This solicitation is for the replacement of the Tanis Mesa recreation cabin located on the Yakutat Ranger District of the Tongass National Forest in Alaska. Major work includes demolishing the existing 60-foot A-frame cabin and constructing a new single-story 15-foot by 17-foot log cabin with associated site work, deck, ramp, stairs, heating system, and foundation. Other existing structures are to remain. The project site is accessible by helicopter or bush plane. Offerors must provide pricing for all line items under the firm fixed-price contract, which has a value between $250,000 and $500,000. Technical and price proposals are due by June 12, 2023. This is a small business set-aside project. The selected contractor must complete all work by September 1, 2024.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No: 1240BJ23R0005 Project Name: Yakutat Tanis Mesa Cabin
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
1240BJ23R0005
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
5/12/2023
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
1099688
6. PROJECT NO.
7. ISSUED BY CODE 8. ADDRESS OFFER TO: (E-Mail Only)
Procurement & Property Services, Field Procurement Operations Northwest Zone – Construction & A-E Attn: Roxanne Anderson, CO
Note: All proposal documents must be e-mailed to roxanne.d.anderson@usda.gov. An e-mail copy of the Bid Bond is acceptable for proposals valued at $150,000.00 or greater.
9. FOR INFORMATION
CALL:
A. NAME
Roxanne Anderson B. TELEPHONE NO. (Include area code) (NO COLLECT
CALLS)
(503)668-1730 roxanne.d.andeson@usda.gov
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
GAOA Yakutat Cabin Maintenance: Tanis Mesa Cabin Replacement Yakutat Ranger District, Tongass National Forest
Yakutat, Alaska Disclosure of the Magnitude of Construction Project: Between $250,000 and $500,000
Technical POC: Carol Jensen, carol.jensen@usda.gov Contractual POC: Roxanne Anderson – Contracting Officer
Offerors must respond as described in Sections L and M. Proposals that fail to provide a complete response to the Technical Evaluation Factors (Section M) may be rejected and not considered further.
THIS IS A SMALL BUSINESS SET-ASIDE PROJECT. OFFERS RECEIVED FROM OTHER THAN SMALL
BUSINESSES WILL BE REJECTED
11. The Contractor shall begin performance within 10 calendar days and complete it within 420 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See Section F.)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
Ten (10)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and Emailed copies to perform the work required are due at the place specified in Item 8 by June 12, 2023 4;30pm Alaska. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than sixty (60) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
mailto:roxanne.d.anderson@usda.gov mailto:roxanne.d.andeson@usda.gov
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
IPP
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
(see block 7) Invoice Processing Platform IPP All invoices must be submitted electronically through the Invoice
Processing Platform IPP via www.ipp.gov.
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO
SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
ROXANNE ANDERSON
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD
DATE
Table of Contents
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS
B.2 SCHEDULE NOTES
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
C.2 PROJECT LOCATION
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
C.4 TECHNICAL SPECIFICATIONS
SECTION D--PACKAGING AND MARKING
D.1 PACKING AND MARKING
D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
F.2 OTHER REQUIREMENTS ................................................... Error! Bookmark not defined.
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
G.2 OTHER REQUIREMENTS
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
H.2 OTHER REQUIREMENTS
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
J.1 ATTACHMENTS
PART IV--REPRESENTATIONS AND INSTRUCTIONS
SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND
OTHER STATEMENTS OF OFFERORS OR RESPONDENTS
K.1 PROVISIONS
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS
L.1 PROVISIONS
SECTION M--EVALUATION FACTORS FOR AWARD
M.1 PROVISIONS
M.2 PROPOSAL EVALUATION
M.3 TECHNICAL EVALUATION FACTORS
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
GAOA Yakutat Cabin Maintenance: Tanis Mesa Cabin Replacement Yakutat Ranger District, Tongass National Forest
Yakutat, Alaska
B.1 SCHEDULE OF ITEMS
Item Supplies/Services Qty Unit of
Issue Unit Price Total Price
1 Mobilization
1 LS $ $
2 Demolish and remove existing Tanis Mesa Cabin
1 LS $ $
3 Provide and Install new Tanis Mesa Cabin and related work
1 LS $ $
4 Provide and Install Cabin Furnishings and Sign
1 LS $ $
TOTAL BASE BID PRICE $
B.2 SCHEDULE NOTES
EMAIL: __________________________________________________________
UNIQUE ENTITY ID (from SAM.gov): _______________________________
One award will be made from this solicitation, contractors must submit pricing for all items.
