Solicitation Package
47PJ0023R0021
FDA Flooring Replacement Fargo, North Dakota
Table of Contents
SF1442 Solicitation, O�er, & Award …...………………………………………………………… 2
The Agreement ………………………………………………………………………………………………. 5
Construction Scope of Work ………………………………………………………………… 8
Cass County Wage Determination ……………………………………………………….. 17
The Solicitation ………………………………………………………………………………………………. 50
Representations & Certifications …………………………………………………………………… 63
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO negotiable.notice to proceed. This performance period is mandatory calendar days and complete it within calendar days after receiving
b. TELEPHONE NUMBERa. NAME (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)47PJ0023R0021
GSA PBS NORTH DAKOTA FIELD OFFICE 8PMPN
657 2ND AVE N RM 244
Fargo, ND 58102 USA
As detailed in the Construction Scope of Work, contractor will replace the existing vinyl flooring located in the FDA Sample Prep Room.
8PMPN
GSA PBS NORTH DAKOTA FIELD OFFICE 8PMPN
657 2ND AVE N RM 244
Fargo, ND 58102 USA
EQ8PSMMN-23-0010
8PMPN
701-566-6114Laura Funk
N2046208
4:00 PM
PAGE OF PAGES
2 71
3. DATE ISSUED
1/5/2023
1/26/2023
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
8PMPN
GSA PBS NORTH DAKOTA FIELD OFFICE 8PMPN
657 2ND AVE N RM 244
Fargo, ND 58102 USA
PBS PAYMENTS BRANCH -https://finance.ocfo.gsa.gov/
P.O. BOX 17181
https://finance.ocfo.gsa.gov/
FORT WORTH, TX 76102-0181 USA
Laura Funk
GENERAL SERVICES ADMINISTRATION
ITEM NO.
(a)
SUPPLIES OR SERVICES
(b)
QUANTITY
ORDERED
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
0001 __________
PoP: 01/16/2023 - 04/14/2023 flooring in the FDA Sample Prep Room with an epoxy-based
Contract Type: Firm Fixed Price
The purpose of this project is to replace the existing vinyl
PSC: Z2AA -- REPAIR OR ALTERATION OF OFFICE BUILDINGS
FDA Flooring Refresh
Deliverable feet.
LS
Place of Performance: 657 2ND AVE N FARGO, ND 58102-4727 flooring. The Sample Prep room is approximately 235 square
PAGE OF4 71
Sol. Reference No. 47PJ0023R0021 GSA Contract No. TBD
(The Agreement)
Simplified Acquisition Construction Contract for: Food and Drug Administration (FDA) flooring refresh located at 657 2nd Ave N., Fargo, North Dakota.
The Agreement
Table of Contents
I. Project Information
I.A. Project Summary I.B. The Contract I.C. Period of Performance I.D. Work Conditions/Site Requirements I.E. Authorized Representatives I.F. Contract Liquidated Damages Rate I.G. Buy American Exceptions I.H. Statement of Work, Specifications, Drawings, Exhibits, and Other Attachments
III. Prices
III.A. Basis of Pricing III.B. Contract Price Form
IV. Terms and Conditions
IV.A. FAR 52.211-10, Commencement, Prosecution, and Completion of Work and GSAR 552.211-10, Commencement, Prosecution and Completion of Work
IV.B. Contractor Responsibilities IV.C. Material and Workmanship IV.D. Project Schedule IV.E. Interpretation of Specifications and Drawings IV.F. Submittals IV.G. Government's Right to Stop Work for Non-Compliance IV.H. Other Contracts IV.I. Use and Possession Prior to Substantial Completion IV.J. Finality of Contract Modifications IV.K. Liquidated Damages IV.L. Insurance Requirements IV.M. Administrative Matters IV.N. Safeguarding Sensitive Data and Information Technology Resources IV.O. Additional Terms and Conditions
V. Contract Clauses
V.A. Clauses Incorporated in Full Text V.B. Clauses Incorporated by Reference
I. Project Information
I.A. Project Summary
The purpose of this project is to replace the existing vinyl flooring in the FDA Sample Prep Room with an epoxy-based flooring. The Sample Prep room is approximately 235 square feet.
I.B. The Contract
(1) The Contract consists of the SF1442, the Agreement, the Statement of Work, Specifications, Drawings, Exhibits, Amendments, Modifications, and other Attachments identified herein (collectively, the Contract Documents). The Contract contains the entire agreement of the Parties, and no prior written or oral agreement, express or implied, shall be admissible to contradict or modify any part of the Contract.
(2) The Contractor shall provide and pay for all labor, materials, equipment, tools, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution of the work described in and reasonably inferable from the Contract Documents (the Work), whether temporary or permanent. In consideration for, and upon condition of, the Contractor's completion of the Work, GSA shall pay the Contractor the price or prices established in Section II, subject to the terms and conditions set forth in this Contract.
I.C. Period of Performance
(1) Commencement. The Contractor shall commence performance of the Work within 10 days of receiving contract award.
(2) Substantial Completion. The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, no later than 80 calendar days from issuance of contract award.
(3) Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 10 calendar days of Substantial Completion.
I.D. Work Conditions/Site Requirements
Work is located inside of the Federal Building / Post Office at 657 2nd Ave N., Fargo, North Dakota.
I.E. Authorized Representatives
(1) This Contract is between the United States of America, acting by and through the Administrator of General Services (GSA), and the Contractor (the Parties). References in this Contract to "the Owner" or "the Government" shall be understood to refer to GSA. The following individual is designated as the only authorized GSA representative under this Contract, unless other warranted contracting officers are designated in writing:
Authorized Representative Information:
Contracting Officer's Information
Name: Laura Funk
Telephone: (701) 566-6114
Email: laura.funk@gsa.gov
(2) For the applicable authorities and limitations see Section IV of this Agreement, GSAR 552.236-70.
I.F. Contract Liquidated Damages Rate
In accordance GSAR 552.211-12, Liquidated Damages - Construction, in Section IV of this Agreement, liquidated damages shall be calculated at the rate of $0 per calendar day.
I.G. Buy American Exceptions
For the applicable Buy American clause and any exceptions, see Section IV of this Agreement.
I.H. Statement of Work, Specifications, Drawings, Exhibits, and Other Attachments
The following documents are incorporated by reference into this Contract.
[CO Instruction: Insert project specific list of documents, including, as applicable, those listed in the sample. Modify the list to reflect project specific documents (e.g., NEPA, mitigation and historic preservation documents as appropriate).]
(1) GSA Construction Scope of Work dated 12/9/2022
(2) Wage Determination ND20220013, Dated 11/25/2022
[Remainder of Page Intentionally Blank]
CONSTRUCTION SCOPE OF WORK
U.S. GENERAL SERVICES ADMINISTRATION, ROCKY MOUNTAIN REGION 8
Date : 12/9/2022 Revision :
Section 1: Project Title Refresh Flooring in FDA Sample Prep Room
Section 2: Project Location, Building Name, & Building Number Fargo Federal Building / Post Office, 657 2nd Ave N, Fargo, ND 58102 Building Number: ND0046ZZ
Section 3: Contact List
Contracting Officer Name: Laura Funk Email: laura.funk@gsa.gov Address: 657 2nd Ave N. #244
Fargo, ND 58102 Phone (o): 701-566-6114 Phone (c): 701-541-3129
Property Manager Name: Travis Mart Email: travis.mart@gsa.gov Address: 657 2nd Ave N. #244
Fargo, ND 58102 Phone (o): 701-566-6126
Development Project Manager Name: Jim Boisjolie Email: james.boisjolie@gsa.gov Address: 657 2nd Ave N. #244
Fargo, ND 58102 Phone (C): 701-541-2368
(Construction Scope of Work) Page 8 of 71
Section 4: Project Background & Project Description The purpose of this project is to replace the existing vinyl flooring in the FDA Sample Prep Room with an epoxy-based flooring. The Sample Prep room is approximately 235 square feet.
Section 5: Project Objectives The contractor shall provide labor, materials, equipment, and supervision necessary to perform:
1) Remove all furniture and appliances out of the space prior to work. A staging area will be determined by the Building Manager prior to starting work.
2) Remove and dispose of the existing vinyl flooring.
3) Contractor shall remove all surface contamination, loose or weakly adherent particles, laitance, grease, oil, curing compounds, paint, dust, and debris by blast track method or approved mechanical means (acid etch not allowed).
4) If required, use patching and fill material to fill holes and depressions in substrates according to manufacturer's written instructions.
5) Treat control joints and other nonmoving substate cracks from reflecting through resinous flooring according to manufacturer's written instructions.
6) Apply primer over prepared substrate at manufacturer's written recommendations.
7) Apply slip resistant finish.
8) Apply topcoats in number indicated for flooring system and at spreading rates recommended in writing by manufacture.
9) Contractor shall insure the coating is protected from any traffic until it is fully cured to the satisfaction of the coating manufacturer.
10) Upon completion of work, clean up and remove from the premises surplus materials, tools, appliances, empty cans, cartons and rubbish resulting from work. Clean off all spattering and drippings, and all resulting stains.
11) Replace all removed furniture and appliances.
12) Flooring color shall be similar to, Sherwin Williams General Polymers Ceramic Carpet, 332 Charcoal. Submit flooring color sample and grit sample to the Project Manager for approval.
13) A staging area will be determined by mutual agreement after contract award.
14) The following information is provided for bidding purposes only. The contractor is advised to conduct a site visit and field-verify the exact information required for use in completing the work and submitting an offer.
15) No asbestos or lead containing materials shall be used.
16) All work shall comply with codes and standards applicable to each type of work through the course of this project including the National Electric Code (NFPA 70). Contractor shall also comply with the requirements of GSA Build Green Standards, and PBS P-100.
(Construction Scope of Work) Page 9 of 71
17) The contractor is responsible for the protection of all existing building property surfaces from damage due to work performed under this contract. Damages to existing surfaces caused by the performance of this contract shall be repaired as to match the existing surface finish at no additional cost to the Government.
18) The Contractor shall remove all debris generated in the performance of this contract daily.
19) The contractor shall take all necessary precautions to prevent any dust or debris from filtering into other parts of the building including but not limited to mechanical systems.
Should dust or debris filter into other parts of the building the contractor shall take immediate steps to clean the area (no equipment or supplies will be furnished by GSA).
20) At the completion of the project, the project area shall be cleaned to building standards as determined by the GSA Property Manager. Should the contractor fail to clean the project limits in a timely manner, GSA will contract for said cleaning and the cost will be deducted from the contract. Ensure that all penetrations are sealed with fire rated approved material as required by the International Building Code.
21) The CO has the right to reject any unsatisfactory or unsuitable material or workmanship.
Section 6: Proposal Pricing & Site Walk
1) Pre-proposal Site Visit Meeting :
a) The site visit shall consist of a meeting to review construction requirements followed by a walk-thru of the project site. The meeting shall be attended by the contractor and GSA project personnel, and appropriate sub-contractors. Contact the Project Manager to schedule a site visit.
b) Review existing conditions of the project area including any field verification.
c) Review the solicitation/evaluation requirements
2) Cost Proposal Requirements:
a) When submitting a proposal, provide a cost breakdown for each task into the following categories: Materials, equipment, labor hours, subcontractor's quotes, overhead, profit, and bond broken down into shell, tenant improvement (TI) (by tenant), Building- Specific Amortized Capital (BSAC), and environmental (as applicable). Follow P120 guidelines for tier level 3 based on project triage tool.
Pricing shall be broken down by Construction Specification Institute (CSI) divisions.
b) Base Bid-
Section 7: Period of Performance The contractor has 90 calendar days to complete the project from the time of contract award.
The contractor must also promptly begin the badging process at the time of award. Please allow a minimum of 30 days to complete the badging process. Extensions will be granted for
(Construction Scope of Work) Page 10 of 71 unforeseen conditions and other factors outside of the contractor’s control at the Contracting Officer’s discretion.
Section 8: Universal Scope Requirements
● ALL of the requirements in this section are MANDATORY for ALL GSA projects
● See the attached Universal Scope Requirements document for the full details outlining each item
● Failure to comply with any and all of the requirements will result in the project not being accepted as complete
REQUIREMENTS for ALL Projects (Construction, Design & Design/Build)
a. Safety and Health Program
b. Asbestos Containing Materials. To comply with federal and state regulations as well as
GSA policy, an asbestos pre-alteration assessment is required for all construction projects as outlined in Section B of the Universal Scope Requirements.
c. Lead Containing Paint / Lead Based Paint
d. Accessibility
e. Green Purchasing
f. Construction Indoor Air Quality (IAQ) Management Plan
g. Construction Waste Diversion
Section 9: Submittals
1) Contractor shall submit a Method of Procedures (MOP) to the GSA Delivery Project
Manager (PM) for approval prior to commencement of work. At a minimum, the MOP shall include:
a) Brief narrative describing method of accomplishment, construction techniques, etc
b) Project schedule (to include critical path, major milestones, long lead time items, mobilization & demobilization, inspection dates, substantial completion, and occupancy dates)
c) Service/Utility Outages (if necessary)
d) Phasing schedule (if necessary)
e) Any building infrastructure/BAS equipment that may be impacted
2) As- Builts (CAD and/ or BIM) BIM is required for any project above the Simplified Acquisition Threshold, currently $250,000.
3) Pre-alteration assessment report
4) All new equipment and anything requiring a preventative maintenance plan shall be inputted into Maximo upload template. Information needed from the contractor will be all:
Manufacturer, Model Number, Part Number, Serial Number, Any Manufacturer Warranty Information.
5) Manufacturer's specifications, instructions and material specification sheets in original form
6) Submittal register/ log for all products specified to establish a standard of quality to include. Submittal register response by the government shall be 14 calendar days or less.
(Construction Scope of Work) Page 11 of 71
a) For pricing purposes, please assume 1 hard copy of submittals and 1 electronic copy to be sent to the project manager. Distribution list including final quantities will be finalized after receipt of the submittal log/ register by GSA project manager.
7) If product samples are not submitted in a timely fashion, any delays caused by the contractor will not warrant a time extension. After completion of all work, the Contractor shall submit to the project manager the manufacturer's specifications, instructions and material specification sheets in original form. Additionally, the Contractor shall submit all inventory changes (removals, additions, upgrades, etc., and new condition codes) to the
COR.
8) Submittal response by the government shall be 14 calendar days or less.
Section 10: General Requirements
1) Contractor Use of the Premises
During the period of the project, the contractor will have access to the site only during business hours of 8:00 am and 5:00 pm. No on-site work shall be performed outside these hours or on holidays unless otherwise directed by the Contracting Officer. The contractor will need to coordinate with the Contracting Officer to arrange access to the parking lot. The contractor shall make every effort to cause a minimum of damage to parking lots, any other paved areas, any items that need to be moved during the course of the project, and any areas not included in this scope of work. Any damage caused will be repaired at the contractor’s expense.
2) Progress Meetings Progress meetings are not required for this project. The project manager and building team representative shall make daily inspections of the work progress.
3) Equipment The contractor shall provide all equipment associated with the entire project, operate in a safe manner and adhere to all OSHA and GSA standards.
4) Equipment and Material Storage The contractor shall provide and store all equipment, the materials specified above, and any other materials required completing the project. The materials are required to be kept clean and dry throughout the duration of the project. Contractor to coordinate with building manager for location of storage sheds.
5) Electricity, Water, and Gas GSA will pay for electricity, water, and gas during the course of this project. The contractor is responsible for making connections to the existing systems. Temporary electrical work shall meet the requirements of NFPA 70-1996 (NEC), Article 305. When temporary connections are removed, restore existing utility services to their original condition.
6) Contractor’s Field Office The contractor may provide an office for their own use. Size, location, and construction shall be subject to approval.
7) Fire Watch Contractor shall be responsible for providing fire watch if required per attached GSA fire watch guidelines.
(Construction Scope of Work) Page 12 of 71
8) Fire Alarm Impairment and Hot Work When a fire suppression or alarm system impairment is required, the contractor shall provide a written outage request to GSA for approval in advance of impairing any systems. Contractor shall be responsible for having a GSA approved NICET certified fire alarm contractor perform all system impairments. During fire alarm/suppression impairments or hot work procedures, the contractor shall provide a fire watch per the GSA Regional Fire Watch Guidelines.
9) Protection of Public The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.
The contractor shall illuminate barricades and obstructions at night and maintain safe building access and egress for tenants.
10) Housekeeping The project site shall be kept in a neat, orderly, and safe condition at all times. The contractor shall provide enough containers for collecting construction debris and construction materials to be recycled. The contractor shall wet down dry materials and rubbish to prevent blowing dust and keep volatile wastes in covered containers.
11) Transportation and Deliveries The contractor shall arrange deliveries of materials in accordance with construction schedules; coordinate with COR to avoid conflict with other tenants and other work conditions at the site. Contractor must make GSA PM & CO aware of any lead times that may affect the project schedule.
12) Cleaning Before scheduling the final inspection, the Contractor shall accomplish six items: (1) Remove all tools, equipment, surplus material, and rubbish; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Remove grease, dirt, stains, foreign materials, and labels from finished surfaces; (4) Thoroughly clean building interiors; (5) Pickup all construction debris from the site; and
(6) At time of final inspection, project shall be thoroughly cleaned and ready for use.
13) Protection of the Building The construction contractor is responsible for the protection of all existing building property for damage due to work performed under this contract. Any damage caused by the performance of this contract shall be repaired to match like or better condition at no additional cost to the government
14) Disruptive Work All painting, staining, or other activity which may cause noxious or undesirable fumes and/ or any noisy work that may be disruptive to the tenants/ public must be performed after normal working hours. The use of paint or stain that does not generate odors is preferred and may be required if the space will be occupied the following day with prior written approval from GSA.
Section 11: Badging & Security
1) The Contractor is responsible to follow GSA’s security and badging requirements as detailed in the Badging & Security Requirements provided at contract award.
(Construction Scope of Work) Page 13 of 71
2) US Access shared enrollment centers can be found at fedidcard.gov. Travel distances to the nearest center should be accounted for during the badging process.
Section 12: Payments Information regarding payment requests and payment is in the solicitation/ contract. Please contact the CO if you have any questions regarding payments.
Section 13: Substantial Completion & Final Inspection
1) When the project, or designated portion of the project is complete, request a final inspection. Upon receipt of a request that the project is substantially complete, the Contracting Officer will proceed with the inspection within ten days of receipt of request or will advise the contractor of items that prevent the project from being designated substantially complete.
2) Red-lined drawings and CAD and/or BIM as-built drawings, and field training for Operations and Maintenance (O&M) personnel shall be provided at completion of project. Maintain one complete set of contract drawings. Clearly mark changes, deletions, and additions using GSA CAD Standards to show actual construction conditions. Show additions in red, deletions in green, and special instructions in blue print. Provide to GSA within a time frame negotiated at time of award.
3) The contractor shall provide O&M manuals. The O&M manuals shall contain the following:
● Executed Warranties (at project completion)
● Maintenance and operation manuals
Section 14: Historical Building N/A
Section 15: Attachments
1) Universal Scope Requirements
2) Room Pictures
(Construction Scope of Work) Page 14 of 71
(Construction Scope of Work) Page 15 of 71
(Construction Scope of Work) Page 16 of 71
"General Decision Number: ND20220013 11/25/2022
Superseded General Decision Number: ND20210013
State: North Dakota
Construction Type: Building
County: Cass County in North Dakota.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $15.00 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2022. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $11.25 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2022. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at https://www.dol.gov/agencies/whd/government-contracts.
Modification Number Publication Date 0 01/07/2022 1 01/21/2022
(Cass County Wage Determination) Page 17 of 71
2 02/25/2022 3 04/15/2022 4 06/17/2022 5 07/22/2022 6 10/07/2022 7 11/25/2022
BOIL0647-006 01/01/2021
Rates Fringes
BOILERMAKER......................$ 40.94 28.44
* BRND0001-002 05/30/2022
Rates Fringes
BRICKLAYER.......................$ 33.54 14.86
ELEC1426-004 06/01/2022
Rates Fringes
ELECTRICIAN (Excludes Low Voltage Wiring)..................$ 33.85 11.5%+$12.44
IRON0512-006 05/01/2022
Rates Fringes
IRONWORKER, STRUCTURAL...........$ 35.95 33.11
PLAS0633-001 05/01/2021
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 33.88 16.87
PLUM0300-016 06/07/2021
Rates Fringes
PIPEFITTER.......................$ 38.19 17.42
PLUMBER..........................$ 38.19 17.42
SFND0669-002 04/01/2022
Rates Fringes
SPRINKLER FITTER (Fire Sprinklers)......................$ 36.78 21.85
SHEE9010-002 06/06/2022
Rates Fringes
SHEET METAL WORKER (HVAC Duct Installation Only)...............$ 28.19 21.15
* SUND2012-002 08/18/2014
Rates Fringes
CARPENTER (Drywall Finishing/Taping Only)...........$ 21.22 7.11
(Cass County Wage Determination) Page 18 of 71
CARPENTER, Excludes Drywall Finishing/Taping, Drywall Hanging, and Metal Stud Installation.....................$ 19.24 4.89
DRYWALL HANGER AND METAL STUD
INSTALLER........................$ 21.36 0.00
ELECTRICIAN (Low Voltage Wiring Only).....................$ 21.14 5.73
INSULATOR - MECHANICAL
(Duct, Pipe & Mechanical System Insulation)...............$ 15.80 2.60
LABORER: Common or General......$ 13.05 ** 2.92
LABORER: Mason Tender - Brick...$ 15.32 0.00
LABORER: Mason Tender - Cement/Concrete..................$ 14.54 ** 3.41
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 26.00 3.82
OPERATOR: Crane.................$ 26.18 9.39
OPERATOR: Forklift..............$ 23.06 15.47
OPERATOR: Loader................$ 23.75 0.00
PAINTER (Brush and Roller).......$ 21.86 8.41
ROOFER...........................$ 16.37 2.84
SHEET METAL WORKER, Excludes HVAC Duct Installation...........$ 27.27 7.76
TRUCK DRIVER: Dump Truck........$ 19.81 5.42
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($15.00) or 13658 ($11.25). Please see the Note at the top of the wage determination for more information.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is
(Cass County Wage Determination) Page 19 of 71 like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers (Cass County Wage Determination) Page 20 of 71
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
(Cass County Wage Determination) Page 21 of 71
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISIO"
(Cass County Wage Determination) Page 22 of 71
"General Decision Number: ND20220013 11/25/2022
Superseded General Decision Number: ND20210013
State: North Dakota
Construction Type: Building
County: Cass County in North Dakota.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $15.00 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2022. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $11.25 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2022. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at https://www.dol.gov/agencies/whd/government-contracts.
Modification Number Publication Date 0 01/07/2022 1 01/21/2022
(Cass County Wage Determination) Page 23 of 71
2 02/25/2022 3 04/15/2022 4 06/17/2022 5 07/22/2022 6 10/07/2022 7 11/25/2022
BOIL0647-006 01/01/2021
Rates Fringes
BOILERMAKER......................$ 40.94 28.44
* BRND0001-002 05/30/2022
Rates Fringes
BRICKLAYER.......................$ 33.54 14.86
ELEC1426-004 06/01/2022
Rates Fringes
ELECTRICIAN (Excludes Low Voltage Wiring)..................$ 33.85 11.5%+$12.44
IRON0512-006 05/01/2022
Rates Fringes
IRONWORKER, STRUCTURAL...........$ 35.95 33.11
PLAS0633-001 05/01/2021
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 33.88 16.87
PLUM0300-016 06/07/2021
Rates Fringes
PIPEFITTER.......................$ 38.19 17.42
PLUMBER..........................$ 38.19 17.42
SFND0669-002 04/01/2022
Rates Fringes
SPRINKLER FITTER (Fire Sprinklers)......................$ 36.78 21.85
SHEE9010-002 06/06/2022
Rates Fringes
SHEET METAL WORKER (HVAC Duct Installation Only)...............$ 28.19 21.15
* SUND2012-002 08/18/2014
Rates Fringes
CARPENTER (Drywall Finishing/Taping Only)...........$ 21.22 7.11
(Cass County Wage Determination) Page 24 of 71
CARPENTER, Excludes Drywall Finishing/Taping, Drywall Hanging, and Metal Stud Installation.....................$ 19.24 4.89
DRYWALL HANGER AND METAL STUD
INSTALLER........................$ 21.36 0.00
ELECTRICIAN (Low Voltage Wiring Only).....................$ 21.14 5.73
INSULATOR - MECHANICAL
(Duct, Pipe & Mechanical System Insulation)...............$ 15.80 2.60
LABORER: Common or General......$ 13.05 ** 2.92
LABORER: Mason Tender - Brick...$ 15.32 0.00
LABORER: Mason Tender - Cement/Concrete..................$ 14.54 ** 3.41
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 26.00 3.82
OPERATOR: Crane.................$ 26.18 9.39
OPERATOR: Forklift..............$ 23.06 15.47
OPERATOR: Loader................$ 23.75 0.00
PAINTER (Brush and Roller).......$ 21.86 8.41
ROOFER...........................$ 16.37 2.84
SHEET METAL WORKER, Excludes HVAC Duct Installation...........$ 27.27 7.76
TRUCK DRIVER: Dump Truck........$ 19.81 5.42
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($15.00) or 13658 ($11.25). Please see the Note at the top of the wage determination for more information.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is
(Cass County Wage Determination) Page 25 of 71 like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers (Cass County Wage Determination) Page 26 of 71
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
(Cass County Wage Determination) Page 27 of 71
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISIO"
(Cass County Wage Determination) Page 28 of 71
III. Prices
III.A. Basis of Pricing
(1) Contract Prices. All Contract prices set forth in this Section include all costs necessary to complete the work for which the price is established (e.g., Base Contract, Unit Price, Options) in accordance with the Contract Documents, including, but not limited to, the cost of work performed by subcontractors and consultants, indirect costs, fees, expenses, taxes, and profit.
(2) Knowledge of Conditions Affecting Price. FAR 52.236-3, Site Investigations and Conditions Affecting the Work, is incorporated by reference in this Contract. The Contractor shall be presumed to have established all prices with knowledge of general and local conditions that may affect the cost of Contract performance at the site where the Work is to be performed, to the extent that such information is reasonably obtainable.
(3) Unit Prices and Allowances. If any portion of the Work is to be performed on a unit price basis, the Unit Price shall include all costs of coordinating and incorporating the unit-priced portion of the Work into the Base Contract Work. The Contractor shall only be obligated to perform unit-priced work to the extent that an Allowance has been established. The Contractor shall be obligated to perform such work in excess of a unit quantity for which an Allowance is established only if directed by the Contracting Officer in writing.