who is not an employee or Responsible Person of the Asbestos Contractor or entity which conducted the work. The asbestos Contractor shall not subcontract with an Asbestos Project Monitor to perform the visual inspection or the clearance air monitoring. The Air Monitoring Plan shall detail the procedures for collecting and analyzing the following air samples relative to the project:

Background: Collected prior to abatement inside of, or adjacent to, what will become the regulated area. Background samples are collected and analyzed to assess ambient airborne fiber concentrations prior to the start of abatement activities.

Perimeter (area): Collected outside of a regulated area during abatement activities. Often collected at an entrance to a decontamination unit and/or outside the barrier walls of a regulated area.

Blank: A filter through which no air is drawn. In accordance with the NIOSH 7400 method, the number of blanks submitted to the laboratory should be ten percent of the total sample submission set, with a minimum of two blank samples per set.

Clearance: Collected following the completion of an abatement activity to evaluate the adequacy of the detailed cleaning activities and to determine whether the project’s air clearance criterion has been met. Should be preceded by a thorough visual inspection of the work area.

Exposure Monitoring: Also known as “personal” air monitoring. Personal sampling is required by 29 CFR 1926.1101 and is the contractor's responsibility.

Employee exposure assessment procedures shall address monitoring and documenting employee exposures. Personal air exposure monitoring, at a minimum, shall include monitoring for twenty-five percent (25%) of the on-site work personnel, or a minimum of two (2) workers per work shift. Breathing zone air samples must be representative of the 8-hour TWA and 30-minute short term exposures of each employee. Plan shall state the name of the contractor’s asbestos competent person collecting all personal air sampling, provide documentation of his/her qualifications, the number of samples to be collected, analytical method to be used, and sample analysis turnaround time. Documentation for the certified/accredited AIHA laboratory that will perform sample analyses must be provided.

Results of breathing zone samples must be posted at the job site and made available to the GDA within 5 working days of the date of collection.

C. Emergency Response: Emergency procedures shall be documented in the Abbreviated

Accident Prevention Plan and will include a map with directions to the nearest hospital, emergency contact numbers, and onsite First Aid/CPR responders.

D. Required Personnel: When emergency medical services are not accessible within five (5) minutes of the work location and there are two (2) or more workers onsite, at least two (2) employees shall be trained in First Aid and CPR. Minimum qualifications are listed in EM 385-1-1, Section 03.A.02.c.

2) Competent Persons:

A. Competent Persons are defined as one who can identify existing and predictable hazards in the working environment or working conditions that are dangerous to personnel and who has authorization to take prompt corrective measures to eliminate them. The contractor shall have a competent person onsite for each of the following applicable aspects that are involved in the project scope of work.

B. Competent Person, Asbestos: An individual who meets the requirements for competent person as specified in 29 CFR 1926.1101 including a person capable of identifying existing asbestos hazards in the workplace and selecting the appropriate control strategy for asbestos exposure, who has the authority to take prompt corrective measures to eliminate them, and is specifically trained in a training course which meet the criteria of EPA's Model Accreditation Plan (40 CFR 763) for Asbestos Supervisor.

The Competent Person must be experienced in the administration and supervision of asbestos abatement projects including exposure assessment and monitoring, work practices, abatement methods, protective measures for personnel, setting up and inspecting asbestos abatement work areas, evaluating the integrity of containment barriers, placement and operation of local exhaust systems, ACM generated waste containment and disposal procedures, decontamination units installation and maintenance requirements, site safety and health requirements, and notification of other employees onsite.

The Designated Competent Person must be on-site at all times when asbestos abatement activities are underway. Submit training certification and current Asbestos Supervisor license in the State in which work is being conducted.

Provide documentation that the Designated Competent Person has a minimum of 3 years of RELATED on-the-job asbestos abatement experience relevant to OSHA designated competent person requirements.

C. Site Safety and Health Officer (SSHO): The Contractor shall designate one individual as the SSHO who shall have the qualifications detailed below.

Documentation of SSHO qualifications shall be submitted for approval prior to initiating work. The SSHO may have other duties in addition to site safety and health, but may not be the Contractor’s Site Superintendent.

I. A minimum of five years of experience in implementing safety and health programs at similar projects

II. Working knowledge of construction safety procedures as well as Federal and state occupational safety and health regulations.

III. 30-hour OSHA Construction Safety certification or as an equivalent, 30 hours of formal construction safety and health training covering the subjects of the OSHA 30 -hour course.

3) Safety Reporting:

A. Safety Briefing and Equipment Inspection Documentation

The Contractor shall conduct a safety meeting at the project site on the first day of work, whenever a new activity or phase of work begins, or at least weekly during the progress of work. All safety meetings shall be documented. A copy of a suggested weekly safety meeting form will be provided by the Contracting Officer’s Representative. Records of the safety briefings shall be submitted to the GDA weekly.

The Contractor shall submit to the GDA a current written safety inspection for all heavy equipment proposed for use on this contract. The Contractor, upon award of the contract, will be required to make available for suitability and safety compliance inspection all equipment proposed for use to perform the work of this contract. Equipment shall be made available for inspection by the GDA five working days prior to the start of work. Any additional equipment added during the prosecution of the work shall also be made available for inspection prior to its use on the project. Equipment not accepted by the GDA should be repaired or replaced by the Contractor.

B. Incident Reporting

All work-related incidents, to include injuries, illnesses, near misses, and property related accidents (excluding on the road- vehicle accidents), shall be immediately reported to the GDA and documented appropriately. All incidents shall be investigated to identify all root causes and recommended hazard control measures.

ENG Form 3394 shall be completed for all OSHA recordable injuries or illnesses and property damage accidents, for which property damage exceeds $5,000.00. A Lessons Learned Document shall also be submitted separately within five days of the incident.

C. Exposure Hour Reporting

The Contractor shall complete the attached “USACE Contractor Monthly Summary Record of Injuries/Illness and Work Hour Exposure” (for prime and its subcontractors) and forward the completed form to the GDA no later than close of business on the 5th calendar day of the following month. The method of transmission by the prime contractor to the GDA shall be electronically.

6. Preconstruction Conference

Prior to the start of any work, the Technical Point of Contact will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Preconstruction conference the contractor shall provide the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Preconstruction Conference:

Authority of the Technical Point of Contact and Quality Assurance Inspectors.

Contractor’s Safety Program (including sub-contractors).

Abbreviated Accident Prevention Plan (Submitted & accepted prior to start of work on site) Activity Hazard Analysis (Submitted and accepted prior to the start of work) Weekly Safety Meetings (Documented on NED Form 251) Accident Reporting (ENG Form 3394) Safety Data Sheet (SDS) requirements Correspondence, Communication and Administrative Procedures.

Invoice and payment.

7. Permits

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

8. Security

The contractor will comply with all established security policies at the Barnes Building. Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor’s ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The Contractor shall be given at least 24-hour notice of any such closure.

9. Contractor Conduct

Alcohol and firearms are prohibited on project grounds. Contractor and employees must comply with CFR 36 Rules and Regulations.

10. Payment

Payment shall be made on a per job basis. After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. For jobs greater than 30 days the contractor may request multipleinstallation payment.

All invoices may be mailed to:

U.S. Army Corps of Engineers New

England District, Real Estate 696 Virginia Road

Concord, MA 01742 Attn:

Clare Lubicz-Nawrocki

Or E-mailed to clare.c.lubicz-nawrocki@usace.army.mil

2. Technical Requirements: 1 General:

1. Existing Conditions:

The Navy Talent Acquisition Group (NTAG) office at the Barnes Building currently has 927 sq ft of carpet spanning the conference room and sitting area. (see informational photos 3 & 4). A flooring inspection was done in 2018 which called out the presence of asbestos. Please reference the flooring inspection report for details.

Contractor will move all office furniture, filing cabinets and obstructions from carpeted surfaces.

2. Requests for Information:

Requests concerning the work of this project should be directed to the Technical Point of Contact, Clare Lubicz-Nawrocki, at the U.S. Army Corps of Engineers at (978) 318-8029 or at clare.c.lubicz-nawrocki@usace.army.mil.

3. Submittals:

Although the Government technically reviews submissions required by this scope of work, it is emphasized that the Contractor’s work must be prosecuted using proper internal controls and review procedures. The documents identified below must be prepared in accordance with the applicable standards, submitted for review and accepted by the government prior to the commencement of any field activities.

1.3.1. Copy of contractor’s Accident Prevention Plan (APP) prior to start of work

1.3.2. Copy of contractor’s Accident Hazard Analysis (AHA) prior to start of work

1.3.3. Manufacturer Warranty for applicable products prior to final payment

1.3.4. Carpet Tile style/colors samples

1.3.5. First Aid and CPR certifications

1.3.6. Floor plan – room locations for carpet installation and removal

1.3.7. USACE ENG form 3394 – Accident Report

1.3.8. Contractor exposure hourly report

1.3.9. Flooring inspection report

1.3.10. Navy Space Flooring Sample Locations

1.3.11. Informational Photos

4. Clean Up:

The Contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials.

Upon completing work in an area the contractor shall remove any tools, equipment, and materials that are not the property of the government. Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.

Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the contractor at the site, and the site will be inspected/ cleaned on a daily basis. Water, air and land resources shall not be adversely impacted during the course of the work.

Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.

5. Government Resources:

The contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, telephone services or other resources. The contractor may use the restroom at the office but must proceed directly to and from the restroom.

6. Omissions:

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

7. Quality Assurance:

The contractor is responsible for the quality control of the contract work. The government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

8. Other Contracts:

The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.

9. Clean Up and Waste Disposal – The Contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area free from accumulation of waste materials.

Upon completing work in an area the contractor shall remove any tools, equipment, and materials that are not the property of the government Any and all disturbed areas resulting from contractor activities shall be restored by the contractor to the satisfaction of the Technical Point of Contact.

10. Environmental Protection – Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the contractor at the site, and the site will be inspected/ cleaned on a daily basis. No burning is permissible. Water, air and land resources shall not be adversely impacted during the course of the work. Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.

11. Receiving and Storing Materials:

The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive material or supplies for the contractor and will not be responsible for damage to contractor equipment or material.

Part 2 Products:

1. Materials & Equipment - General

a. The intent of this material section is not to specify every product to be used in the execution of the work. Rather, to define the expected standards to be followed and the quality of the product to be used.

b. All construction material shall be new, un-used and be first quality material or products. In addition, construction material shall be produced domestically or manufactured domestically in accordance with the Buy American Act.

c. All construction material shall be in conformance to the applicable sections of the International Building Code (2012).

d. All construction material shall be in conformance to the applicable sections of the National Fire Protection Association (NFPA) Fire and Life Safety Codes [in place of the International Fire Code (IFC)].

e. As a minimum, meet requirements of UL, where UL standards are established for those items, and requirements of NFPA 70 for all materials, equipment, and devices.

2. Materials & Equipment - Sustainability [Army Green Procurement Guide]

a. As a minimum, where applicable meet the requirements EPA-Designated Recovered Material for Construction Products. Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials, and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive- procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels.

Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.

b. As a minimum, where applicable meet the requirements USDA-Designated Biopreferred Program Products for Construction Products.

https://www.biopreferred.gov/BioPreferred/faces/catalog/Catalog.xhtml

3. Carpet

a. Carpet shall be 24” x 24”, Pattern Loop, nylon carpet tiles

1. Synthetic backing

2. Installation in Monolithic pattern

3. Soil Protection

4. 0.117 inch finished pile thickness

5. Lifetime commercial warranty against edge ravel, zippering, delamination, an moisture degradation

6. Color/pattern is to be approved by the technical point of contact

7. New carpet similar in appearance and qualities to existing carpet which is Shaw US Navy

Recruiting Standard #800G3 Color Water Garden 69400

W912WJ22Q0154

Part 3 Execution:

1. General

a. Perform asbestos abatement to approximately 927 square feet (927 sq ft) within the NTAG Office in rooms 302-A, 302-B and 302-D. Once the asbestos has been identified, containment will be needed to avoid spreading throughout the office. Necessary precautions to cover other surfaces like ceilings and walls should be taken. Remove all asbestos containing materials and dispose of properly to avoid breakage and the release of asbestos fibers. All areas containing asbestos should be thoroughly decontaminated.

b. Nine hundred twenty-seven square feet (927 sq ft) of pre-existing carpet and adhesive shall be removed from the sub floor surface and replaced with new low Volatile Organic Compounds (VOC’s) release adhesive and 24” x 24” carpet tiles and black rubber base cove, 4” at the Barnes Bldg., NTAG Office.

2. Demolition

a. The contractor shall remove and legally dispose of the existing materials and equipment identified below in accordance with all federal, state and local laws and regulations. Demolition materials shall be reused/recycled if possible.

1. Existing tiles, carpet and glue remnants will be removed and disposed of in a way as to not damage the surrounding baseboard, walls or paint.

2. Any debris created by the removal of existing tiles and carpet will be cleaned up and removed by the contractor.

3. Any damage to surrounding areas, including but not limited to walls, baseboard, paint, etc. shall be returned to previous condition at no additional expense to the Government.

3. Installation

a. The contractor shall install all materials and equipment in accordance with the applicable codes and a manner that is consistent with the industry standards.

b. Installation of all products shall meet specified requirements and be in accordance with the manufacturer's installation instructions.

1. Clean, prepare and level subfloor as needed to properly install new 24” x 24” carpet squares.

2. New tiles shall be installed using a low Volatile Organic Compounds (VOC’s) release adhesive.

3. New tiles shall be installed in a monolithic pattern with all arrows pointing in the left direction upon walking into the entrance of the space.

4. Install new black rubber base cove, 4” high.

5. Contractor shall provide at minimum one box (1) additional carpet squares for future replacements

c. Contractor shall not install damaged materials or equipment

ATTACHMENTS

REFER TO PHOTOS, REPORTS, AND FLOOR PLANS WITHIN THE SOLICITATION FOR ADDITIONAL

INFORMATION.

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 90 dys. ADC 1 REAL ESTATE DIVISION

CLARE LUBICZ-NAWROCKI

ARMY CORPS OF ENGINEERS NEW

ENGLAND DISTRICT

IA ROAD

CONCORD MA 01742-2751

978-318-8029 FOB: Destination

W912WJ

Section H - Special Contract Requirements

SECURITY REQUIREMENTS

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the Technical Point of Contact NLT 5 calendar days after the completion of the training.

All US based contractor employees and associated sub-contractor employees traveling overseas will receive the government provided AOR specific AT awareness training. The documentation of training completion must be provided to the Technical Point of Contact prior to departure.

All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks or background investigation and to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

WAGE DETERMINATION

"General Decision Number: MA20220001 08/12/2022

Superseded General Decision Number: MA20210001

State: Massachusetts

Construction Type: Building

Counties: Barnstable, Bristol, Dukes, Essex, Middlesex, Nantucket, Norfolk and Suffolk Counties in Massachusetts.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes and apartments up to and including 4 stories)

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $15.00 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2022. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $11.25 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2022. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at https://www.dol.gov/agencies/whd/government-contracts.

Modification Number Publication Date

0 01/07/2022 1 02/11/2022 2 02/18/2022 3 02/25/2022 4 03/04/2022 5 04/22/2022 6 05/06/2022 7 06/03/2022 8 07/08/2022 9 08/05/2022 10 08/12/2022

ASBE0006-001 09/01/2021

Rates Fringes

Insulator/asbestos worker Includes the application of all insulating materials, protective coverings, coatings, and finishes to all types of mechanical systems

(ZONE A)...................$ 50.00 32.89

(ZONE B)...................$ 50.00 32.89

ZONES:

ZONE A

BARNSTABLE COUNTY (Brewster, Chatham, Dennis, Eastham, Harwich, Orleans, Provincetown, Truro, Wellfleet, Yarmouth) BRISTOL COUNTY (Easton), MIDDLESEX COUNTY, and NORFOLK COUNTY (Avon, Braintree, Brookline, Canton, Cohasset, Dedham, Dover, Foxborough, Holbrook, Medfield, Medway, Millis, Milton, Needham, Norfolk, Norwood, Quincy, Randolph, Sharon, Stoughton, Walpole, Wellesley, Westwood, Weymouth)

ZONE B

BARNSTABLE COUNTY (Barnstable, Bourne, Falmouth, Mashpee, Sandwich), BRISTOL COUNTY (All cities except Easton),and NORFOLK COUNTY (Bellingham, Franklin, Plainville)

ASBE0006-002 09/01/2021

BARNSTABLE (Brewster, Chatham, Dennis, Eastham, Harwich, Orleans, Provincetown, Truro, Wellfleet and Yarmouth); BRISTOL (Easton); ESSEX; MIDDLESEX; NORFOLK (Avon, Braintree, Brookline, Canton, Cohasset, Dedham, Dover, Foxboro, Holbrook, Hull, Medfield, Medway, Millis, Milton, Needham, Norfolk, Norwood, Quincy, Randolph, Sharon Stoughton, Walpole, Wellesley, Westwood, and Weymouth) AND SUFFOLK COUNTIES

Rates Fringes

HAZARDOUS MATERIAL HANDLER

(Includes preparation, wetting, stripping, removal, scrapping, vacuuming, bagging and disposing of all insulation materials from mechanical systems whether they contain asbestos or not)....$ 40.00 33.04

ASBE0006-010 09/01/2021

BARNSTABLE (Barnstable, Bourne, Falmouth, Mashpee and Sandwich); BRISTOL (Acushnet, Attleboro city, Berkeley, Dartmouth, Dighton, Fairhaven, Fall river City, Freetown, Marion, Mansfield, New Bedford City, North Attleboro, Norton, Raynham, Rehoboth, Seekonk, Somerset, Swansea, Taunton City and Westport); DUKES; NANTUCKET; NORFOLK (Bellingham, Franklin, Plainville, and Wrentham); PLYMOUTH (Lakeville, Mattapoisett, Middleboro, Rochester and Wareham)

Insulator/asbestos worker (Includes the application of all insulating materials, protective coverings, coatings and finishes to all types of mechanical systems.)....$ 50.00 32.89

BOIL0029-001 01/01/2021

BOILERMAKER......................$ 45.87 29.02

BRMA0001-008 02/01/2021

FOXBORO CHAPTER

BRISTOL (Attleboro, Berkley, Dighton, Mansfield, North Attleboro, Norton, Raynham, Rehoboth, Seekonk, Taunton) AND NORFOLK (Bellingham, Canton, Dedham, Foxboro, Franklin, Norfolk, Norwood, Plainville, Sharon, Walpole, Westrwood, Wrentham) COUNTIES

Bricklayer, Cement Mason, Plasterer........................$ 53.61 35.94

BRMA0001-009 02/01/2021

LOWELL CHAPTER

MIDDLESEX (Acton, Asby, Ayer, Bedford, Billerica, Boxboro, Carlisle, Chemsford, Dracut, Dunstble, Ft. Denvens, Groton, Littleton, Lowell, North Acton, Pepperell, Shirley, South Acton, Tewksbury, Townsend, Tyngsboro, West Acton, Westford, Wilmington)

Bricklayer and plasterer.........$ 53.61 35.94

BRMA0001-010 08/01/2020

LOWELL CHAPTER

MIDDLESEX (Ashland, Framingham, Holliston, Hopkinton, Hudson, Maynard, Natick, Sherbvorn, Stow); and NORFOLK (Medfield, Medway,Millis)

BRICKLAYER.......................$ 53.16 34.95

BRMA0003-001 02/01/2021

Marble & Tile Finisher...........$ 42.57 32.00 Marble, Tile & Terrazzo Workers..........................$ 54.69 33.80

TERRAZZO FINISHER................$ 55.77 34..47

BRMA0003-003 02/01/2021

BOSTON CHAPTER

MIDDLESEX (Arlington, Cambridge, Everett, Malden, Medford, Melrose, Somerville); NORFOLK (Brookline, Milton); and SUFFOLK

BRICKLAYER.......................$ 55.75 35.85

BRMA0003-006 08/01/2021

LYNN CHAPTER

ESSEX (Amesbury, Andover, Beverly, Boxford, Danvers, Essex, Georgetown, Gloucester, Groveland, Hamilton, Haverhill, Ipsewich, Lawrence, Lynn, Lynnfield, Manchester, Marblehead, Merrimac, Methuen, Middleton, Nahant, Newbury, Newburyport, North Andover, Peabody, Rockport, Rowley, Salisbury, Salem, Saugus, Swampscott, Topsfield Wakefield, Wenham, West Newbury);

and MIDDLESEX (Reading, North Reading, Wakefield)

Bricklayer, cement mason and plasterer........................$ 57.17 35.98

BRMA0003-007 08/01/2021

WALTHAM CHAPTER

MIDDLESEX (Belmont, Burlington, Concord, Lexington, Lincoln, Stoneham, Sudbury, Waltham, Watertown, Wayland, Weston, Winchester, Woburn)

Bricklayer and plasterer.........$ 57.17 35.98

BRMA0003-008 08/01/2021

NEWTON CHAPTER

MIDDLESEX (Newton) and NORFOLK (Dover, Needham, Wellesley) plasterer........................$ 57.17 35.98

BRMA0003-009 08/01/2021

NEW BEDFORD

BARNSTABLE; BRISTOL (Acushnet, Darmouth, Farhaven, Fall River, Freetown, New Bedford, Somerset, Swansea, Westport); DUKES; and

NANTUCKET COUNTIES

plasterer........................$ 57.17 35.98

BRMA0003-010 08/01/2021

QUINCY CHAPTER

NORFOLK COUNTY (Avon, Braintree, Cohasset, Holbrook, Quincy, Randolph, Soughton, Weymouth) plasterer........................$ 57.17 35.98

CARP0056-011 08/01/2021

SUFFOLK (All of County); and those areas of BARNSTABLE, BRISTOL, ESSEX, MIDDLESEX & NORFOLK COUNTIES situated inside Boston Beltway (I-495) and North of Cape Cod Canal. ALL of

DUKES AND NANTUCKET COUNTIES

PILEDRIVERMAN....................$ 50.74 33.66

CARP0056-012 08/01/2020

The areas of BARNSTABLE, BRISTOL, and NORFOLK COUNTIES situated OUTSIDE Boston Beltway (I-495) and South of Cape Cod Canal

PILEDRIVERMAN....................$ 49.07 35.57

CARP0056-013 08/01/2021

Those areas of ESSEX and MIDDLESEX COUNTIES situated OUTSIDE Boston Beltway (I-495)

PILEDRIVERMAN....................$ 44.61 33.45

CARP0327-001 03/01/2022

MIDDLESEX (Belmont, Cambridge, Everett, Malden, Medford, Somerville); NORFOLK (Brookline, Dedham, Milton); and SUFFOLK

CARPENTER........................$ 53.87 29.62

CARP0339-001 03/01/2022

BRISTOL (Attleborough, North Attleborough); ESSEX; MIDDLESEX (Except Belmont, Cambridge, Everett, Malden, Medford, Somerville); AND NORFOLK (Bellingham, Canton, Foxboro, Franklin, Medfield, Medway, Millis, Needham, Norfolk, Norwood, Plainville, Sharon, Walpole, Wellesley, Westwood, Wrentham)

CARPENTER........................$ 44.53 29.52

CARP0346-003 09/01/2021

NORFOLK COUNTY (Braintree, Cohassett, Scituate, Weymouth, Quincy)

CARPENTER........................$ 44.18 29.27

CARP0624-005 09/01/2017

DUKES; NANTUCKET

Rates Fringes

CARPENTER........................$ 46.43 28.35

CARP0624-007 09/01/2017

BARNSTABLE; BRISTOL (Except Attleboro & North Attleboro); AND NORFOLK (Avon, Holbrook, Randolph, Stoughton) COUNTIES

CARPENTER........................$ 39.28 27.90

CARP1121-001 01/03/2022

SUFFOLK COUNTY

Rates Fringes

MILLWRIGHT.......................$ 45.20 28.05

CARP1121-003 01/03/2022

BARNSTABLE, BRISTOL, DUKES, ESSEX, MIDDLESEX, NANTUCKET and

NORFOLK COUNTIES

MILLWRIGHT.......................$ 40.35 28.05

CARP2168-001 03/01/2022

MIDDLESEX (Belmont, Cambridge, Everett, Malden, Medford, Somerville); NORFOLK (Brookline, Dedham, Milton); and SUFFOLK

FLOOR LAYER: Carpet.............$ 49.93 29.70

CARP2168-004 03/01/2022

BRISTOL; ESSEX; MIDDLESEX (Except Belmont, Cambridge, Everett, Malden, Medford, Somerville); Remainder of Norfolk County

FLOOR LAYER: Carpet.............$ 49.93 29.70

CARP2168-005 03/01/2022

BARNSTABALE; DUKES; AND NANTUCKET

Rates Fringes

FLOOR LAYER: Carpet.............$ 47.62 29.70

ELEC0096-001 09/06/2021

MIDDLESEX (Ashby, Ashland, Ayer, Ft. Devens, Groton, Hopkinton, Hudson, Marlboro, Pepperell, Shirley, Stow, Townsend)

ELECTRICIAN......................$ 45.01 11%+25.01

Teledata System Installer........$ 32.85 28.12

ELEC0099-001 06/01/2021

BRISTOL (Attleboro, North Attleboro, Seekonk)

Rates Fringes

ELECTRICIAN......................$ 43.61 54.71%

Teledata System Installer........$ 31.21 13.1%+14.93

ELEC0103-001 03/01/2022

ESSEX; MIDDLESEX (Excluding Ashby, Ashland, Ayer, Ft. Devens, Groton, Hopkinton, Hudson, Marlboro, Pepperell, Shirley, Stow, Townsend); NORFOLK (Excluding Avon, Holbrook, Plainville, Randolph, Stoughton) SUFFOLK

Teledata System Installer........$ 44.71 32.41

ELEC0103-002 03/01/2022

ESSEX (Amesbury, Andover, Boxford, Georgetown, Groveland, Haverhill, Lawrence, Merrimac, Methuen, Newbury, Newburyport, North Andover, Rowley, Salisbury, West Newbury); MIDDLESEX (Bedford, Billerica, Boxboro, Burlington, Carlisle, Chelmsford, Dracut, Dunstable littleton, Lowell, North Reading, Tewksbury, Tyngsboro, Westford, Wilmington)

ELECTRICIAN......................$ 57.32 34.68

ELEC0103-004 03/01/2022

ESSEX (Beverly, Danvers, Essex, Gloucester, Hamilton, Ipswich, Manchester, Marblehead, Middleton, Peabody, Rockport, Salem, Topsfield, Wenham)

ELEC0103-005 03/01/2022

ESSEX (Lynn, Lynnfield, Nahant, Saugus, Swampscott); MIDDLESEX (Acton, Arlington, Belmont, Cambridge, Concord, Everett, Framingham, Holliston, Lexington, Lincoln, Malden, Maynard, Medford, Melrose, Natick, Newton, Reading, Sherborn, Somerville, Stoneham, Sudbury, Wakefield, Waltham, Watertown, Wayland, Weston, Winchester, Woburn); NORFOLK (Bellingham, Braintree, Brookline, Canton, Cohasset, Dedham, Dover, Foxboro, Frankloin, Medfield, Medway, Millis, Milton, Needham, Norfolk, Norwood, Quincy, Sharon, Walpole, Wellesley, Westwood, Weymouth, Wrentham); PLYMOUTH (Hingham and Hull);SUFFOLK

ELEC0104-001 09/01/2021

Rates Fringes

Line Construction:

Cableman....................$ 51.09 27.91+A Equipment Operator..........$ 43.43 24.62+A Groundman...................$ 28.10 11.80+A Lineman.....................$ 51.09 27.91+A

A. PAID HOLIDAYS: New Year's Day; Memorial Day;

Independence Day; Labor Day; Thanksgiving Day; Christmas Day and Columbus Day, provided the employee has been employed 5 working days prior to any one of the listed holidays.

ELEC0223-005 03/01/2022

BARNSTABLE; BRISTOL (Except Attleboro, North Attleboro, Seekonk); DUKES; NANTUCKET AND NORFOLK (Avon, Halbrook, Plainville, Randolph, Stoughton)

ELECTRICIAN......................$ 44.82 31.18%+14.00

ELEC0223-006 03/01/2022

BARNSTABLE; BRISTOL (Except Attleboro, North Attleboro, Seekonk); DUKES; NANTUCKET AND NORFOLK (Avon, Halbrook, Plainville, Randolph, Stoughton)

Teledata System Installer........$ 38.1625.34%+2.75%+3%+13.75

ELEV0004-001 01/01/2022

Rates Fringes

ELEVATOR MECHANIC................$ 65.62 36.885+a+b

FOOTNOTE FOR ELEVATOR MECHANICS:

a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.

b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.

ENGI0004-001 12/01/2021

Rates Fringes

Power equipment operators:

Group 1.....................$ 51.38 30.10 Group 2.....................$ 50.83 30.10 Group 3.....................$ 33.69 30.10 Group 4.....................$ 41.76 30.10 Group 5.....................$ 23.48 30.10 Group 6.....................$ 28.44 30.10

FOOTNOTE FOR POWER EQUIPMENT OPERATORS:

A. PAID HOLIDAYS: New Year's Day, Washington's Birthday, Labor Day, Memorial Day, Independence Day, Patriot's Day, Columbus Day, Veteran's Day, Thanksgiving Day, Christmas Day

HOURLY PREMIUM FOR BOOM LENGTHS (Including Jib):

Over 150 ft. +2.18 Over 185 ft. +3.84 Over 210 ft. +5.39 Over 250 ft. +8.16 Over 295 ft. +11.29 Over 350 ft. +13.14

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

Group 1: Crane; shovel; truck crane; cherry picker;

dragline; trench hoe; backhoe; three drum machine; derrick;

pile driver; elevator tower; hoist; gradall; shovel dozer;

front end loader; fork lift; suger; boring machine; rotaryu drill; post hole hammer; post hole digger; pumpcrete machine; asphalt plant (on site); concrete batching and/or mixing plant (on site); crusher plant (on site); paving concrete mixer; timber jack Group 2: Sonic or vibratory hammer; grader; scraper; tandem scraper; concrete pump; bulldozer; tractor; york rake;

mulching machine; portable steam boiler; portable steam generator; roller; spreader; tamper (self propelled or tractor drawn); asphalt paver; mechanic - maintenance;

paving screed machine; stationary steam boiler; paving concrete finishing machine; cal truck; ballast regulator;

switch tamper; rail anchor machine; tire truck Group 3: Pumps (1-3 grouped); compressor; welding machine (1-3 grouped); generator; concrete vibrator; heater (power driven 1- 5); well point system (operating);

syphon-pulsometer; concrete mixer; valves controlling permanent plant air or steam; conveyor; Jackson type tamper; single diaphragm pump; lighting plant Group 4: Assistant engineer (fireman) Group 5: Oiler (other than truck cranes and gradalls) Group 6: Oiler (on truck cranes and gradalls) stant engineer (on truck crane and gradall)

IRON0007-006 03/16/2022