SOLICITATION 2026.16 ITB Effluent Discharge System - Pipeline - Pump Station - Sprayfield 2.pdf

PDF 499 KB Posted

Attached to
Effluent Discharge System Pipeline – Pump Station – Sprayfield 2
Solicitation number
2026.16
Issued by
Santa Rosa County, Florida

About this file

Summary

This Invitation to Bid (ITB) No. 2026.16, issued by the City of Milton, Florida, solicits sealed bids from qualified and properly licensed contractors to construct an Effluent Discharge System comprising three segments: an Effluent Pipeline consisting of approximately 35,430 linear feet of 20-inch SDR 26 PVC pipe with associated valves and fittings connecting the Downtown Plant Pump Station to the Effluent Pump Station; an Effluent Pump Station featuring a pre-cast concrete building, triplex pumping station, 7.5-million-gallon wet-lined wet-weather storage pond, splitter box, yard piping, fencing, and electrical components; and Sprayfield Site 2 with piping, fittings, valves, and sprinkler assemblies. The project is located in Santa Rosa County. The pre-bid conference is mandatory on November 19, 2026, at 10:00 a.m. CST, with a mandatory site visit following the conference. Written questions are due by December 3, 2026, at 2:00 p.m. CST, with answers posted by December 10, 2026. Bids must be submitted by December 17, 2026, at 10:00 a.m. CST to Milton City Hall. Substantial Completion is required within 510 calendar days and Final Completion within 570 calendar days after issuance of the Notice to Proceed. Liquidated damages are assessed at $2,700 per calendar day for delays beyond the completion deadlines.

The contract is issued on a unit price basis with payment based on actual quantities of work performed and accepted by the City. Bidders must submit a bid bond equal to five percent of the total bid amount. The successful bidder must provide Performance and Payment Bonds in an amount equal to 100 percent of the contract price in accordance with Florida Statutes Section 255.05. Minimum qualifications require the bidder to be legally authorized to conduct business in Florida, hold a current active contractor license, demonstrate successful completion of at least three similar projects within the past five years with a contract value of at least $10,000,000, provide three references, possess bonding capacity, and comply with all statutory eligibility requirements. Contract 2 is funded by a 2026 Florida Legislative Appropriation managed by the Florida Department of Environmental Protection (FDEP), which prohibits local vendor preference. Contracts 3 and 4 are not restricted by state funding and may be eligible for local vendor preference consideration. Comprehensive insurance coverage is required, including Commercial General Liability, Automobile Liability, Workers' Compensation, Umbrella Liability, Builders Risk, and Contractors' Pollution Insurance (if applicable).

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO BID (ITB)

CITY OF MILTON

MILTON, FL

BID NO 2016.16

2026.16 Effluent Discharge System

Pipeline – Pump Station – Sprayfield 2

Publish Date: Pre-Bid Conference:

11/05/2026 11/19/2026 10:00 AM (CST)

Question Due by: Answers Posted by:

12/03/2026 at 2:00 PM (CST) 12/10/2026

Submittal Deadline: Where to Deliver Bid:

12/17/2026 by 10:00 AM (CST) Milton City Hall

6738 Dixon Street

Milton, FL 32570

City of Milton

Purchasing Department

(850) 983-5480 mwilliams@miltonfl.org mailto:mwilliams@miltonfl.org

ITB No.: 2026.16

Contents

ADVERTISEMENT FOR BIDS

SECTION 1 - AUTHORITY

SECTION 2 – DEFINITIONS

SECTION 3 – GENERAL INFORMATION

SECTION 4 – SCOPE OF WORK

SECTION 5 – COMPENSATION AND PRICING

SECTION 6 – MINIMUM QUALIFICATIONS

SECTION 7 – SPECIAL REQUIREMENTS

SECTION 8 – EVALUATION AND BASIS OF AWARD

SECTION 9 – AWARD PROCESS AND CONTRACT

SECTION 10 – BID SUBMITTAL REQUIREMENTS

SECTION 11 – INSTRUCTIONS TO BIDDER

APPENDIX A

BIDDER QUALIFICATION STATEMENT

BIDDER SITE EXAM CERTIFICATION

BIDDER CERTIFICATION AND ADDENDA ACKNOWLEDGEMENT

APPENDIX B

SUBCONTRACTOR LIST

Affidavit of Compliance with Human Trafficking Laws

CERTIFICATION REGARDING NONDISCRIMINATION

CONFLICT-OF-INTEREST CERTIFICATION

DRUG-FREE WORKPLACE CERTIFICATION

E-VERIFY COMPLIANCE CERTIFICATION

NON-COLLUSION AFFIDAVIT

PROMPT PAYMENT COMPLIANCE CERTIFICATION

PUBLIC ENTITY CRIMES AFFIDAVIT

SCRUTINIZED COMPANIES CERTIFICATION

APPENDIX C

APPENDIX D

ADVERTISEMENT FOR BIDS

SECTION 1 - AUTHORITY

The City of Milton (“City”) issues this Invitation to Bid (“ITB”) as a competitive sealed bid pursuant to §255.20, Florida Statutes, and as applicable: Article VIII, Section 2(b) of the Florida Constitution; Chapter 166, Florida Statutes, including

§166.021, F.S.; Chapter 255, Florida Statutes, including §255.20, F.S.; and the City of Milton Purchasing Policy 9.0, as may be amended.

This ITB solicits sealed bids from qualified and properly licensed contractors to furnish all labor, materials, equipment, supervision, and services necessary to complete the Work described in the Contract Documents (the “Work”).

The Work constitutes public construction subject to the bidding thresholds and the payment and performance bond requirements of §255.05, F.S.

Bidders shall hold all licenses required under Chapter 489, F.S., in the appropriate classification at the time of bid submission and shall maintain such licensure throughout the term of the Contract.

Award, if made, shall be to the lowest responsive and responsible Bidder in accordance with applicable Florida law, the City’s Purchasing Policy, and the terms and conditions of this ITB. The City reserves the right to reject any or all bids, to waive minor irregularities, and to accept the bid determined to be in the best interest of the City.

SECTION 2 – DEFINITIONS

For purposes of this Invitation to Bid and the resulting Contract, the following terms shall have the meanings set forth below:

2.1 “ITB” or “Solicitation” means this Invitation to Bid and all addenda issued by the City prior to Bid opening.

2.2 “Addendum” means a written clarification, modification, or revision to the

ITB issued by the City prior to Bid opening.

2.3 “Bid” means the written offer submitted by a Bidder in response to this ITB to perform the Work described in the Contract Documents for the price(s) stated therein.

2.4 “Bidder” means a firm, partnership, corporation, or other legal entity properly licensed under Chapter 489, F.S., that submits a Bid in response to the

ITB and is legally authorized to perform public construction in the State of

Florida.

2.5 “Base Bid” means the Bidder’s stated lump sum or unit price amount for performing the Work described in the ITB exclusive of any Add Alternates.

2.6 “Add Alternate” or “Alternative Bid Item” means a separately identified portion of the Work described in the ITB for which the Bidder provides a separate price, to be added to or deducted from the Base Bid at the City’s sole discretion in determining award.

2.7 “Responsive Bid” means a Bid that conforms in all material respects to the requirements of this ITB and the Contract Documents, including submission of all required forms, pricing, acknowledgments, bonds, certifications, and other required documentation, without material deviation, reservation, or irregularity.

2.8 “Responsible Bidder” means a Bidder who has the capability, integrity, financial capacity, experience, equipment, and personnel necessary to fully perform the Contract requirements and to assure good faith performance.

2.9 “Bid Bond” means the security submitted with a Bid to guarantee that the

Bidder will enter into the Contract and furnish required Performance and

Payment Bonds if awarded.

2.10 “Performance and Payment Bonds” means the bonds required under

§255.05, F.S., to secure faithful performance of the Contract and payment to subcontractors and suppliers.

2.11 “Notice of Award” means the written notice issued by the City informing the successful Bidder that it has been selected for award of the Contract.

2.12 “Agreement” or “Contract” means the written agreement executed between the City and the successful Bidder, including all Contract Documents incorporated therein.

2.13 “City” means the City of Milton, Florida.

2.14 “Contractor” means the Bidder to whom the Contract is awarded and who executes the Agreement with the City.

2.15 “Work” means all labor, materials, equipment, supervision, services, and other items necessary to construct and complete the Project in accordance with the Contract Documents.

2.16 “Contract Documents” means the documents that form the binding agreement between the City and the Contractor, including the Agreement, this ITB and all addenda, the Bid Form, required bonds, General and

Supplementary Conditions, Technical Specifications, Drawings, Notice to

Proceed, and properly executed Change Orders.

2.17 “Contract Time” means the number of calendar days stated in the

Contract Documents within which the Work must achieve Substantial

Completion and Final Completion.

2.18 “Notice to Proceed” means the written authorization issued by the City directing the Contractor to commence the Work and establishing the

Contract Time.

2.19 “Substantial Completion” means the stage in the progress of the Work when the Work, or a designated portion thereof, is sufficiently complete in accordance with the Contract Documents so that the City can occupy or utilize the Work for its intended purpose.

2.20 “Final Completion” means the point at which the Work has been fully completed in accordance with the Contract Documents, all punch list items have been corrected, all required closeout documentation has been submitted and accepted, and the City has issued written final acceptance.

2.21 “Liquidated Damages” means the predetermined amount stated in the

Contract Documents that the Contractor shall pay to the City for each

Calendar Day the Work remains incomplete beyond the time required for

Substantial Completion or Final Completion, as applicable, representing the parties’ reasonable estimate of damages that would be difficult to ascertain at the time of contracting.

2.22 “Unit Price” means the price stated in the Bid for a single unit of Work, including all labor, materials, equipment, overhead, and profit necessary to complete that unit of Work as specified.

2.23 “Lump Sum” means a single fixed price stated in the Bid for completion of a defined portion of the Work, regardless of the actual quantities required, except as adjusted by Change Order.

2.24 “Change Order” means a written amendment to the Contract executed by the City and the Contractor authorizing a change in the Work, Contract

Price, Contract Time, or any combination thereof.

2.25 “Field Order” means a written order issued by the City or Engineer that clarifies or interprets the Contract Documents or orders minor changes in the

Work that do not change the Contract Price or Contract Time.

2.26 “Subcontractor” means an individual or entity having a direct contract with the Contractor to perform a portion of the Work at the Project site.

2.27 “Engineer” means the professional engineer or engineering firm identified in the Contract Documents that prepared the plans and specifications for the

Project and may provide technical review, inspections, or recommendations regarding the Work. The Engineer is not the Contract Administrator and does not have authority to modify the Contract unless expressly authorized in writing by the City.

2.28 “Calendar Day” means every day shown on the calendar, including weekends and legal holidays.

2.29 “Business Day” means any day other than a Saturday, Sunday, or legal holiday observed by the City of Milton.

SECTION 3 – GENERAL INFORMATION

3.1 Solicitation Overview

The City is soliciting sealed bids from qualified and properly licensed contractors to furnish all labor, materials, equipment, supervision, and services necessary to construct the project described in the Contract Documents (the “Project”).

The Project contains 3 separate segments:

• Effluent Pipeline, consisting of approximately 35,430 linear feet of 20-inch

SDR 26, PVC Pipe, gate valves, air relief valves, tees and fittings for a complete and operational system connecting flow from the Downtown

Plant Pump Station to the Effluent Pump Station.

• Effluent Pump Station, consisting of a pre-cast fabricated concrete building, a triplex pumping station, a 7.5 million gallon wet lined wet-weather storage pond, splitter box, yard piping, fencing, valves and fittings, electrical components, conduit, and wiring system for a complete and operational effluent pump station.

• Sprayfield Site 2, consisting of piping, fittings, valves and sprinkler assemblies and all appurtenances for a complete and operational system.

3.2 Issuing Office

This solicitation is issued by the City of Milton, Florida Purchasing Division.

All communications regarding this ITB shall be directed only to the designated

Procurement Contact identified below in §3.3.

3.3 Administrative Details and Dates

Bid No.: 2026.16

Bid Title:

2026.16 Effluent Discharge System

Pipeline – Pump Station – Sprayfield 2

Date of Issuance: 11/05/2026

Project Description and Scope of Work: • Effluent Pipeline, consisting of approximately 35,430 linear feet of

20-inch SDR 26, PVC Pipe, gate valves, air relief valves, tees and fittings for a complete and operational system connecting flow from the Downtown Plant Pump

Station to the Effluent Pump Station.

• Effluent Pump Station, consisting of a pre-cast fabricated concrete building, a triplex pumping station, a

7.5 million gallon wet lined wet-weather storage pond, splitter box, yard piping, fencing, valves and fittings, electrical components, conduit, and wiring system for a complete and operational effluent pump station.

• Sprayfield Site 2, consisting of piping, fittings, valves and sprinkler assemblies and all appurtenances for a complete and operational system.

Project Location: Santa Rosa County

Procurement Contact: Name: Michele Williams

Phone: (850) 983-5480

Email: mwilliams@miltonfl.org

Engineer: Donovan-Hill Group

Pre-Bid Conference:

Pre-Bid Conference is Mandatory.

Date: 11/19/2026

Time: 10:00 am

Location: Milton City Hall

Reference: Instructions to Bidder: Section 11

(Pre-Bid Conference)

Written Questions Due By: 12/03/2026

Bid Submittal Deadline: 12/17/2026 by 10:00 am

Site Visit: Date: 11/19/2026 mailto:mwilliams@miltonfl.org

Site Visit will be Mandatory.

Time: Following the Pre-Bid Conference

Location: Santa Rosa County

If applicable, the site inspection form included herein must be signed and submitted with bids. Bids received from

Bidders not submitting the mandatory site inspection form will be considered non-responsive and will be rejected.

Reference: Instructions to Bidder: Section 11

(Examination of Solicitation Documents and

Site)

3.4 Addenda

All changes shall be issued by written addendum. Verbal statements are not binding. Bidders are responsible for acknowledging receipt of all addenda in the Bid Form.

3.5 Bid Validity

Bids shall remain valid for ninety (90) calendar days after bid opening, unless extended by mutual written agreement of the parties.

3.6 Communications Restrictions

From the date of advertisement of this Solicitation until the City issues a Notice of

Award, or otherwise withdraws, all communications regarding this Solicitation shall be directed solely to the Procurement Contact identified in §3.3.

Violation of this provision may result in the Bid being deemed non-responsive or the Bidder being determined non-responsible, if the City determines that such contact has resulted in an unfair competitive advantage or otherwise compromised the integrity of the procurement process.

3.7 Form of Agreement

Sample Form. The form of Construction Services Contract attached to this ITB as

Appendix C - "Form of Agreement", shows the general terms and conditions the

City intends to use for the resulting contract. It is provided for informational purposes and is not an offer by the City.

Reserved Modifications. Before execution, the City reserves the right to revise the

Form of Agreement to:

• Complete blanks, exhibits, and project-specific information, including

Contract Price, Contract Times, liquidated damages, and the awarded

Bidder's information;

• Incorporate any addenda issued under this ITB;

• Incorporate provisions required by any State or Federal funding agency, grant agreement, or loan agreement applicable to the Project;

• Conform to Applicable Laws, including changes in law taking effect before execution;

• Incorporate requirements of the City Attorney, City Manager, or City

Council as a condition of approval; and

• Make non-material clarifications, corrections, and conforming changes.

No Material Change to Bid Basis. No revision under subsection (b) shall materially change the scope of Work, the bid pricing, or the allocation of risk on which bids were submitted, except by mutual written agreement with the awarded Bidder or as required by law or by a funding agency.

Bidder's Acceptance. By submitting a bid, the Bidder agrees to execute a contract substantially in the form of the Form of Agreement, as revised under this

Section.

3.8 No Negotiation

This is a competitive sealed bid. Except as permitted by law, the City shall not negotiate price with the lowest responsive and responsible Bidder.

SECTION 4 – SCOPE OF WORK

4.1 Scope of Work

The Project will require a qualified and properly licensed contractor to furnish all labor, materials, equipment, supervision, and services necessary to construct the project described in the Contract Documents (the “Project”).

The Scope of Work contains 3 separate segments:

• Effluent Pipeline, consisting of approximately 35,430 linear feet of 20-inch

SDR 26, PVC Pipe, gate valves, air relief valves, tees and fittings for a complete and operational system connecting flow from the Downtown

Plant Pump Station to the Effluent Pump Station.

• Effluent Pump Station, consisting of a pre-cast fabricated concrete building, a triplex pumping station, a 7.5 million gallon wet lined wet-weather storage pond, splitter box, yard piping, fencing, valves and fittings, and electrical components, conduit, and wiring system for a complete and operational effluent pump station.

• Sprayfield Site 2, consisting of piping, fittings, valves and sprinkler assemblies and all appurtenances for a complete and operational system.

The complete plans and technical specifications are set forth in the Engineer’s

Plans and Technical Specifications.

4.2 Work Included

The Contractor shall provide all labor, materials, equipment, tools, supervision, transportation, permits, testing, and incidentals necessary to fully complete the

Work in accordance with the Contract Documents, whether or not specifically enumerated, as required for a complete and operational project.

4.3 Plans and Specifications

The Work shall be performed in strict accordance with the plans, drawings, technical specifications, and other Contract Documents issued with this ITB, including any addenda. The complete plans and technical specifications are set forth in the Engineer’s Plans and Technical Specifications.

In the event of a conflict among Contract Documents, the order of precedence set forth in the Agreement shall govern.

4.4 Permits and Regulatory Compliance

Unless otherwise expressly stated in the Contract Documents, the Contractor shall obtain and pay for all permits, inspections, and approvals required for the performance of the Work and shall comply with all applicable federal, state, and local laws, codes, ordinances, and regulations.

4.5 Safety and Worksite Conditions

The Contractor shall be solely responsible for initiating, maintaining, and supervising all safety precautions and programs in connection with the Work and shall comply with all applicable occupational safety and health requirements.

The Contractor shall maintain the Project site in a safe condition and take all necessary precautions to protect persons and property.

4.6 Standards of Performance

All Work shall be performed in a good and workmanlike manner, consistent with industry standards and in accordance with the Contract Documents.

Materials and equipment incorporated into the Work shall be new and of suitable quality unless otherwise specified.

4.7 Supervision

The Contractor shall designate a competent on-site superintendent authorized to act on behalf of the Contractor and shall maintain adequate supervision of the Work at all times during performance.

4.8 Work Hours

Work shall be performed during the hours of:

7:00am – 4:30pm

Work outside of permitted hours may require prior written approval from the City.

4.9 Protection of Property and Coordination

The Contractor shall protect existing facilities, utilities, public and private property, and adjacent improvements from damage arising from the performance of the Work.

The Contractor shall coordinate the Work with the City, utility providers, and other contractors as necessary to ensure orderly and timely completion of the

Project.

4.10 Unauthorized Work

The Contractor shall not perform any work beyond the scope of the Contract

Documents without prior written authorization from the City. The City shall not be responsible for payment for unauthorized work.

SECTION 5 – COMPENSATION AND PRICING

5.1 Contract Price

This Solicitation is issued on a Unit Price basis, as identified in the Bid Form.

If issued on a Unit Price basis, payment shall be based on actual quantities of

Work performed and accepted by the City at the Unit Prices submitted in the

Bid Form. Any quantities listed in the Bid Schedule are estimated for evaluation purposes only and are not guaranteed.

If issued on a Lump Sum basis, the Contract Sum shall be the Base Bid amount, as adjusted by any Add Alternates accepted by the City and any approved

Change Orders.

Add Alternates, if accepted by the City, shall be incorporated into the Contract

Sum at the prices stated in the Bid Form.

5.2 Bid Quantities

Where the Bid includes estimated quantities for unit price items, such quantities are approximate and are provided solely for evaluation purposes. Actual quantities may increase or decrease as required for completion of the Work.

SECTION 6 – MINIMUM QUALIFICATIONS

6.1 Minimum Requirements

☒ Shall Apply.

To be considered for award, the Bidder must meet the following minimum qualifications at the time of Bid submission:

1. Legal Authorization

The Bidder must be legally authorized to conduct business in the State of

Florida.

2. Licensure

The Bidder must hold a current and active contractor license issued pursuant to Chapter 489, Florida Statutes, in the classification required for the Work described in this ITB.

The license must be active and in good standing at the time of Bid submission and shall remain active throughout the duration of the

Contract. The City reserves the right to verify licensure status.

3. Experience

The Bidder must have successfully completed at least three (3) projects of similar size, scope, and complexity within the past five (5) years.

For purposes of this requirement, "similar" means projects involving construction of a wastewater effluent disposal system with a contract value of at least $10,000,000.00.

4. References

The Bidder must provide a minimum of three (3) references for comparable projects performed within the past five (5) years. Each reference shall include the project name, location, description of work performed, contract value, and owner contact information.

5. Bonding Capacity

The Bidder must be capable of providing Performance and Payment

Bonds in the full amount of the Contract Price in accordance with

§255.05, Florida Statutes.

6. Insurance Capability

The Bidder must be capable of obtaining and maintaining the insurance coverage required in Section 7 of this ITB and the resulting Contract.

7. Statutory Eligibility

The Bidder must not be disqualified from public contracting pursuant to

§§287.133–287.135, Florida Statutes, and must comply with §448.095, Florida Statutes.

Failure to meet any of the above minimum qualifications may result in the Bidder being determined non-responsible and ineligible for award.

SECTION 7 – SPECIAL REQUIREMENTS

7.1 Business Tax Receipts

☒ Shall Apply.

The successful Bidder shall obtain all required business tax receipts or local occupational licenses required to perform the work within the City prior to issuance of a Purchase Order or execution of the Contract, as applicable.

Submission with the Bid is not required.

7.2 Insurance

☒ Shall Apply.

The successful Bidder shall obtain and maintain, at its own expense, the minimum insurance coverages and limits specified in this Section 7 and shall maintain such coverage for the duration of the Contract. Proof of insurance shall be submitted to and approved by the City prior to contract execution and commencement of work.

The City shall be named as an additional insured on all required liability policies, and coverage shall be primary and non-contributory, as further detailed in the

Form of Agreement.

Minimum Insurance Coverages and Limits:

A. ☒ Commercial General Liability

Occurrence form, including bodily injury, property damage, personal and advertising injury, and products/completed operations:

• General Aggregate: $1,000,000

• Products/Completed Operations Aggregate: $1,000,000

• Each Occurrence: $1,000,000

• Personal & Advertising Injury: $1,000,000

B. ☒ Automobile Liability

Coverage for owned, non-owned, and hired vehicles with a combined single limit of not less than $1,000,000 per accident.

C. ☒ Workers’ Compensation and Employer’s Liability

Workers’ Compensation in compliance with Chapter 440, F.S.

Employer’s Liability limits not less than:

• Each Accident: $100,000

• Disease – Each Employee: $500,000

• Disease – Policy Limit: $100,000

D. ☒ Umbrella Liability

Umbrella coverage with limits of not less than $1,000,000 per occurrence, excess over required liability policies.

E. ☒ Builders Risk Insurance

Builders Risk Insurance utilizing an “All Risk” coverage form, with limits equal to the completed value of the project and no coinsurance penalty.

(City of Milton shall be named as a Loss Payee on this policy, as its interest may appear. This policy shall remain in force until acceptance of the project by the City.)

F. ☒ Contractors’ Pollution (Required if herbicides or chemicals are used)

Required if herbicides or chemical applications are performed. Minimum limits:

• $1,000,000 per occurrence

• $1,000,000 aggregate

7.3 Supplementary Conditions

Funding Source Shall Apply to Contract 2

2026 Florida Legislative Appropriation to be managed by FDEP (L0500) –

Standard Terms and Conditions and Special Project Specific Terms and

Conditions will apply and will be posted immediately upon receipt.

Funding Source Shall Not Apply to Contract 3 and Contract 4

Special Notification

If additional funding is received from state or federal sources for the performance of any Contract, the Contractor agrees to comply with all applicable funding terms, conditions, regulations, and reporting requirements. Any additional state or federal provisions added shall be incorporated into Contracts via a formal written amendments.

7.4 Bid Bond

☒ Shall Apply.

Each Bid must include Bid Security in the amount of not less than five percent

(5%) of the total Bid amount, payable to the City of Milton, Florida.

Bid Security shall be in the form of:

A Bid Bond issued by a surety authorized to conduct business in the State of

Florida and accompanied by a current and valid Power of Attorney; or

A certified check or cashier’s check drawn on an FDIC-insured financial institution.

Failure to submit acceptable Bid Security in the required form and amount at the time of Bid opening shall render the Bid non-responsive.

7.5 Bid Bond Return and Validity

Each Bid shall remain firm and shall not be withdrawn for a period of ninety (90) calendar days after Bid opening.

Bid Security of Bidders not under consideration for award shall be returned within a reasonable time after Bid opening. The Bid Security of the apparent successful

Bidder shall be retained until the Contract has been executed and required

Performance and Payment Bonds have been furnished and approved.

If the successful Bidder fails to execute the Contract or furnish required bonds within the time specified, the Bid Security may be forfeited in accordance with

Section 9.

7.6 Performance and Payment Bonds

☒ Shall Apply.

For construction contracts exceeding the threshold set forth in §255.05, Florida

Statutes, the successful Bidder shall furnish both a Performance Bond and a

Payment Bond, each in the amount of one hundred percent (100%) of the

Contract Price.

The bonds shall:

• Be issued by a surety authorized to conduct business in the State of

Florida;

• Be accompanied by a current and valid Power of Attorney; and

• Comply with the requirements of §255.05, F.S.

The required bonds shall be furnished within ten (10) calendar days after issuance of the Notice of Award, unless otherwise authorized by the City, and shall be a condition precedent to Contract execution and issuance of the

Notice to Proceed.

Failure to furnish acceptable bonds shall constitute grounds for withdrawal of award and forfeiture of Bid Security as provided in Section 9.

7.7 Public Records

Pursuant to Chapter 119, Florida Statutes, all documents submitted in response to this ITB are subject to public inspection and copying unless exempt from disclosure by law.

Sealed bids are exempt from public disclosure until the City provides notice of an intended decision or as otherwise provided by §119.071(1)(b), Florida

Statutes.

If a Bidder claims that any portion of its Bid is exempt from disclosure, the Bidder shall identify the specific information claimed to be exempt and cite the applicable statutory basis. The City shall determine whether any claimed exemption applies.

By submitting a Bid, the Bidder acknowledges that the City is subject to Chapter

119, Florida Statutes, and cannot guarantee the confidentiality of submitted information.

IF THE RESPONDENT HAS QUESTIONS REGARDING THE APPLICATION OF CHAPTER 119, FLORIDA STATUTES, TO THE RESPONDENT’S DUTY TO PROVIDE PUBLIC RECORDS RELATING TO ANY RESULTING CONTRACT, CONTACT THE CUSTODIAN OF PUBLIC RECORDS AT:

Molly Turnes

Phone: (850) 983-5402

Email: mturnes@miltonfl.org

Address: 6738 Dixon Street, Milton, FL 32570

7.8 Local Vendor Preference

Pursuant to the City of Milton Purchasing Policy 9.0, the City encourages participation by local vendors. Local Vendor Preference in determining the lowest responsive and responsible Bidder preference is prohibited for Contract 2 due to applicable Fla. Stat. § 255.0991 which prohibits local governments from using local ordinances or preferences in competitive solicitations for construction services if the project/contract is funded 50% or more by state-appropriated funds. However, Local Vendor Preference in determining the lowest responsive and responsible Bidder is not prohibited for Contract 3 and 4 and City may consider Local Vendor Preference on Contracts 3 and 4.

mailto:mturnes@miltonfl.org https://www.google.com/goto?url=CAESbwHrOzAVk8sYkB5z5QMTiJbWD_f3fYN9rhVPMZxyQG3g6CYEv6Nhrw_McrM85cBFbLYfiZ9H2RTSvzojx4r2RBUppu5hkwbnQnY3DEoo3e0psBu4UA4j4HcF_VsdzfM_th9fG3fidHa6qxICeRDu6Q

SECTION 8 – EVALUATION AND BASIS OF AWARD

8.1 Evaluation

This Solicitation is issued as a competitive sealed bid pursuant to §255.20, Florida

Statutes. Award, if made, shall be to the lowest responsive and responsible

Bidder whose Bid conforms in all material respects to the requirements of this ITB.

If issued on a Lump Sum basis, the lowest responsive and responsible Bidder shall be determined based on the Base Bid amount stated in the Bid Form.

If issued on a Unit Price basis, the lowest responsive and responsible Bidder shall be determined based on the Total Evaluated Bid Amount calculated by applying the submitted Unit Prices to the estimated quantities provided for evaluation purposes.

Estimated quantities are approximate and are provided solely for comparison of

Bids. Actual quantities may increase or decrease as required for completion of the Work, and payment shall be based on actual quantities incorporated into the Work at the Unit Prices bid.

Where Add Alternates are included, the City may determine award based on the Base Bid or Total Evaluated Bid Amount alone, or plus any combination of

Add Alternates selected by the City.

8.2 Responsiveness

The City will review each Bid to determine whether it is responsive to the requirements of this ITB.

A responsive Bid is one that conforms in all material respects to the Solicitation

Documents without material deviation, reservation, or irregularity.

Failure to submit required forms, failure to acknowledge addenda, failure to include required bonds, or failure to comply with material requirements of this ITB may result in the Bid being deemed non-responsive.

8.3 Responsibility

The City shall determine whether the lowest responsive Bidder is responsible.

In determining responsibility, the City may consider factors including, but not limited to:

• Relevant experience on projects of similar size and scope

• Financial capacity and bonding capability

• Availability of equipment and personnel

• Safety record

• Past performance on public construction projects

• Compliance with applicable statutory requirements

• Ability to obtain required insurance and permits

The City may request additional information to assist in its responsibility determination. Failure to provide requested information within the time specified may result in a determination of non-responsibility.

8.4 Clarifications

The City may request clarification of information submitted in a Bid for the purpose of resolving ambiguities or confirming compliance with the requirements of this ITB. Clarifications shall not constitute negotiations and shall not permit modification of price, scope, or other material terms of the Bid.

Clarifications shall not cure a material defect or omission.

8.5 Rejection of Bids

The City reserves the right to:

• Reject any or all Bids.

• Reject a Bid determined to be mathematically or materially unbalanced.

• Waive minor irregularities or informalities that do not affect price, competition, or substantive rights.

• Verify references and qualifications.

• Conduct investigations as permitted by law.

• Award in the best interest of the City as authorized by law.

The City’s determination of responsiveness and responsibility shall be final, subject to applicable protest procedures set forth in the City of Milton

Purchasing Policy 9.0.

8.6 Tie Bids

In the event of a tie between two or more lowest responsive and responsible

Bidders, the tie shall be resolved in accordance with the City of Milton

Purchasing Policy 9.0.

SECTION 9 – AWARD PROCESS AND CONTRACT

9.1 Notice of Intended Award

Following completion of the evaluation described in Section 8, the City will post a Notice of Intended Award identifying the lowest responsive and responsible

Bidder.

The Notice of Intended Award shall be posted in accordance with the City of

Milton Purchasing Policy 9.0.

9.2 Protest Procedures

Any actual or prospective Bidder who is aggrieved in connection with this

Solicitation or the intended award may file a protest in accordance with the procedures and timeframes set forth in the City of Milton Purchasing Policy 9.0.

The protest period shall commence upon posting of the Notice of Intended

Award. Failure to timely file a protest in accordance with Purchasing Policy 9.0 shall constitute a waiver of all protest rights.

9.3 Notice of Award

If no timely protest is filed, or upon resolution of any timely protest, the City may issue a Notice of Award to the successful Bidder.

Issuance of the Notice of Award does not authorize commencement of the

Work and does not constitute a binding contract between the parties.

9.4 Contract Execution and Bond Submission

Within the time specified in the Notice of Award, the successful Bidder shall:

• Execute the Form of Agreement;

• Furnish the required Performance and Payment Bonds in accordance with

§255.05, Florida Statutes; and

• Provide all required insurance documentation.

Execution of the Agreement and submission and approval of required bonds and insurance are conditions precedent to issuance of the Notice to Proceed.

9.5 Failure to Execute or Provide Required Bonds

Failure of the successful Bidder to timely execute the Agreement or furnish required bonds and insurance may result in withdrawal of the award and forfeiture of the Bid Bond as permitted by law.

The City may, at its discretion, award the Contract to the next lowest responsive and responsible Bidder or reject all Bids and re-solicit.

9.6 Notice to Proceed

The Contractor shall not commence Work until the City issues a written Notice to

Proceed. The Contract Time shall commence as stated in the Notice to

Proceed.

9.7 Contract Term

The Contract shall become effective upon execution by both parties and shall remain in effect until Final Completion has been achieved, all closeout requirements have been satisfied, and final payment has been made, unless terminated earlier in accordance with the Contract Documents.

9.8 Contract Time

Substantial Completion shall be achieved within 510 Calendar Days after issuance of the Notice to Proceed.

Final Completion shall be achieved within 570 Calendar Days after issuance of the Notice to Proceed.

9.9 Liquidated Damages

Failure to achieve Substantial Completion within the Contract Time shall result in assessment of Liquidated Damages in the amount of $2,700 per Calendar Day for each day the Work remains incomplete beyond the required completion date.

Failure to achieve Final Completion within the Contract Time shall result in assessment of Liquidated Damages in the amount of $2,700 per Calendar Day for each day the Work remains incomplete beyond the required completion date.

Liquidated Damages for Final Completion shall apply only after Substantial

Completion has been achieved and shall not be assessed concurrently with

Liquidated Damages for Substantial Completion.

SECTION 10 – BID SUBMITTAL REQUIREMENTS

10.1 Bid Submittal Deadline

Bids must be received no later than the date and time stated in Section 3. Bids received after the stated deadline will not be accepted and will be returned unopened.

10.2 Bid Submittal Location

Bids shall be submitted in a sealed envelope, one (1) original and one (1) copy, to:

City of Milton

Attn: Purchasing Department

6738 Dixon Street

Milton, Florida 32570

10.3 Public Bid Opening

Bids will be publicly opened and read aloud at the beginning at 2:00 pm Milton

City Hall, 6738 Dixon Street, Milton, FL 32570.

10.4 Required Bid Contents

The Bidder shall include the following fully completed and executed documents in its sealed Bid submission:

1. Appendix A:

a. Bid Form

b. Bid Schedule

c. Bidder’s Qualification Statement

d. Site Examination Certification

e. Bidder’s Certification and Addenda Acknowledgement

2. Appendix B:

a. Subcontractor List

b. Anti-Human Trafficking Compliance Affidavit

c. Certification Regarding Nondiscrimination

d. Conflict-of-Interest Disclosure and Certification

e. Drug-Free Workplace Certification

f. E-Verify Compliance Certification

g. Non-Collusion Affidavit

h. Prompt Payment Compliance Certification

i. Public Entity Crime Affidavit

j. Scrutinized Companies Certification

3. Additional Items:

a. Bid Bond (as required in Section 7)

b. Contractor’s License {Insert applicable licensure required}

All required forms shall be properly executed. Forms requiring notarization must be notarized.

Failure to submit all required documents at the time of Bid opening may result in the Bid being deemed non-responsive.

10.5 Addendum Acknowledgement

Failure to properly acknowledge receipt of all issued addenda in the Bid Form may result in the Bid being deemed non-responsive.

10.6 Withdrawal or Modification

Bids may be modified or withdrawn prior to the submission deadline by written notice.

10.7 Required Envelope Markings

The sealed envelope shall clearly display:

10.8 Responsibility for Delivery

It is the sole responsibility of the Bidder to ensure that its Bid is received at the designated location on or before the stated deadline. The City shall not be responsible for delays caused by mail, courier service, or other delivery methods.

Bids submitted by telephone, email, facsimile, or other electronic transmission will not be accepted unless expressly authorized in this Solicitation.

Failure to comply with the submission requirements of this ITB may result in the Bid being deemed non-responsive.

To: C i ty of Milton

VENDOR Name:

SEALED BID * DO NOT OPEN

Sealed ITB #2026.16

Title: 2026.16 ITB Effluent Discharge System (Pipeline, Pump Station, Sprayfield 2)

DUE DATE/TIME: Thursday, December 17, 2026 / 10:00 a.m. (CST)

SECTION 11 – INSTRUCTIONS TO BIDDER

11.1 General

This Invitation to Bid (“ITB”) is issued as a competitive sealed bid for a public construction project. The Work is fully described in the Solicitation Documents.

Bidders shall submit sealed Bids in strict accordance with the requirements of this

ITB.

All documents issued in connection with this Solicitation, including the ITB, plans, specifications, appendices, exhibits, and addenda, collectively comprise the

Solicitation Documents and are complementary to one another.

It is the responsibility of each Bidder to monitor the City’s designated solicitation platforms and website for the issuance of addenda. Failure to acknowledge addenda as required may result in the Bid being deemed non-responsive.

11.2 Official Posting Platforms

The City utilizes BidNet Direct, DemandStar, and the City’s official website for publication of solicitation opportunities and addenda. Bidders are solely responsible for monitoring these platforms and ensuring receipt of any addenda issued.

11.3 Proposal Forms

Bidders shall submit their Bid on the forms furnished by the City. All blank spaces shall be completed in ink or typed. Where required, amounts shall be stated in both words and figures.

Bidders shall not modify, alter, or substitute the City’s Bid Form. Submission of a

Bid on any form other than that provided may result in the Bid being deemed non-responsive.

All documents required by this ITB, including bid security, certifications, affidavits, and other required attachments, shall be submitted with the Bid. Such required attachments shall not be considered modifications to the Bid Form.

If additional space is necessary for completion of any required form, clearly labeled supplemental pages may be attached.

11.4 Signature Requirements

The Bid shall be signed by an individual authorized to bind the Bidder.

If the Bid is submitted by a corporation, limited liability company, partnership, or other legal entity, the person signing the Bid shall certify that they are authorized to execute the Bid on behalf of the entity.

If the Bid is signed by an agent, written evidence of the agent’s authority to bind the Bidder shall be submitted with the Bid.

Electronic signatures are accepted unless otherwise stated in this ITB.

11.5 Addenda

Addenda may be issued to clarify, modify, or revise the Solicitation Documents.

Addenda shall be issued in writing and posted on the City’s designated solicitation platforms.

Verbal statements, interpretations, or clarifications shall not be binding.

Each Bidder is responsible for determining whether any addenda have been issued and for acknowledging receipt of all addenda in the Bid Form.

11.6 Examination of Solicitation Documents and Site

Each Bidder is responsible for:

• Thoroughly examining the Solicitation Documents;

• Visiting the Project site to become familiar with existing conditions that may affect the Work;

• Reviewing applicable federal, state, and local laws, regulations, permits, and ordinances that may affect performance of the Work;

• Studying and correlating observations with the Contract Documents; and

• Promptly notifying the City of any conflicts, errors, or discrepancies discovered in the Solicitation Documents.

Submission of a Bid constitutes representation that the Bidder has satisfied itself as to all conditions affecting the Work and that the Bid is based upon performance in accordance with the Contract Documents.

11.7 Pre-Bid Conference

If a pre-bid conference is scheduled, the date, time, and location shall be as stated in this ITB. Attendance shall be mandatory as indicated in Section 3.

Statements made at a pre-bid conference are not binding unless confirmed by written addendum.

11.8 Pre-Bid Questions and Interpretations

All questions regarding the meaning or intent of the Solicitation Documents shall be submitted in writing to the Procurement Representative as identified in

Section 3.

Questions must be received no later than the deadline stated in this ITB.

Responses deemed necessary by the City shall be issued by written addendum.

Only written addenda issued by the City shall be binding. No verbal interpretation or clarification shall modify the Solicitation Documents.

11.9 Bid Quantities (If Unit Price Contract)

Bidders shall not modify the estimated quantities provided in the Bid Schedule but shall insert a unit price for each item listed.

11.10 Compliance with Applicable Laws

Bidders shall comply with all applicable federal, state, and local laws, rules, and regulations in the preparation and submission of their Bid.

11.11 Mathematical Errors

In the event of discrepancy between the Bid Form total and the sum of individual line items, the sum of the individual line items shall govern.

11.12 Word vs. Figure Discrepancy

In the event of discrepancy between words and figures, the amount stated in words shall govern.

11.13 Americans with Disabilities Act (ADA)

The City of Milton complies with the Americans with Disabilities Act (ADA).

Any person requiring special accommodations to participate in this solicitation process should contact the City’s Purchasing Department at least seventy-two

(72) hours prior to the scheduled event.

11.14 Reservation of Rights

The City reserves the right to waive minor irregularities, request clarifications, verify information, reject any or all Bids, cancel or re-advertise the Solicitation, and take any action authorized by applicable law, including accepting the Bid determined to be in the best interest of the City. No contractual relationship shall exist until a written Agreement is executed by authorized representatives of both parties.

APPENDIX A

• Bid Form

• Bid Schedule

• Bidder Qualification Statement

• Site Examination Form

• Bidder Certification and Addenda Acknowledgement

MUST BE SUBMITTED WITH THE BID.

FAILURE TO DO SO WILL RENDER BID NON-RESPONSIVE.

BIDDER QUALIFICATION STATEMENT

The following information is required for the City to determine responsiveness, responsibility, and statutory eligibility in accordance with Florida law and the

Solicitation Documents.

Failure to provide complete and accurate information may result in the Bidder being determined non-responsible or ineligible for award.

PART A – RESPONSIBILITY REQUIREMENTS

The following information is used by the City to determine whether the Bidder is responsible and capable of performing the Contract.

1. LEGAL ENTITY INFORMATION

Legal Name of Bidder (as registered with the Florida Division of Corporations):

State of Incorporation/Organization: __________________________

Date of Formation: __________________________________________

FEIN: _______________________________________________________

Primary Business Address:

Street: ______________________________________________________

City, State, Zip: _____________________________________________

Phone: _________________________

Email: __________________________

Website (if applicable): ______________________________________

If an out-of-state Corporation currently authorized to do business in Florida, give date of such authorization: ______________________________________

2. FLORIDA CONTRACTOR LICENSING

The Bidder certifies that all required licenses are active and in good standing with the Florida Department of Business and Professional Regulation and that the

Bidder is properly licensed to perform the Work described in this Solicitation.

The successful Bidder shall maintain all required licenses in active status for the duration of the Contract.

Failure to maintain required licensure may be grounds for termination of the

Contract.

3. BUSINESS EXPERIENCE

Number of years the Bidder has been engaged in construction services: ________

Number of years under present business name: ___________________

If the Bidder has operated under a different name within the past five (5) years, provide details: _____________________________________________________________

4. REFERENCES – SIMILAR PROJECTS

List at least three (3) projects completed within the past five (5) years in which the Bidder served as Prime Contractor, and which are similar in size, scope, and complexity to the Work described in this Solicitation.

1. Project Name: ___________________________________________________

Owner (Entity Name): ____________________________________________

Owner Contact Person: __________________________________________

Phone/Email: ____________________________________________________

Description of Project Scope: _____________________________________

Original Contract Amount: $______________________________________

Final Contract Amount (if different): $_____________________________

Original Contract Completion Date: ______________________________

Actual Final Completion Date: ____________________________________

Were time extensions granted? □ Yes □ No

If yes, total number of days extended: ____________________________

Were liquidated damages assessed? □ Yes □ No

If yes, total amount assessed: $____________________________________

2. Project Name: ___________________________________________________

Owner (Entity Name): ____________________________________________

Owner Contact Person: __________________________________________

Phone/Email: ____________________________________________________

Description of Project Scope: _____________________________________

Original Contract Amount: $______________________________________

Final Contract Amount (if different): $_____________________________

Original Contract Completion Date: ______________________________

Actual Final Completion Date: ____________________________________

Were time extensions granted? □ Yes □ No

If yes, total number of days extended: ____________________________

Were liquidated damages assessed? □ Yes □ No

If yes, total amount assessed: $____________________________________

3. Project Name: ___________________________________________________

Owner (Entity Name): ____________________________________________

Owner Contact Person: __________________________________________

Phone/Email: ____________________________________________________

Description of Project Scope: _____________________________________

Original Contract Amount: $______________________________________

Final Contract Amount (if different): $_____________________________

Original Contract Completion Date: ______________________________

Actual Final Completion Date: ____________________________________

Were time extensions granted? □ Yes □ No

If yes, total number of days extended: ____________________________

Were liquidated damages assessed? □ Yes □ No

If yes, total amount assessed: $____________________________________

5. BONDING CAPACITY

Name of Surety Company: ____________________________________

Surety Agent Name: _________________________________________

Phone: _________________________

Email: __________________________

The Bidder certifies that it is capable of obtaining Payment and Performance

Bonds in the full amount required under §255.05, F.S., if applicable.

6. INSURANCE CAPABILITY

The Bidder certifies that it can obtain and maintain the insurance coverage required by the Solicitation Documents and Contract.

7. LITIGATION AND CLAIMS HISTORY

Within the past five (5) years, has the Bidder:

A. Been terminated for cause on a construction contract? □ Yes □ No

B. Had liquidated damages assessed in excess of $50,000 on any single project?

□ Yes □ No

C. Had a bond called, or surety claim made? □ Yes □ No

If yes to any above, provide explanation:

8. FINANCIAL RESPONSIBILITY

The City reserves the right to request financial statements or other documentation reasonably necessary to determine the Bidder’s responsibility.

Failure to provide requested documentation may result in a determination of non-responsibility.

PART B – STATUTORY ELIGIBILITY

The Bidder certifies that:

A. It is not on the Convicted Vendor List pursuant to §287.133, F.S.

B. It is not listed on any Scrutinized Companies List pursuant to §§287.134–

287.135, F.S.

C. Pursuant to §448.095, F.S., it is registered with and uses the E-Verify system to verify the work authorization status of all newly hired employees and will require all subcontractors to comply with §448.095, F.S., and provide evidence of enrollment upon request.

Failure to comply with the above statutory requirements may result in rejection of the Bid, termination of the Contract, or other remedies provided by law.

CERTIFICATION

The undersigned certifies that:

1. All information provided herein is true, correct, and complete.

2. The Bidder possesses the experience, financial resources, and capability to perform the Work.

3. The City may conduct investigations to verify the information…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .