The provided document is a Construction Daily Report/Log template. It includes fields for recording daily construction activities, work performed, safety information, equipment used, and other pertinent details for a construction project.
The related federal contract opportunity is for the modernization of passenger and service elevators at the John M. Shaw U.S. Courthouse in Lafayette, Louisiana. The procurement is a 100% small business set-aside with an estimated construction cost between $1,000,000 and $5,000,000. The applicable NAICS code is 238290 Other Building Equipment. The solicitation will be issued via a Request for Proposal (RFP) using the best value trade-off source selection method. A site visit is scheduled for May 16, 2024, and the solicitation closing date is June 11, 2024. The solicitation and all related information will be electronically posted on the SAM.gov website.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION DAILY REPORT/LOG
Construction Daily Log Date:
Contract Number: Title & Location: Report Number:
Contractor: Superintendent:
AM Weather: PM Weather: Max Temp (F): Min Temp (F):
Work Performed Today
Schedule Activity #
Work Location & Description Employer Number Trade Hrs
Job Safety Was Job Safety/Toolbox Mtg held this Date? (If yes attach copy of the mtg minutes)
Yes No Total Work Hrs on Job site, this date, include con’t sheets
Were there any lost time accidents this date?
Yes No
Was Crane/Manlift/Trenching/Scaffold/HV ELEC/High Work/Hazmat Work Done?
Yes No Cum total of work hrs from previous report
Superintendent on site: Yes No
Was Hazardous Material/Waste Released into the environment? (If yes attach description of incident and proposed action)
Yes No QC Manager on site: Yes No
Safety Manager on site: Yes No
Schedule Activity #
List Safety Actions Taken Today/Safety Inspections Conducted
Safety Req’ts have been met
Yes No
Equipment/material received today to be incorporated in job (indicate schedule activity number)
Schedule Activity #
Submittal # Description of Equipment/Material Received
Attachment 6
Construction and plant equipment on the job site today. Indicate hours used and schedule activity number.
Schedule Activity #
Owner Description of construction equipment used today (include make and model)
Schedule Activity #
Remarks/Other Information
Signature (Contractor/Superintendent & Company Name): Date: