Solicitation W90VN920R0043.pdf

PDF 441 KB Posted

Attached to
Replace Hot Water Boiler at Camp Walker, Daegu
Solicitation number
W90VN920R0043
Issued by

View the file

Other files

File Type Posted
W90VN920R0043 Amend 01.pdf PDF
Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0011518634

MR. HONG, YUN PYO 315-763-5685

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

15-Jul-2020

(RFP)

(IFB)

X

CALL:

Replace Hot Water Boiler

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________150 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________05 Aug 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

RCO DAEGU, UNIT #15682

APO AP 96218-5682

UNITED STATES

W90VN9

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

10:00 AM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

J1-00601-0J

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W90VN920R0043 19

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued)

(Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W90VN920R0043

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

Replace a Boiler(Gas type), B363, C/W

FFP

The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and specifications.

FOB: Destination

PURCHASE REQUEST NUMBER: 0011518634

PSC CD: 4510

NET AMT

Section C - Descriptions and Specifications

SOW

PROJECT NO TITLE LOCATION

J1-00601-0J Replace a Defective Hot Water Heating Boiler with Camp Walker

Gas Type at Bldg. No. S-363 (Barrack)

DESCRIPTION: The work to be performed shall be in accordance with all drawings and specifications provided under this contract.

a. Work by Contractor:

(1) The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and specifications.

(2) The contractor shall replace a defective hot water heating boiler with gas type at Bldg. No. S-363

(Barrack), Camp Walker in accordance with the specifications and drawings.

b. Work by In-House Labor: Not applicable to this project.

c. Work by Troop Labor: Not applicable to this project.

(3) Performance Period: Shall be 150 calendar days, including 120 days for procurement of US origin materials after Notice to Proceed (NTP) is issued.

PRINCIPAL FEATURES: This project shall include the following:

General Services:

The contractor shall submit completed material lists and shop drawings to DPW, Engineering Division, Design and

Technical Review Branch.

Schedule #I, Repair (K): All work shall be in accordance with the attached drawings and specifications.

A. Mechanical Work

1. Replace existing deteriorated hot water heating boiler system with new one including piping, insulation, valves, concrete pad, smoke stacks with all necessary accessories and parts. (Bldg. No. S-363)

2. Provide new gas line for new hot water heating boiler with all necessary accessories and parts as indicated on drawing. (Bldg. No. S-363)

TP I-1

3. Install grounding for boiler support and gas pipe line.

4. Install junction box with electrical line protector for LWCO (low water cut-off) of new hot water heating boiler.

TP I-2

TECHNICAL PROVISIONS - II

TECHNICAL DETAIL SPECIFICATIONS

GENERAL: The specifications are from the "Standard Technical Specifications for O&MA Projects, Korea", dated

30 October 2015, issued by the Department of the Army, Installation Management Command. The most current specifications are available (for referral purposes only) on the USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK. The electronic version of the specifications are

Acrobat® PDF format and can be read with the Acrobat Reader® software.

TP II – 1

TECHNICAL PROVISIONS - III

SPECIAL CONDITIONS

1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price

Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which is incorporated in to the contract.

2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours (Monday through

Saturday) except for Korean Legal Holidays. Any proposed change in working hours should be approved by the

Contracting Officer (KO) and Contracting Officer's Representative (COR).

3. NOTIFICATION OF INSPECTION SECTION: The contractor shall also give the project inspector seven (7) working days notice prior to each concrete placement, field test, weld application, protective coating application, or any other work deemed by the Government to require inspection.

4. COORDINATION: The contractor shall coordinate his work with all others (subcontractor and government agencies) involved in this project and shall cooperate with all other contractors and government agencies so as to facilitate the general progress of the work. Before proceeding with any work, the contractor and/or subcontractor shall consult applicable drawings and specifications for each trade involved.

5. CONSTRUCTION: The contractor shall submit a request for the construction permit at least ten (10) working days prior to the starting of work. The request shall be submitted to the COR for approval.

6. MATERIALS COMPLIANCE: The contractor shall make certain all materials used meet the requirements of the contract and proof thereof upon request of the COR. Materials not meeting the requirements of the contract shall not be brought to the job site. All materials shall be new and the standard products of a manufacturer regularly engaged in the manufacturing of such materials.

7. HOISTING AND MOVING EQUIPMENT: The Contractor and each subcontractor shall provide and be responsible for all cranes, lifts, etc., necessary for the proper and efficient movement of materials. The equipment shall be provided with proper guys, bracing, safety devices, etc., as required by law.

8. EQUIPMENT: All contractor equipment shall be subject to functional and safety inspection by the COR.

Equipment not completely safe or functional shall be repaired before work is started.

9. RECORD DRAWINGS: During performance of work, the contractor shall accurately record and delineate on a set of full-size blue line prints of contract drawings all changes in such work which constitute departures from the original contract drawings. The set of drawings (one original and one blue line print), thus corrected and changed, usually referred to as “As-Built Drawings”, shall be delivered to the COR at the final acceptance/inspection of the completed work by the Government.

TP III - 1

10. US ORIGIN MATERIALS: If applicable, all US Origin Materials will be ordered immediately after Notice to

Proceed.

11. RELEASE OF FACILITIES WITH U.S. ORIGIN MATERIALS: If applicable, Building/facility will not be released to the contractor by the COR until all U.S. origin building construction supplies are available or due within such a time frame that there will be no delay in project completion.

12. UTILITY CUTOVERS AND INTERRUPTIONS: Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and U. S. Government holidays. Conform to procedures required in the paragraph

"Work Outside Regular Hours." Ensure that new utility lines are complete, except for the connection, before interrupting existing service. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruption shall be limited to 4 hours. This time includes for deactivation and reactivation.

13. WORK OUTSIDE REGULAR HOURS: Work outside regular working hours requires Contracting Officer approval. Make application 14 calendar days prior to such work to allow arrangements to be made by the

Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During the period of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours on Saturdays, Sundays, and U. S. Government holidays unless directed otherwise.

14. WINTERIZATION: The contractor may be required to perform the work during the winter season, which may cause the contractor for additional cost. These additional costs are the contractor’s responsibility in the event of working during this period. The Contractor shall reflect these costs in the preparation of his proposal.

15. SAFETY: The safety plan must be approved before any work can be performed on this contract. Hard hats, suitable work boots and other necessary personnel protective gear are mandatory. Contractors are required to get a written permission from safety office (POC: Mr. To, Pong Uk, DSN: 768-8971) and Fire and Emergency Service

(POC: Fire Communication office, DSN: 768-4120) prior to enter confined spaces (i.e. manholes). Contractors should be properly trained and equipped with PPEs, calibrated air monitoring instrument, to work at confined spaces to insure compliance with OSHA (Occupational Safety and Health Administration) 29 CFR 1910.146.

16. SECURITY: All prime contractor and subcontractor personnel will be required to obtain a station pass from the

Base Security Office. It is the prime contractor’s responsibility to supply information to security regarding all prime and subcontractor personnel and a list of all vehicles that will be driven on the site.

17. WARRANTY: The contractor shall be responsible for remedy of failure in government contract during the one

(1) year warranty time. The contractor shall be refurnishing services or/and repair and replacement for remedy. The one (1) year warranty starts the day after final inspection approval from the authorized personnel.

TP III – 2

18. ANTITERRORISM/OPRATIONS SECURITY REQUIREMENTS.

18.1. AT Level 1 Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a

COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.

18.2. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil

18.3. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the

National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database

(TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at

OCONUS locations, in accordance with status of forces agreements and other theater regulations.

18.4. iWATCH TRAINING. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

19. ENVIRONMENTAL MANAGEMENT SYSTEM (EMS): Recycling all eligible material, including glass, paper (including magazines), plastic, aluminum, and cardboard to the maximum extent practicable;

Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content;

Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling;

Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must;

TP III – 3

http://jko.jten.mil/ http://jko.jten.mil/

20. CONTAMINATION FIND CLAUSE: When contaminated soil is encountered during excavation work, contractor shall report the findings to the Environmental Office immediately and contractor will segregate contaminated soil from clean soil.

21. INADVERDENT FIND CLAUSE: When potential cultural or historic items are inadvertently found during construction activities, contractor shall cease activities in the vicinity of the discovery and report the findings to the

Environmental Office immediately. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch.

12, Para 12-3 J)

22. FUEL TANK AND LINES: If applicable, when underground piping associated with POL storage containers shall be tested for integrity and leaks at the time of installation, modification, construction, relocation, or replacement. New underground piping must be protected against corrosion IAW recognized industry standards.

(Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 9, Para 9-3.b. (5))

23. Non-PCB TRANSFORMER CERTIFICATION: If applicable, before contractor replace/install any transformer at USAG Daegu, contractor shall submit two copies of non-PCB transformer certification to COR for each to be installed transformer. New transformer will be installed after COR's approval for non-PCB transformer certification for each to be installed transformer.

24. CONTRACTING MANPOWER REPORTING

24.1 (CMR) Requirement: The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor will report ALL Contractor manpower (including sub-contractor manpower) required for performance of this contract. The Contractor is required to completely fill in all the CMR information in the format using the following web address:

https://cmra.army.mil. However, before the Contractor can begin reporting CMR data in this website, he or she must first register as a User. In order to register, the Contractor must have a Cage Code.

24.2 How to Obtain Cage Code for Korean Company: If you are a Korean company needing a Cage Code, at

Telephone #82-2-2079-4639, FAX 82-2-773-7587, EMAIL CAGEKR@dapa.go.kr , Address: The Standard

Planning Team of the Standard Management Bureau Defense Acquisition Program Division (23 Yongsangogyogil), #2-15 Yongsan 2 ga dong, Yongsan-gu, Seoul (140-841), Republic of Korea.

신청 절차

1. 방위사업청 국방전자조달 홈페이지 (www.d2b.go.kr)에 접속 합니다.

2. 방위사업청 국방전자조달 홈페이지 메인화면의 민원서비스 – 나토 생산자 (Ncage) 부호 신청을 클릭

합니다. 로긴(Login) 없이 접속 가능

3. 나토생산자부호 (Ncage) 부여요청을 위한 Login 화면에서 회원가입을 합니다.

*유의사항: 아이디와 비밀번호는 요청및 결과확인용으로 가능하며 국방전달조달 메뉴에 있는 기타

다른 업무에는 사용할 수 없습니다.

TP III – 4

4. 회원가입시 번호 부여 대상이 회사인 경우에는 사업자등록증번호, 개인일 경우에는 DUNS번호를

기입합니다.

5. 가입한 아이디와 비밀번호로 로긴하여 접속 후 온라인 나토생산자부호 요청서에 해당업체에 대한

정보를 기록합니다.

6. 회사인 경우에는 사업자등록증, 개인일 경우에는 DUNSNUMBER 부여결과서를 스캔하여 EDM에 jpg

파일로 첨부합니다.

7. 등록한 후 재 조회를 하여 업체자료가 정상적으로 신청이 되었는지 확인합니다.

8. 신청서의 접수 및 진도는 요청서 상단의 진행 상태를 확인 합니다.

*진행상태: 신청완료, 접수완료, 작업완료등 빨간색으로 변경

*처리소요기간: 1일-2일 *비용: 무료

Once the CAGE code is issued for your company, your company is ready to do CMR registration. For CMR registration, please follow the instruction in the solicitation/contract titled ―Accounting for Contract Services.

After your company‘s CMR registration application is reviewed by U.S Department of Army. You will receive e-mail notification within 2 to 3 working days whether your CMR registration application is approved or not. If it is disapproved, please read carefully the comments provided by DA and correct registration application as commented.

After your company‘s CMR registration is approved, your company is ready to do CMR report. There will be short lesson giving how you report CMR on the web site.

24.3 CMR Reporting: The information required to be reported in the CMR website includes: (1) Contracting

Office, Contracting Officer, Contracting Officer’s Technical Representative (COTR) or Contracting Officer’s

Representative (COR); (2) Contract Number, including Task and Delivery Order Number(s); (3) Beginning and

Ending dates covered by reporting period; (4) Contractor Name, Address, Phone Number, E-Mail Address, Identity of Contractor Employee entering data; (5) Estimated Direct Labor Hours (including sub-Contractors’ hours); (7)

Total Payments (including sub-Contractors’ payments); (8) Predominant Federal Service Code (FSC) reflecting services provided by Contractor (and separate Predominant FSC for each sub-Contractor if different); (9) Estimated data collection cost; (10) Organizational Title associated with the Unit Identification Code (UIC) for the Army

Requiring Activity reporting this information (the Army Requiring Activity (RA) is responsible for providing the

Contractor with its UIC for purposes of reporting this information); (11) Locations where Contractor and sub-

Contractors perform the work (specified by zip code in the United States and nearest City and Country when in an overseas location, using standardized nomenclature provided on website); (12) Presence of Deployment or

Contingency Contract language; and (13) Number of Contractor and sub-Contractor employees deployed in theater this reporting period (by Country).

TP III – 5

As part of its submission in response to a solicitation or a modification request which includes a contract line item number (CLIN) for this CMR reporting requirement, the Contractor shall also provide the estimated total cost (if any) incurred to comply with this reporting requirement on the associated CMR CLIN. Reporting period will be the period of performance not to exceed 12 months ending September 30 of each Government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a

Contractor’s systems to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from the website.

CMR reporting is a requirement mandated by the Department of Army. Failure of the Contractor to comply with this requirement will be noted as Past Performance information about the Contractor to be used on future procurements for the same or similar services.

TP III – 6

APPENDIX "A"

LIST OF APPLICABLE CONTRACT DRAWINGS

GENERAL: The work shall conform to the standard detail drawings (dated 30 November 2015, issued by the

Department of the Army, Installation Management Agency, Korea Region Office and located USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK), all of which form a part of the specifications.

Drawing No. Ref. No. Sheet No. Description Date

D-20-13 R-1 1 of 1 Title Sheet-1 22 Jun 20

“ M-1 1 of 4 Legend and Abbreviations “

“ M-2 2 of 4 General Notes, Equipment Schedule and Scope of Work “

“ M-3 3 of 4 New Hot Water Heating Boiler System Plan “

“ M-4 4 of 4 New Hot Water Heating Boiler System

Isometric Diagram “

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 POP 26-AUG-2020 TO

26-JAN-2021

N/A W6B1 USA GARRISON DAEGU

W6B1 USA GARRISON DAEGU

DPW

UNIT 15746

APO AP 96218-5746

UNITED STATES

011-82-53-470-65

FOB: Destination

WT4KB6

Section G - Contract Administration Data

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.232-18 Availability Of Funds APR 1984

CLAUSES INCORPORATED BY FULL TEXT

52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)

(a) The offeror certifies that --

(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –

(i) Those prices,

(ii) The intention to submit an offer, or

(iii) The methods of factors used to calculate the prices offered:

(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and

(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.

(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --

(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or

(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);

(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and

(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs

(a)(1) through (a)(3) of this provision.

(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.

(End of Provision)

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the

Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 calendar days from notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

5152.204-4032 REPRESENTATIONS AND CERTIFICATIONS

(a) SUBCONTRACTING:

If the offeror contemplates subcontracting, it must obtain prior written approval of subcontractor from the PCO or

ACO, and list below: (1) the names and addresses of the subcontractor(s), (2) the type of subcontracting, and (3) the estimated price for each subcontract.

(b) AFFILIATED OFFERORS:

(1) Business concerns are affiliates of each other when, either directly or indirectly, one concern controls or has the power to control the other, or a third party controls or has the power to control both.

(2) Each offeror shall furnish, below, the following information:

(i) Whether the offeror has any affiliates;

(ii) The names and addresses of all affiliates of the offeror; and

(iii) The names and addresses of all persons and concerns exercising control or ownership of the offeror and any or all of its affiliates, and whether they are common officers, directors, stockholders holding controlling interest, or otherwise.

AFFILIATED CONCERNS. : (Name, location and, in detail, controlling interest in each)

(c) PRINCIPAL OWNER(S) OR STOCKHOLDER(S):

Each offeror shall list below the name(s) and address(es) of the principal owner(s) or stockholder(s) of the company and percentage of ownership. If a major portion is publicly traded and/or otherwise widely distributed, state that, with the percentage so affected.

(d) STANDARDS OF CONDUCT CERTIFICATION:

This is to certify that, to the best of my knowledge and belief, except as described below, no representative of this firm who deals with US Government employees on any aspect of this procurement is a former US Government employee, to include former US military personnel. I understand that this certification is continuing in nature and places a duty on me and my firm to notify the Contracting Officer of any additional individual(s) who fit the above description prior to the individual's assuming duties.

(i) Name ______________________________________________

Former rank/grade ____________________________________

Last US Government position ___________________________

(ii) Name ______________________________________________

(iii) Name ______________________________________________

Firm ____________________________________________________

Name _____________________________________________________

Signature __________________________________________________

Title _____________________________________________________

Date of Execution ____________________________________________

(e) TAXES:

(1) References:

(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."

(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.

(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.

(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.

(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

This item will be imported specifically for this contract? Yes _____ No _____

(ii) Special Excise Tax:

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

Name of item manufacturer

(iii) Value Added Tax (VAT):

Input VAT on materials purchased for this contract. 10% _____

Input VAT on transportation leased/rented for this contract.10% _____

Input VAT on equipment leased/rented for this contract. 10% _____

Input VAT on services purchased for this contract. 10% _____

Output VAT on total contract amount. 10% _____

(iv) Special Excise (Petroleum) Tax:

No. of U/P

Liters w/o Tax Tax/Unit Total Tax Amount

Regular Gasoline ________ (L) ________ w________ w_____________

Premium Gasoline ________ (L) ________ w________ w_____________

Diesel ________ (L) ________ w________ w_____________

Other ________ (L) ________ w________ w_____________

(v) Education Tax.

(3) Name of the oil company from which POL products will be purchased:

Oil Company: _________________________________________ (Name only)

(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.

Signed (Chop)

(f) CERTIFICATIONS AND REPRESENTATIONS

By submitting an offer, each offeror agrees to be bound by all certifications and representations in this solicitation.

The Government reserves the right to require any and all certifications and representations to be completed and signed in hard copy by the successful offeror prior to contract award. Failure of an offeror to complete the certifications and representations within the time directed by the Contracting Officer may result in a determination that the contractor is not a responsible offeror for this acquisition.

Section L - Instructions, Conditions and Notices to Bidders

INSTRUCTION TO OFFEROR

Addemdum to Instructions to Offeror

The Government intends to award without discussion, but reserves the right to conduct discussions if deemed necessary and to establish a competitive range for efficiency in accordance with FAR 52.215-1(f)(4).

Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted.

The questions are due No Later Than 5 days after the solicitation issued date. All questions should be emailed to yun.p.hong.civ@mail.mil.

SUBMISSION OF PROPOSAL:

SUBMISSION REQUIRED: Offers shall be emailed to yun.p.hong.civ@mail.mil with the evidence document such as screen shot.

CLOSING DATE: The electronic offer shall be submitted by the due date specified in the page # 1, Block # 13 of this RFP.

SUBMISSION REQUIREMENTS:

PRICING PROPOSAL: The pricing proposal must clearly indicate prices for each Contract Line Item Number in

Section B - Supplies or Services and Prices.

DETAILED OFFER BREAKDOWN: The detailed offer breakdown must clearly identify all costs that can materially impact the statement of work.

SECTION K - Representations, Certifications and Other Statements of Offerors

SECTION K-TAXES: Offerors must complete all tax portions of SECTION K. The offeror shall review all expenses to ensure that all applicable taxes are excluded from the overall price. In addition, offerors shall propose exemptions of specific ROK taxes that are legitimate, attributable to the contract, and authorized by the applicable stated references.

SECTION K-OTHER: Offerors must complete all Non-Tax related portions of SECTION K.

COMPLIANCE WITH SOLICITATION: Failure to submit the above requirements under SECTION L may be grounds for determining the proposal to be non-compliant. For example, if a detailed offer breakdown is not submitted, the contracting officer will be unable to find the offeror's pricing proposal acceptable and the offeror's proposal will be ineligible for award. Non-compliance will only be cured if the government holds discussions as detailed in SECTION L.

EVALUATION

Evaluation Factors for Award Electronic offers submitted by 1000 hours Local on the closing date of RFP shall be considered timely.

EVALUATION CRITERIA

The pricing proposal shall be evaluated to determine whether it is complete and reasonable. A complete and reasonable pricing proposal will be deemed acceptable.

mailto:yun.p.hong.civ@mail.mil mailto:yun.p.hong.civ@mail.mil

The detailed offer breakdown will be used by the contracting officer to determine whether proposed prices are complete and reasonable. A detailed offer breakdown may be used by the contracting officer to determine whether an offeror is able to complete the requirements under the contract, and/or whether discussions will be conducted pursuant to instructions to the offerors.

SECTION K - Representations, Certifications and Other Statements of Offerors

SECTION K-TAXES will be evaluated to determine whether it is complete. In addition, propose exemptions of specific ROK taxes will be evaluated to determine whether they are legitimate, attributable to the contract, authorized, and reasonable. A complete SECTION-K that only proposes exemptions of specific ROK taxes that are legitimate, attributable to the contract, necessary to complete the Task Order, do not improperly overstate any proposed tax exemption, authorized, and reasonable will be deemed acceptable.

SECTION K-OTHER will be evaluated to determine whether it is complete. A complete SECTION K-OTHER will be deemed acceptable.

BASIS FOR AWARD: Award shall be made to the responsible offeror submitting the lowest priced offer that is evaluated as acceptable for all evaluation criteria.

CLAUSES INCORPORATED BY FULL TEXT

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for--

Date: 21 July 2020

Time: 10:00 AM

(c) Participants will meet at--

Location: TBD

(d) POC: Mr. Yi, Tong Ki, Email Address: tongki.yi2.ln@mail.mil; Phone Number: 010-3820-3835.

NOTE:

(1) Any participants who need to be escorted must contact POC above a day prior to the date of site visit.

(2) The Attendee must bring a photo identification card (Korean ID Card: Ju-min-deng-rok-jung) when attending the site visit orientation.

(End of provision)

5152.236-4011 CONSTRUCTION PRICE RANGE

Pursuant to FAR 36.204 the estimated price range is between $ 25,000.00 and $100,000.00.