The forest service intends to award this as a “firm-fixed price” construction contract.
All offerors will be required to provide a Bid Bond (20%) with their proposal submission.
Performance and Payment Bonds (100% each) will be required of the successful awardee.
Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under Pay Item (01) Mobilization.
Payment will be made on actual work performed as described in the identified tasks and Schedule of Items
See Section L and Section M for Instructions to Offerors and Submittal Requirements.
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
Description:
This project is for the replacement of one recreation cabin at Tanis Mesa. Major work items under Base Bid include the demolition of the existing Tanis Mesa Cabin, a 60’ long A-Frame, constructing one single story 15’x17’ log cabin and associated site work, as well as, constructing the associated deck, ramp, stairs, heating system, and foundation. All other existing structures at Tanis Mesa to remain.
The cabin shall be closed to the public during periods of active work on site, including demolition, construction, and when construction hazards are present. Work shall be completed in a manner that minimizes the duration of the facility’s closure for public use.
**SEE ATTACHMENTS FOR FULL STATEMENT OF WORK**
C.2 PROJECT LOCATION
Location and Facilities: The project site for Base Bid work is located at Tanis Mesa (59°14'49.56"N, 138°30'11.22"W). This site is approximately 45 miles SE of Yakutat, AK. Access to the Base Bid project site is via helicopter or bush plane; airstrip at cabin site.
There are no utilities at any project site. Cell phone service is not available at Tanis Mesa Yakutat is the nearest community and is accessible by scheduled jet service, barge, and the Alaska Marine Highway ferry system.
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
Price Range: Between $250,000 and $500,000.
C.4 TECHNICAL SPECIFICATIONS
452.211-72 Statement of Work/Specifications (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
452.211-73 Attachments to Statement of Work/Specifications (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
SECTION D--PACKAGING AND MARKING
D.1 PACKING AND MARKING
All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.
D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
E.2 INSPECTION AND ACCEPTANCE (AGAR 452.246-70) (FEB 1988)
A. The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
B. Inspection and acceptance will be performed at the project site.
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
52.236-15 Schedules for Construction Contracts (APR 1984) 52.242-14 Suspension of Work (APR 1984)
52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within _10__ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than _September 1, 2024_.
The time stated for completion shall include final cleanup of the premises.
Estimated start work: July 2023
F.2 NOTICE TO PROCEED (NTP)
A Notice to Proceed will be issued in writing by the Contracting Officer or Contracting Officer’s Representative (COR). No work shall begin until receipt of this notice. Contract time shall commence on the day indicated on the Notice to Proceed.
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled and held within _14_days after the date of contract award. The conference will be held at a mutually agreed location or scheduled teleconference.
G.2 GOVERNMENT FURNISHED PROPERTY (GFP)
The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract/ task order. This property shall be used and maintained by the Contractor in accordance with the provisions of the “Government Property” FAR clause contained elsewhere in the contract.
Item No. Property Description Qty Location Date
Available or Delivery Date
1 diesel stove 1 After NTP
2 detachable diesel fuel tank 1 After NTP
G.3 PAYMENT FOR MATERIALS DELIVERED OFF THE SITE
As provided in FAR 52.232-5, Payments Under Fixed-Price Construction Contracts, material acquired for incorporation into the project, and stored off site by the Contractor, may, at the option of the Contracting Officer, be included in progress payments. Prior to payment, such material will be subject to Government inspection and must be stored separately from other materials, and be identified as, "PROPERTY OF THE UNITED STATES, Project Name and Contract Number." In addition, the Contractor shall furnish the Government with a right of ingress and egress to the property together with right of removal.
G.4 PAYMENTS FOR INCIDENTAL ITEMS
The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items.
All other work and materials will be considered incidental to and included in the payment for items shown.
G.5 PUBLIC OFFICIALS NOT PERSONALLY LIABLE
There shall be no personal liability upon the Government or officer in charge, their agents or employees, for any act performed in the discharge of any duty imposed or the exercise of any power or authority conferred upon them by, or within the scope of the contract, it being understood that in all such matters they act solely as agents and representatives of the
Government.
G.6 RETURN OF PERFORMANCE AND PAYMENT BONDS
Performance and payment security furnished under this contract must be retained by the Government for a minimum of one year after acceptance of all work under the contract.
Performance and payment security other than corporate or individual surety bonds will be returned to the Contractor one year after completion of work if no claims against these bonds have been filed at that time.
G.7 PAYMENT FOR PERFORMANCE AND PAYMENT SECURITY EXPENSES
It is mutually agreed that the premium costs for performance bonds, payment bonds and alternative payment protections furnished for this contract are included in the total amount bid for other items and that any payment to the Contractor for the cost of bonds made in accordance with FAR 52.232-5 refers only to corporate sureties listed in the current Department of Treasury Circular 570 and no advance payment will be made for bond premiums where other than corporate surety bonds are furnished. Bond premiums as used in this paragraph and FAR 52.232-5 shall include any Small Business Administration fees paid in connection with SBA guaranteed corporate surety bonds.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
452.228-71 Insurance Coverage (NOV 1996) Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:
(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.
(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence. (2) The Contractor shall have property damage liability insurance shall be required in the amount of ____*___ per occurrence.
(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.
(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
H.2 REQUIRED SUBMITTALS
The following is a general summary of the required submittals. Other submittals may be required as specified elsewhere in the basic contract.
Submittal Title Referenced By Specification No. Submittal Date
Schedule of Work/Progress Schedule
Schedules For Construction
Contracts
[FAR 52.236-15]
With Proposal and then Updated when Necessary
Job Specific Safety Plan
Section H & Accident
Prevention clause
[FAR 52.236-13]
Prior to Work starting and updated as Necessary
Copy of Required Insurance Coverage
[FAR52.228-5
452.228-71 ]
Section I Prior to Work Starting
Camping Permit Section H Prior to Work Starting
Designation of Representative R6-FS- 6300-6
Superintendence by the Contractor
[FAR 52.236-6]
At the Post Award Conference
Notification of Subcontracting & SF1413 - Statement and Acknowledgement for each Subcontractor including Owner/Operators and other Sole Proprietorship Subcontractors [not required for material suppliers]
Subcontracts (Labor Standards)
[FAR 52.236-11]and Section G
Prior to Subcontractor Starting Work
Payroll Record WH347 Certified Payrolls submitted weekly
Payrolls And Basic Records
[FAR 52.222-8]
Weekly; Hard Copy
Drug Free Workplace Policy Drug-Free Workplace
[FAR 52.223-6]
Before Starting Work
Biobased or BioPreferred Products Section C & I In accordance with FAR 52.223-2
H.3 JOB-SPECIFIC SAFETY PLAN
Prior to the post award meeting, the Contractor shall provide a written job specific safety plan that recognizes the inherently hazardous conditions that will exist on this task order. Some of these hazardous conditions are, but not limited to: blasting, heavy equipment operation, traffic control on haul routes, loading and unloading of materials, site security, noises and dust task order and the use of personal protective equipment (PPE) in the work area. The plan shall be in accordance with OSHA Regulations. The plan shall include all tasks and related activities anticipated to successfully complete the work.
H.4 SAFETY ITEMS
(a) Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. This list shall not be deemed to be all inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the work site.
(b) The following checked activities have been identified by the Government as potential safety hazards, but not limited to:
[X] Confined Entry Space.
[X] Temporary excavation/deep trenching/slope stability.
[ ] Tree Felling.
[X] Fall hazard from work heights exceeding six feet.
[ ] Blasting.
[ ] Traffic control on high-volume and/or high-speed and/or limited visibility roads.
[X] Heavy equipment operation.
[ ] Tree climbing and/or tower climbing.
[ ] Fire hazards.
[X] Hazard materials handling.
[ ] Electrical hazard.
[X] Hydraulic and/or pneumatic and/or other high pressure hazards.
[X] Mechanical hazards such as pulleys, springs, etc.
[X] Power tool operation including eye protection.
[X] Overhead hazards.
[ ] Steep slopes and /or downed logs.
[X] Insects including Asian Hornets.
H.5 PERSONAL PROTECTIVE EQUIPMENT
1. 29 CFR 1910 Subpart I, OSHA’s General Industry Personal Protective Equipment (PPE) standard contains the general requirements for the provision of personal protective equipment and requires employers to perform a hazard assessment to select appropriate PPE for hazards that are present or likely to be present in the workplace. OSHA requires that many categories of personal protective equipment meet or be equivalent to standards developed by the American National Standards Institute (ANSI).
2. Before a worker begins operating equipment, the Contractor must train the workers on the in the safe operation and use of equipment to all workers using such equipment.
3. The Contractor shall provide the appropriate personal protective equipment for the work required to be performed in the contract / task order, whenever necessary by reason of hazards or processes encountered that may cause injury or impairment in the function of any part of the body. Except for foot protection, all PPE must be provided by the employer at no cost to the employee. Includes:
• Head Protection
• Hearing Protection
• Eye/Face Protection
• Leg Protection
• Foot Protection
• Hand Protection
4. PPE must be sanitary and in reliable condition. Contractor shall not use defective or damaged PPE. PPE must be inspected by the Contractor prior to use on each work shift to ensure it is in serviceable condition.
5. A checklist of applicable PPE Guidelines typical for the work performed under this task order is available at https://www.osha.gov/SLTC/personalprotectiveequipment/index.htm or OSHA 3151-12 R 2003 Personnel Protective Equipment Booklet and other locations.
6. At all times, the Contractor is responsible for performing a risk assessment and providing the necessary PPE for their operation on this contract/task order.
https://www.osha.gov/SLTC/personalprotectiveequipment/index.htm%20or%20OSHA%203151-12 https://www.osha.gov/SLTC/personalprotectiveequipment/index.htm%20or%20OSHA%203151-12
7. The Contractor shall be in compliance with the all field sanitations. OSHA’s established minimum standards for field sanitation is applicable to this task contract/task order. Refer to Fact Sheet # 51 Field Sanitation Standards under the Occupational Safety and Health Act.
H.6 HAZARDOUS MATERIALS
Contractor shall notify the Government of any hazardous materials and or waste (as defined in 29 CFR 1910.1200) to be used on the job and will have Material Safety Data Sheets (MSDSs) for those materials available on the job. All such materials shall be labeled in accordance with Federal and State regulations.
If Contractor maintains storage facilities for oil or oil products in the task order area, Contractor shall take appropriate preventive measures to insure that any releases of such oil or oil products does not enter any stream or other waters, or ground of the United States, or any of the individual States and shall conform to Federal, State, and Local regulations.
If the total oil or oil products storage exceeds 1,320 gallons, or if any single container exceeds a capacity of 660 gallons, Contractor shall prepare and implement a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR
112) including certification by a registered professional engineer.
Contractor shall immediately take action to notify appropriate agencies including Contracting Officer, or designated representative, contain, and cleanup without expense to the Government, all petroleum products or other hazardous substance (as defined in 29 CFR 1910.120) releases on/or in the vicinity of the project of construction operations. Contractor shall be held liable for all damages and costs of additional labor, subsistence, equipment, supplies and transportation deemed necessary by the Government for the containment and cleanup of petroleum products releases caused by Contractor’s employees or resulting from construction operations.
All petroleum products or other hazardous substances shall not be released on or into land or into rivers, streams, and impoundments, or into natural or manmade channels leading thereto.
Servicing of all equipment shall be done only in the areas approved by Contracting Officer or designated representative. Contractor shall properly dispose of vehicle oil filters (drained of free-flowing oil), oily rags, and waste oil in accordance with Local, State, and Federal regulations off of Government property and shall transport such material in accordance with State and Federal regulations.
H.7 USE OF PREMISES
A. The Contractor shall comply with the regulations governing the operation of premises which are occupied and shall perform this task order in such a manner as not to interrupt or interfere with the conduct of Government business.
B. Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on Forest Service land or lands administered by the Forest Service, the Contractor shall obtain written permission from the appropriate Ranger District. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor. If permission is granted, a work order will specify all conditions and requirements. Sanitation facilities shall be provided for all employees of the Contractor and members of the campsite.
C. It is further stipulated that in addition to clean-up of any campsites, the Contractor shall remove his equipment from National Forest Service land before final acceptance and payment of the task order.
H.8 PRODUCT SUBSTITUTION
Any modification of other items, designs, materials, products or equipment (including Government-furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.
H.9 LANDSCAPE PRESERVATION
The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall conduct the work at all times in compliance with the following requirements.
a) Prevention of the Landscape Defacement. The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawns, or other natural features or any other improvements in the work area unless specifically authorized by the Contracting Officer.
Unless otherwise provided herein, the Contractor shall confine contract operations to within the areas designated in contract documents.
H.10 FAR 52.236-27 Site Visit (Construction) FEB 1995
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal work hours by contacting:
Name: Carol Jensen, (907) 772-5859 carol.jensen@usda.gov Alternate: Austin Thomas, (732)759-4746 austin.thomas@usda.gov mailto:carol.jensen@usda.gov mailto:austin.thomas@usda.gov
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
Federal Acquisition Regulation (FAR) Clauses:
https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:
https://www.acquisition.gov/agar (AGAR clauses begin with 452) FAR and AGAR Deviations to clauses may be viewed at: Policies & Regulations | USDA
52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights & Requirements to Inform
Employees of Whistleblower Rights (JUN 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or
Statements (JAN 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY
2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN
2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or
Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors
Debarred, Suspended, or Proposed for Debarment (NOV 2021) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns (OCT 2022)(DEVIATION DEC 2022) 52.219-14 Limitations on Subcontracting (OCT 2022) 52.219-28 Post Award Small Business Program Rerepresentation (MAR 2023) 52.222-3 Convict Labor (JUN 2003) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.usda.gov/da/ocp/ppd/policies-regulations https://www.usda.gov/sites/default/files/documents/far-class-deviation-regarding-threshold-small-disadvantaged-business.pdf
52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY
2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations
(MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC
2010) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-54 Employment Eligibility Verification (MAY 2022) 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN
2022) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction
Contracts (SEP 2013) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN
2020) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT
2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023)
52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)
Alternate I (NOV 1991) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)
Alternate I (APR 1984) Alternate II (APR 1984)
52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-2 Subcontracts (JUN 2020) 52.244-6 Subcontracts for Commercial Products and Commercial Services (MAR 2023) 52.245-1 Government Property (SEP 2021) - Alt 1 (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994)
Alternate I (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)
Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984)
Alternate I (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991) 452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV
1996) 452.236-71 Prohibition Against the Use of Lead-Based Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archaeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)
52.225-9 Buy American Act-Construction Materials (OCT 2022)
(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if–
(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components https://www.acquisition.gov/far/part-2#FAR_2_101 https://www.acquisition.gov/far/part-25#FAR_25_105 of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
[Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505 determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1) (i)Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction Material Description Unit of Measure Quantity Price (Dollars)* Item1
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______
[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]
(End of clause)
52.228-1 Bid Guarantee (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –
(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be __20__ percent of the bid price or $___N/A____, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt…