This is a sealed bid Invitation for Bid (IFB) solicitation for construction services at the Federal Correctional Institution in Bastrop, Texas. The solicitation number is 15BBNF27Q50100001, issued on October 23, 2026, with a bid opening date of December 2, 2026 at 11:00 AM US/Pacific time.
The contractor shall provide all materials, labor, and equipment to complete the project titled "Install Generator at FCI Bastrop" in accordance with the attached Statement of Work and Specifications. The contract is firm fixed price with a project magnitude between $1,000,000 and $5,000,000. The contractor must begin performance within 10 calendar days of award and complete work within 420 calendar days. Performance and payment bonds equal to 100 percent of the original contract price are required within 10 days of award. A bid guarantee of 20 percent of the bid price or $3,000,000, whichever is less, must be submitted with the bid. Required insurance includes Workers Compensation ($100,000), Comprehensive General Liability ($500,000 per occurrence), and Comprehensive Automobile Liability ($200,000 per person, $500,000 per occurrence). The Federal Bureau of Prisons, Field Acquisition Office in Grand Prairie, Texas will administer the contract. The assigned Contract Administration Office and payment address is FCI Bastrop, located at 1341 Highway 95 North and PO BOX 730, Bastrop, TX 78602. Sealed bids must be uploaded to the specified Box.com URL. Offers must provide Government acceptance within 90 calendar days of the bid due date, and offerors should complete all solicitation form fields including Unique Entity Identifier, Tax Identification Number, CAGE Code, and Contractor Email.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Criminal History Check Form.pdf | ||
| Instructions to Offerors.pdf | ||
| Bid Bond SF24.pdf | ||
| Wage Determination TX20260285 Modification 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
15BBNF27Q50100001 Page 1 of 55
SOLICITATION,OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NUMBER
15BBNF27Q50100001
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
2. TYPE OF SOLICITATION 3. DATE ISSUED
10/23/2026
PAGE OF PAGES
1 55
IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
26Z5AV1
CODE 15BBNF
Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051
7. ISSUED BY 8. ADDRESS OFFER TO
9. FOR
INFORMATION CALL:
a. NAME
Patrick Ford pford@bop.gov
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
202-913-1665
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
The selected contractor shall provide all materials, labor, and equipment to complete the project titled Install Generator at the Federal Correctional Institution located in Bastrop, Texas, in accordance with the attached Statement of Work and Specifications.
PLEASE COMPLETE THE FOLLOWING ITEMS:
UNIQUE ENTITY IDENTIFIER:_____________________________
TAX IDENTIFICATION NUMBER: ____________________________
CAGE CODE:________________________________
CONTRACTOR EMAIL:_______________________________
System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in
SAM.
11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving10 420 award, X notice to proceed. This performance period is X mandatory negotiable. (See __________________________.)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).
X YES NO
12b. CALENDAR DAYS
Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
11:00 AM US/
Pacific a.
12/02/2026
b. An offer guarantee X is, is not required.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.
90d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d)
15B50126PR000252
Upload all documents to the following URL:
https://jefs.app.box.com/f/4e4f2bea75a149e2a95b05109fbfcbad
15BBNF27Q50100001 Page 2 of 55
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
CODE FACILITY CODE
The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
17.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified) 27
ITEM
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE
UNITED STATES CODE AT
26. ADMINISTERED BY 15B501
Federal Bureau of Prisons FCI Bastrop 1341 Highway 95 North Bastrop, TX 78602
Federal Bureau of Prisons FCI Bastrop
PO BOX 730
Bastrop, TX 78602
27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
Patrick R Ford
31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA
BY
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
15BBNF27Q50100001 Page 3 of 55
Table of Contents
Section Description Page Number
1 Solicitation, Offer and Award 2 Commodity or Services Schedule 3 Special Contract Requirements 4 Contract Clauses 5 Attachments
6 Solicitation Provisions 7 Representations and Certifications
15BBNF27Q50100001 Page 4 of 55
Section 2 - Commodity or Services Schedule
Firm Fixed Price
SCHEDULE OF SUPPLIES/SERVICES
CONTINUATION SHEET
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 The selected contractor shall provide all materials, labor, and equipment to complete the project titled Install Generator at FCI Bastrop in accordance with the attached Statement of Work and Specifications.
PSC: Z2FF
1 JB $________ $_________________
NOTE: The successful contractor shall be responsible for all applicable federal, state, and local taxes. No tax exemption certification will be issued by the Federal Bureau of Prisons. THE TOTAL PRICE SHALL BE WRITTEN ON LINE ITEM 17 OF THE SF-1442.
SPECIAL CONTRACT REQUIREMENTS
BONDS
(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)
(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Officer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows; a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)
(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(c) For construction contracts greater than $35,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives (FAR 28.102-1(b)(1)):
(1) A Payment Bond;
(2) An irrevocable letter of credit (ILC);
(3) A tripartite escrow agreement;
(4) A Certificate of Deposit; or
15BBNF27Q50100001 Page 5 of 55
(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.
(d) Individual Sureties.
(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, payment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they claim in their net worth at time of bid opening.
The Government's preferred method of proof is to have a statement of net worth prepared by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP). Statements from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Surety, is insufficient and will not be accepted without additional proof of value and ownership.
(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract location, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and information required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.
MAGNITUDE
The magnitude of this project is between $1,000,000.00 and $5,000,000.00.
REQUIRED INSURANCE
See FAR 52.228-5, Insurance - Work on a Government Installation.
The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required in the
Schedule or elsewhere in the contract.
TYPE AMOUNT
(1) WORKERS COMPENSATION & EMPLOYER'S LIABILITY $100,000
The required Workmen's Compensation Insurance shall extend to cover employee's liability for accidental bodily injury or death and for occupational disease with a minimum liability of $100,000.
(2) COMPREHENSIVE GENERAL LIABILITY with a minimum limit of:
PER ACCIDENT OR
OCCURRENCE FOR BODILY INJURY $500,000
This insurance shall include contractor's protective and contractual liability
(3) COMPREHENSIVE AUTOMOBILE LIABILITY with the following minimum limits:
PER PERSON $200,000
PER OCCURRENCE FOR BODILY INJURY $500,000
15BBNF27Q50100001 Page 6 of 55
PER OCCURRENCE FOR PROPERTY DAMAGE $ 20,000
PRE-CONSTRUCTION CONFERENCE
(a) Prior to the start of construction, Contracting Officers shall call a conference with the contractor, subcontractor(s), Warden, Controller/Business Administrator, Safety Manager, Facilities Administrator, Project Representative, A&E firm, Captain and other interested personnel to discuss the statutory labor standards, prevailing wage requirements, submission of the contractor's payrolls, subcontractor's responsibilities, institution work schedules, local policies, contraband, parking, storage of vehicles and equipment, etc.
Minutes of the conference shall be recorded, listing the names and titles of all attendees, and the subject matter of all items covered. The minutes shall be signed by the contractor and the Contracting Officer, and a signed copy placed in the contract file.
(b) The Contractor shall familiarize himself/herself with all procedures involved in normal institution routines. Any requirements which may constitute a problem or result in conflict, will be brought to the attention of the Contracting Officer or his representative for determination.
SUBMITTALS
Within 10 calendar days after commencement of work or as otherwise established by the Contracting Officer, all materials and articles requiring approval, as contemplated by the Materials and Workmanship clause, shall be submitted by the contractor.
The submittal process is in place to allow the Government the opportunity to determine whether materials or procedures used by the contractor are in accordance with contract requirements. It is ultimately the Contractor's responsibility via the quality control process to ensure submittal items installed under the contract and work performed on site are in accordance with industry standards and general practices.
(a) The types of submittal requirements specified in this contract may include, but is not limited to; shop drawings, product data, samples, certificates of conformance or compliance, certified test or inspection reports, equipment, materials, and miscellaneous work related submittals for construction.
Individual submittal requirements are generally specified in applicable sections for each unit of work in the specifications and/or as a whole in one section in the statement of work.
(b) The Bureau of Prisons (BOP) Contracting Officer’s Representative (COR) shall act for the Contracting Officer in the review and acceptance of all submittals. The Contractor shall submit submittals as required by the contract/specifications to the COR for transmittal to the Contracting Officer. Fabrication of any work or purchase or use of any submittals (such as materials for which samples are required or equipment, etc.) shall not take place until written acceptance is given by the COR, except at the Contractor's own risk.
(c) The Contractor shall submit all shop drawings and submittals sufficiently in advance (unless otherwise specified in the specifications) of the construction requirements to allow ample time for checking, re-submitting, and re-checking.
(d) Failure of any materials to pass their specified tests shall be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. The
15BBNF27Q50100001 Page 7 of 55
Government reserves the right to disapprove any material or equipment which has previously proven unsatisfactory in service.
(e) The Contracting Officer’s or designee’s approval or acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work. The Contractor is responsible for delivering a final product/system that is operational as intended by the contract requirements, regardless of any Government approvals or acceptance of submittals. The Government assumes no liability during the submittal approval/ acceptance process. It is the sole responsibility of the Contractor to deliver a properly functioning product or system.
CONTRACTOR USE OF PERMISES
Work Hours
The project schedule is based on a normal forty (40) hour work week, eight (8) hours per day, Monday through Friday, excluding Federal holidays. The Contracting Officer’s Representative (COR) shall establish the work hour time frames for the duration of the project, subject to the approval of the Contracting Officer. Work hours and work days may be altered only with a 48 hour advance approval of the Contracting Officer.
NOTE: Access to the site will be available during normal working hours except during emergencies.
It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight hour day. The Government assumes no responsibility to the Contractor, nor to any of his subcontractors, for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines. The procedures and institutional entrance/exit routines applicable to this project will be explained at both the pre-bid conference/site visit and the pre-construction meeting.
Contraband
The Contractor shall inform his employees that intoxicating beverages, drugs, weapons, etc., will not be allowed on the site. Introduction of contraband shall be subject to the penalties prescribed by Title
18 USC-1791.
Explosives
The use of explosives is absolutely forbidden without written authorization from the Contracting Officer.
Parking and Temporary Office
Parking will be available at the site to the extent it does not interfere with construction activities.
Otherwise, parking shall be provided for by the Contractor, at his expense, off the site for workmen employed on the project. Any temporary field office used by the Contractor shall be located in an area approved by the COR.
Safety and Accident Prevention
In performing work under this contract the contractor shall:
(a) Conform to the specific safety requirements established by this contract;
15BBNF27Q50100001 Page 8 of 55
(b) Comply with the safety rules of the Government institution that concern related activities not directly addressed in this contract;
(c) Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and
(d) Take such additional immediate precautions as the Contracting Officer and/or COR may reasonably require for safety and accident prevention purposes.
PAYMENT SERVICES
(a) Original application for payment shall be prepared on AIA (American Institute of Architects) Form G-702 "Application and Certificate for Payment" and submitted to the Contracting Officer. The contractor may use another form; however, it shall contain similar information as the AIA Form G-702.
The Contracting Officer’s Representative (COR) will approve the amount of payment by signing.
The approved application for payment shall be forwarded as follows: Original to Accounting; Copy for Contract Award File.
(b) All small business contractors are required to self-certify on all invoices their small business status.
(c) The following information is required with each application for payment:
• Name and address of contractor
• Contract number
• Contractor invoice/application for payment number
• Description, price, and quantity of construction completed/rendered
• Payment terms (reference the contract payment clause)
• Other substantiating documentation or information required by the contract
• Name, title, and phone number of official to be notified in the event of a defective invoice
• Contractor TIN (Tax ID Number)
REQUEST FOR FINAL INSPECTION
The Contractor shall give the Contracting Officer’s Representative (COR) a minimum of ten (10) working days advanced written notice of the date on which the work will be fully completed and ready for the Government’s final inspection.
CONSTRUCTION CONTRACT SECURITY
In addition to the information contained in clause “DOJ-03 Personnel Security Requirements For Contractor Employees (Nov 2021); (Alt. I) -- Classified Information Cleared Contractors”, the following additional security is required to be completed and submitted for all contract employees who will be working under the terms of the contract:
Criminal History Check – BP-A0660 (May 2018)
CJIS Name Check Request Form
15BBNF27Q50100001 Page 9 of 55
BOP Contractor Pre-employment Questionnaire
BOP Authority for Release of Information
The contactor should be aware that the time required for contractor security clearances to be completed may vary. For the purposes of this solicitation, __35 _ calendar days [contracting officer to insert the number of days based on performance period memo] have been included in the performance period. The number of days listed above is contingent upon the contractor providing completed clearance packages for their employees within 10 calendar days of the Notice to Proceed.
For any subsequently awarded subcontract, completed security clearance packages for subcontractor workers shall be submitted in conjunction with the completed SF-1413.
**A form package will be issued by the Administrative Contracting Officer or Contracting Officer's Representative (COR) at the institution upon contract award. Completed packages shall be submitted by the PRIME CONTRACTOR ONLY to obtain clearance for each prime and sub-contract employee. Security Clearance packages will NOT be accepted from sub-contractors. Upon clearance being obtained the contractor will be notified. Should a contract employee NOT be cleared to enter the facility for this project, the contractor will be notified immediately. The contractor will be responsible to submit another contract employee as soon as possible for clearance. Be advised, the Federal Bureau of Prisons cannot disclose why an individual does not pass the security clearance process, as it is a violation of law.**
ASSIGNMENT OF CONTRACT ADMINSTRATION OFFICE AND FUNCTIONS
Pursuant to FAR 42.201 and 42.202, the assigned Contract Administration Office is listed in Block 26 of the Standard Form 1442 Back. This assignment carries with it the authority to perform all of the contract administration functions listed in FAR 42.302(a) and 42.302(b) to the extent that those functions apply to the contract.
The Contract Administration Office is required, however, to obtain written authorization from the Procuring Contracting Officer (PCO) to perform any function listed under 42.302(b). Specifically, the Administrative Contracting Officer (ACO) is required to obtain written authorization to perform the below referenced functions FOR CONSTRUCTION CONTRACT AWARDS:
(1) Negotiate or negotiate and execute supplemental agreements incorporating contractor proposals resulting from change orders issued under the Changes clause. Before completing negotiations, coordinate any delivery schedule change with the contracting office.
(2) Negotiate prices and execute priced exhibits for unpriced orders issued by the contracting officer under basic ordering agreements.
(3) Negotiate or negotiate and execute supplemental agreements changing contract delivery schedules.
(4) Complete Contractor Performance Assessment Report System (CPARS) evaluations of contractor performance in accordance with FAR Subpart 42.15.
Should any other function under FAR Subpart 42.15 not listed above be required, the ACO is required to contact the PCO for authority.
SCHEDULE OF VALUES
15BBNF27Q50100001 Page 10 of 55
The Contractor shall prepare a Schedule of Values (SOV) for the project and submit to the Contracting Officer for approval prior to submitting the first application for payment. The SOV shall be correlated with the construction schedule. The SOV shall be formatted per the Construction Specification Institute Master Format structure. The Contractor may propose an alternate organizational format to the Contracting Officer for approval.
(a) The SOV shall include:
(1) Project name, location, and contract number;
(2) Contractor’s name and address;
(3) Date of submittal.
(b) The SOV shall be arranged in a tabular form with separate columns to indicate the following for each item listed:
(1) Description of Work or Material;
(2) Related specification section, if applicable;
(3) Name of subcontractor, if applicable;
(4) Name of manufacturer or fabricator, if applicable;
(5) Name of supplier, if applicable;
(6) Change orders (modifications) that have affected value, if applicable;
(7) Dollar value;
(8) Percentage of Contract sum rounded to the nearest percent, adjusted to total 100 percent.
(c) The SOV shall breakdown the contract sum in sufficient detail to facilitate continued evaluation of applications for payment and progress reports. The contractor should separate principal subcontract amounts down into several line items.
(d) SOV amounts shall be rounded to the nearest whole dollar. The total of all SOV amounts shall equal the total contract amount.
(e) The contractor shall progress the percentage of completion, with the concurrence of the Contracting Officer’s Representative, for each value in conjunction with the preparation of each monthly application for payment. The progressed value percentages shall directly correlate to the calculated total amount due for each monthly progress payment.
(f) The SOV shall remain fixed for the duration of contract performance. Any revisions to the SOV must be requested in writing, with justification, for approval by the Contracting Officer.
PROGRESS MEETINGS
The Administrative Contracting Officer (ACO) shall conduct progress meetings at the project site on a monthly basis, or at intervals as determined by the ACO.
(a) At a minimum, the attendees shall include but is not limited to:
15BBNF27Q50100001 Page 11 of 55
(1) FBOP: Administrative Contracting Officer, Contracting Officer’s Representative (COR), Facility Administrator/Manager, Architect/Engineer (if applicable), Other Personnel (Executive Staff, Captain, Safety Manager, etc.).
(2) Contractor: Project Manager, Superintendent, and technical support disciplines as appropriate (Subcontractors, Manufacturers, Suppliers, etc.).
(b) The meeting should include, but is not limited to issues such as:
Administrative Contracting Officer:
(1) Old business from previous progress meeting(s);
(2) Status of modifications, certified payrolls, submittals, requests for information (RFI);
(3) Review of payments made to date and review/approve current payment request;
(4) Status of modification proposal requests;
(5) Discuss new business.
COR:
(1) Status of escort coverage;
(2) Review gate or sallyport entrance/exit issues;
(3) Discuss other delays contractor may be experiencing;
(4) Discuss performance/quality issues.
Contractor:
(1) Review/discuss updated progress schedule;
(2) Provide 30 day outlook;
(3) Discuss other issues affecting performance.
CONTRACT CLOSEOUT PROCEDURES (FOR CONSTRUCTION CONTRACTS EXCEEDING THE
SAT)
Contract Closeout must be completed within six (6) months of physical completion of the work.
Prior to payment of final invoice:
The contractor shall submit the following documents:
(1) Contractor’s Affidavit of Release of Liens (AIA Document G706A);
(2) Contractor’s Affidavit of Payment of Debts and Claims (AIA Document G706);
(3) All as-built drawings/shop drawings, if applicable;
(4) Contractor’s final invoice;
(5) Release of Claims (GSA Form 1142);
(6) Consent of Surety to Final Payment (AIA Document G707);
(7) Letter establishing warranty dates;
15BBNF27Q50100001 Page 12 of 55
(8) Complete list of subcontractors with telephone numbers and points of contact;
(9) Guarantees and warranties;
(10) All balance and test reports;
(11) All operation/maintenance manuals;
(12) All permits and certifications.
AIA forms can be obtained from The American Institute of Architects at www.aiabookstore.com.
GSA forms can be obtained from the General Services Administration at www.gsa.gov (click on the “Forms Library” link).
CHANGES
(a) Changes will be in accordance with the Changes clause 52.243-4 or Changes and Changed Conditions clause 52.243-5 whichever applies to this contract.
(b) When changes are made in the work that requires an equitable adjustment to the contract, the Contractor shall submit to the Contracting Officer, through the Contracting Officer’s Representative (COR), a written proposal for adjustment of the amount of increase or decrease. With the proposal, the Contractor shall submit an itemized breakdown in at least the following detail:
(1) Material quantities and unit cost
(2) Labor costs by material item
(3) Construction equipment cost
(4) Workmen's compensation and public liability insurance
(5) Overhead
(6) Profit or commission
(7) Employment taxes (FICA and FUTA)
(c) The maximum allowable overhead, profit and commission percentages are contained below.
The percentages for overhead, profit and commission shall be negotiated and may vary according to the nature, extent and complexity of the work involved, but in no case shall exceed the following:
(1) To the Contractor, on work performed by other than his own forces. The commission is 10% in the first $20,000, 7 1/2% on the next $30,000, 5% on the balance over $50,000.
(2) To the Contractor, and/or the Subcontractors for that portion of the work performed with their respective forces. The commission is 10% overhead and 10% profit on the first $20,000, 7 1/2% overhead and 7 1/2% profit on the next $30,000, and 5% overhead and 5% profit on the balance over $50,000.
Not more than three (3) percentages, not to exceed the maximum percentage amounts shown above, will be allowed regardless of the number of Subcontractors (i.e., the mark up on work subcontracted by the Subcontractor will be limited to the overhead percentage and one profit percentage in addition to the prime Contractor's commission percentage). On proposals covering both increases and
15BBNF27Q50100001 Page 13 of 55 decreases in the amount of the contract, overhead, profit and commission will be allowed on the net increase only.
(d) When certified cost or pricing data are required under FAR 15.403-4 for proposals over $2,000,000, the cost or pricing data shall be submitted in accordance with FAR 15.408, Table 15-2.
No itemized breakdown will be required for proposals amounting to less than $1,000.
(e) When the necessity to proceed with a change does not allow sufficient time to negotiate a modification or because of failure to reach an agreement, the Contracting Officer may issue a change order instructing the contractor to proceed on the basis of a tentative price based on the best estimate available at the time, with the firm price to be determined later. Furthermore, when the change order is issued, the contractor shall submit a proposal for cost of changes in work within 30 calendar days.
(f) The Contracting Officer will consider issuing a settlement by determination to the contract, if the contractor's proposal required by paragraphs (a) and (b) of this clause is not received within 30 calendar days, or if agreement has not been reached.
(g) Where a change involves credit items only, a proper measure of the amount of downward adjustment in the contract price is the reasonable cost to the contractor if he/she had performed the deleted work. A reasonable allowance for overhead and profit are properly includable as part of the downward adjustment for a deductive change. The amount of such allowance is subject to negotiation.
(h) Overhead and contractor's fee percentages shall be considered to include insurance other than mentioned herein, field and office supervisors and assistants, security police, use of small tools, incidental job burdens, and general home office expenses and no separate allowance will be made therefor. Assistants to office supervisors include all clerical, stenographic and general office help. Incidental job burdens include, but are not necessarily limited to, office equipment and supplies, temporary toilets, telephone and conformance to OSHA requirements. Items such as, but not necessarily limited to, review and coordination, estimating and expediting relative to contract changes are associated with field and office supervision and are considered to be included in the contractor's overhead and/or fee percentage.
(i) The Contractor shall submit with his proposal a request for time extension, if applicable.
(j) The COR shall review the proposal and check estimates in detail, utilizing unit prices where specified or agreed upon. If they are in agreement, the COR shall forward the proposal to the Contracting Officer. The Contracting Officer will forward copies to the Architect-Engineer (if applicable) and the Regional Project Manager for their review and recommendations. After their review, the Architect-Engineer and Project Manager will forward their comments to the Contracting Officer.
(k) If the Contracting Officer determines that an equitable adjustment is to be made, the contract shall be modified in writing utilizing the prescribed Standard Form 30 (Amendment of Solicitation/ Modification of Contract)(SF-30). After the SF-30 has been signed by the Contractor and executed by the Contracting Officer, distribution shall be made as follows:
(1) Original: Contract file
(2) Copy to: Contractor
Regional Project Manager
Contracting Officer’s Representative (COR)
15BBNF27Q50100001 Page 14 of 55
Architect-Engineer Firm (if applicable)
Accounting Supervisor
Contracting Officer
EQUITABLE ADJUSTMENTS: WAIVER AND RELEASE OF CLAIMS
(a) When the Contractor, after receipt of notification of a change made pursuant to the clause of this contract entitled "Changes" or after affirmation of constructive change thereunder, submits any claim for equitable adjustment under this clause, such claim shall include all types of adjustments in the total amounts to which that clause entitles the Contractor, including but not limited to adjustments arising out of delays or disruptions or both caused by such change. Except as the parties may otherwise expressly agree, the Contractor shall be deemed to have waived (i) any adjustments to which it otherwise might be entitled under the aforesaid clause where such claim fails to request such adjustment, and (ii) any increase in the amount of equitable adjustments additional to those requested in its claim.
(b) Further, the Contractor agrees that, if required by the Contracting Officer, it will execute a release, in form and substance satisfactory to the Contracting Officer, as part of the supplemental agreement setting forth the aforesaid adjustment, and that such release shall discharge the Government, its officers, agents, and employees, from any further claims, including but not limited, to further claims arising out of delays or disruptions or both caused by the aforesaid change.
PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS
a. Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.
a. Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
1. The Contractor’s request for progress payments shall include the following substantiation:
1.
i. An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
ii. A listing of the amount included for work performed by each subcontractor under the contract.
iii. A listing of the total amount of each subcontract under the contract.
iv. A listing of the amounts previously paid to each such subcontractor under the contract.
v. Additional supporting data in a form and detail required by the Contracting Officer.
1. In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if-
i. Consideration is specifically authorized by this contract; and
ii. The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.
a. Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)
(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that-
1. The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
2. All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
15BBNF27Q50100001 Page 15 of 55
3. This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
4. This certification is not to be construed as final acceptance of a subcontractor’s performance.
__________________________________________________ (Name)
__________________________________________________ (Title)
__________________________________________________ (Date)
(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-
1. Notify the Contracting Officer of such performance deficiency; and
2. Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until-
i. The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected;
or
ii. The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved.
When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds.
Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-
1. Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
2. Waiving the right of the Government to require the fulfillment of all of the terms of the contract.
(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
(h) Final payment. The Government shall pay the amount due the Contractor under this contract after-
1. Completion and acceptance of all work;
15BBNF27Q50100001 Page 16 of 55
2. Presentation of a properly executed voucher; and
3. Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor’s claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 ( 31 U.S.C.3727 and 41 U.S.C. 6305).
(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions.
A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
(j) Interest computation on unearned amounts. In accordance with 31 U.S.C. 3903(c)(1), the amount payable under paragraph (d)(2) of this clause shall be-
1. Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and
2. Deducted from the next available payment to the Contractor.
15BBNF27Q50100001 Page 17 of 55
Section 3 - Special Contract Requirements
Clauses By Reference
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov
Clause Title Fill-ins (if applicable)
2852.222-70 Domestic Violence, Sexual Assault, and Stalking (DEC
2014)
Clauses By Full Text
DOJ-05 Security of Department Information and Systems (APR 2026)
I. Applicability to Contractors and Subcontractors Section 2839.102 of the Justice Acquisition Regulation (JAR), (48 C.F.R. § 2839.102), applies to this contract.
Accordingly, all contractors are obligated to comply with all applicable DOJ security policies, directives, or guidance documents, including the security requirements in the provisions in this contract clause. This contract clause applies to all contractors and subcontractors, including cloud service providers (“CSPs”), and personnel of the contractors and subcontractors (hereinafter collectively, “Contractor”) that may access, collect, store, process, maintain, use, share, retrieve, disseminate, transmit, or dispose of DOJ Information. The security requirements set forth herein are in addition to those required by the Federal Acquisition Regulation (“FAR”), and any other applicable laws, mandates, contract clauses, DOJ policies, directives or guidance documents and Executive Orders pertaining to the development and operation of Information Systems and/or the protection of Government Information. This clause does not alter or diminish any existing rights, obligations, or liability under any other civil and/or criminal law, rule, regulation, or mandate.
II. General Definitions The following general definitions apply to this clause. Specific definitions also apply as set forth in other paragraphs.
A. Authorization to Operate (“ATO”), as defined in National Institute of Standards and Technology (“NIST”) Special Publication (“SP”) 800-37 Revision 2, is the official management decision given by a senior Federal official or officials to authorize operation of an information system and to explicitly accept the risk to agency operations (including mission, functions, image, or reputation), agency assets, individuals, other organizations, and the Nation based on the implementation of an agreed-upon set of security and privacy controls.
B. Cloud Computing, as defined in DOJ Order 0904 Cybersecurity Program, is a model for enabling ubiquitous, convenient, on-demand network access to a shared pool of configurable computing resources (e.g., networks, servers, storage, applications, and services) that can be rapidly provisioned and released with minimal management effort or service provider interaction. This cloud model is composed of five essential characteristics, three service models, and four deployment models in accordance with NIST SP 800-145.
