About this file
This Solicitation Development Form for a Construction/IFB (Invitation for Bid) is issued by the City of St. Petersburg, Florida, involving a storm drainage infrastructure improvement project. The project, designated as Project No. 19045-110, involves installing a new stormwater conveyance system along 7th Street North and 50th Avenue North, with major components including approximately 1,100 linear feet of 66" reinforced concrete pipe (RCP), 1,400 linear feet of additional RCP in varying sizes (18"–54"), and 165 linear feet of 8'x5' concrete box culvert. The work encompasses roadway and sidewalk reconstruction, including new curbs, pavement, traffic signage, and striping, plus installation of pre-manufactured "Hydroplanter" systems for water quality treatment. The contract requires substantial completion within 365 calendar days after the Notice to Proceed, with a total of 30 additional calendar days for final completion.
The project has a budget of $6,300,000 and is funded through multiple sources including CoSP, SWFWMD, and FEMA/FDEM. Bidders must meet strict pre-qualification requirements, including having completed a minimum of three projects in the past five years that meet specific criteria: two projects involving large-diameter stormwater infrastructure and urban/residential roadway reconstruction, one project for a government agency, and each project valued over $5,000,000. The solicitation allows up to 75% of work to be subcontracted and requires compliance with environmental permitting from Southwest Florida Water Management District, U.S. Army Corps of Engineers, and Pinellas County Water and Navigation Control Authority. Insurance requirements and background checks for Parks & Recreation are specified, with the bid acceptance period set at 90 days after bid closing.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rev: 6/23/25
Solicitation Development Form - Construction / IFB
Project No./Project Title 19045-110 - 7th St N, 50th Ave N and Vicinity Storm Drainage Improvements Part 1
Type of Solicitation Sealed Bid Light Construction
For ECID use only Yes No
OpenGov Followers: David Ojeda and Christy Carlton Routing Council Items and Related Questions:
David Ojeda, Roger Johnson, Sarah Johnson, Brejesh Prayman, Janice MacKinnon OpenGov Approvers: Roger Johnson and Brejesh Prayman
Charge Account 16711.19045-110.03.06.81964.4013 Budget $ 6,300,000
Funding Source / Grant Info, if known CoSP, SWFWMD, FEMA/FDEM Acceptance Period 90 Days, after bid closes
Background Checks Parks & Rec Police Port WRD
Class Item Commodity Description
958.26 Construction Management Services
913-50-82 Surface Course, Bituminous Concrete Class I
913-82-75 Removal and/or Replacement of Existing Sidewalks
210-07-00 Basins, Catch, Including Accessories and Parts
913-60-03 Construction of Drainage Piping
Insurance Requirements:
See General Conditions Article G-54 for Standard Limits.
See Supplement General Conditions if changes in limits or additional coverage are required.
Commercial General Liability Change in Limits? Yes No
Builders Risk Insurance Change in Limits? Yes No
Commercial Auto
Change in Limits? Yes No
Pollution/Environmental Liability
Change in Limits? Yes No
Workers Compensation
Change in Limits? Yes No
Professional Liability
Change in Limits? Yes No
US Longshore & Harbor Worker's Act
Change in Limits? Yes No
Other:
Pre-bid meeting required? Yes No
Trench Act required? Yes No
Percentage of Work that may be Subcontracted: 75%
Scope of Work: This project includes the installation of a new stormwater conveyance system along 7th Street North and 50th Avenue North in St. Petersburg, Florida. Major components include approximately 1,100 LF of 66" reinforced concrete pipe (RCP), 1,400± LF of additional RCP in varying sizes (18"–54"), and 165± LF of 8'x5' concrete box culvert to improve drainage capacity. The work also includes roadway and sidewalk reconstruction—new curbs, pavement, traffic signage, and striping—and the installation of pre-manufactured “Hydroplanter” systems for water quality treatment. All work must comply with applicable environmental and
Rev: 6/23/25 permitting requirements from the Southwest Florida Water Management District (SWFWMD), U.S. Army Corps of Engineers, and the Pinellas County Water and Navigation Control Authority. Restoration work will follow utility installation and must be performed in accordance with City of St. Petersburg standards.
Contractor Pre-Qualifications: The Bidder is hereby advised that the City will only accept bids from qualified Contractors who have successfully completed a minimum of three (3) projects in the five (5) years preceding the advertisement for this Solicitation, and whose project superintendent has also successfully completed a minimum of three (3) projects in the five (5) years preceding the advertisement for this Solicitation, in which each of the projects meet or exceed the following qualification requirements:
A. Two (2) projects must include:
• Installation of large-diameter stormwater infrastructure (including RCP 36" or greater and/or box culverts).
• Associated roadway and sidewalk reconstruction within an urban/residential corridor.
B. One (1) project must include:
• Construction of similar size and scope for a government agency
C. Each of the three (3) projects must have a construction and/or renovation value in excess of $5,000,000
Failure to demonstrate compliance to the above requirements will render the Bid non-responsive.
Contract Completion Time: Contractor shall commence the Work within ten (10) calendar days after the City issues the Notice to Proceed. After issuance of the Notice to Proceed, the Contractor shall:
• Reach Substantial Completion of all Work within three hundred sixty five (365) calendar days, and
• Reach Final Completion within thirty (30) calendar days after the City’s delivery of the punch list.
Special Instructions:
Attachments
Insurance Requirements Checklist Contract Specifications
Bidder Security and Bidder Information Contract Plans
Florida Trench Act Other:
Pay Items – Price Page
Draft Agreement, Public Construction Bond, and additional Compliance forms will be provided by Procurement.