C. Covered Contract is any contract, order or other agreement under which the contractor, or a subcontractor at any tier, including a cloud service provider, may access, collect, store, process, maintain, use, share, retrieve, 15BBNF27Q50100001 Page 18 of 55 disseminate, transmit, or dispose of DOJ Information (as defined below) in the course of providing a product or service to the Department, with the exception of acquisitions under the micro-purchase threshold.
D. Covered Information System means any information system used for, involved with, or allowing, the processing, storing, or transmitting of DOJ Information under a Covered Contract.
E. Data means recorded information, regardless of form or the media on which it may be recorded. The term includes technical data, computer software, and personally identifiable information (PII) (defined below). The term does not include information incidental to contract administration, such as financial, administrative, cost or pricing, or management information.
F. DOJ Information, as defined in DOJ Order 0904, means any Information that is owned, produced, controlled, protected by, or otherwise within the custody or responsibility of the DOJ, including, without limitation, information related to DOJ programs or personnel. It includes, without limitation, Information (1) provided by or generated for the DOJ, (2) managed or acquired by the Contractor for the DOJ in connection with the performance of the contract, and/or (3) acquired to perform the contract.
G. Information, as defined in DOJ Order 0904, is any communication or representation of knowledge such as facts, data, or opinions, in any form or medium, including textual, numerical, graphic, cartographic, narrative, or audiovisual. This includes any communication or representation of knowledge in an electronic format that allows it to be stored, retrieved, or transmitted.
H. Information System, means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502(8)).
I. Personally Identifiable Information (“PII”), as defined in the FAR 24.101, means information that can be used to distinguish or trace an individual's identity, either alone or when combined with other information that is linked or linkable to a specific individual. It includes but is not limited to common data elements such as names, addresses, dates of birth, and places of employment, to identity documents, Social Security numbers or other government-issued identifiers, precise location information, medical history, and biometric records. This definition covers all PII that is created by or becomes available to the contractor, including its employees, subcontractors, or affiliates, as a result of performing under this contract. PII, as supplementally defined in DOJ Order 0904, also includes information about an individual maintained by an agency, including, but not limited to, information related to education, financial transactions, medical history, and criminal or employment history and information, which can be used to distinguish or trace an individual’s identity.
J. Private Cloud, as defined in NIST SP 800-145, is the deployment model for cloud infrastructure provisioned for exclusive use by a single organization comprising multiple consumers (e.g., business units). It may be owned, managed, and operated by the organization, a third party, or some combination of them, and it may exist on or off premises.
K. Security Breach means any security incident (as defined below) that directly relates to the loss of control, compromise, exfiltration, manipulation, unauthorized disclosure, unauthorized acquisition, unauthorized exposure or unauthorized access or any similar occurrence of any Covered Information System or any DOJ Information or any PII accessed by, retrievable from, processed by, stored on, or transmitted within, to or from any such system. This includes incidents where (1) a person other than an authorized user accesses or potentially accesses PII or DOJ Information or (2) an authorized user accesses or potentially accesses PII or DOJ Information for an unauthorized purpose.
a. Potential Security Breach (hereinafter, “Potential Breach”) means any suspected, but unconfirmed security breach (as defined above).
b. Confirmed Security Breach (hereinafter, “Confirmed Breach”) means any confirmed security breach (as defined above).
L. Security Incident means any occurrence that (1) may actually or imminently jeopardize, without lawful authority, the availability, integrity, authentication, confidentiality, or nonrepudiation of DOJ Information or a Covered Information System; or (2) may constitute a violation or imminent threat of violation of law, security policies, security procedures, or acceptable use policies.
a. Potential Security Incident means any suspected, but unconfirmed security incident (as defined above).
b. Confirmed Security Incident means any confirmed security incident (as defined above).
15BBNF27Q50100001 Page 19 of 55
M. Vulnerability, as defined in DOJ Vulnerability Management Plan, and the OCIO Information Security Management Procedure, means a weakness or flaw discovered in the design of a system that, when exploited, may result in a loss of confidentially, integrity, or availability of DOJ Information or an Information System.
III. Confidentiality and Non-Disclosure of DOJ Information A. Preliminary and final contract deliverables and all associated working papers and material generated by the Contractor developed using DOJ Information, product, source code, and/or methods of operations, are the property of…