This document is a Request for Quotation (RFQ) for construction services to renovate and repair the Marine Security Guard Residence (MSGR) at the U.S. Embassy Residential Compound in Juba, South Sudan.

The scope of work includes removing existing plaster, installing ferrocement jacketing to repair interior non-bearing masonry walls with large cracks, and restoring the affected areas. The work must comply with U.S. building codes and standards. The RFQ utilizes a Lowest Price Technically Acceptable (LPTA) source selection process. Proposals are due by April 24, 2024 at 2300 CAT. The U.S. Agency for International Development (USAID) South Sudan office is the contracting authority. The solicitation includes a mandatory site visit on April 16, 2024 and a Bill of Quantities for the required work. The awarded contract will be a Firm Fixed Price Purchase Order.

View the file

Other files

File Type Posted
ATTACHMENT - MSGR DRAWINGS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER

REQ-668-24-000090

PAGE 1 OF

2. CONTRACT NO.

7. FOR SOLICITATION

INFORMATION CALL:

3. AWARD/EFFECTIVE

DATE

a. NAME

See page 11

4. ORDER NUMBER 5. SOLICITATION NUMBER

72066824Q00031

b. TELEPHONE NUMBER (No collect calls)

See page 11

6. SOLICITATION ISSUE

DATE

04/08/2024

8. OFFER DUE DATE/

LOCAL TIME

04/24/2024

2300 CAT

9. ISSUED BY CODE 720668

USAID/South Sudan

10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

4420 Juba Place Washington DC 20251-4420 00000

HUBZONE SMALL

BUSINESS

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

SMALL BUSINESS PROGRAM

EDWOSB

8 (A)

NAICS:

SIZE STANDARD:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13b. RATING

14. METHOD OF SOLICITATION

RFQ IFB RFP

15. DELIVER TO CODE 720668

Kololo Street, 2nd Block Next to European Union US Embassy, Juba South Sudan

16. ADMINISTERED BY CODE

USAID/SOUTH SUDAN/EXO

17a. CONTRACTOR/

OFFEROR

CODE FACILITY

CODE

18a. PAYMENT WILL BE MADE BY CODE

TELEPHONE NO.

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED SEE ADDENDUM

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

Procure services to renovate and repair Marine Security Guard Residence (MSGR) at the US Embassy Residential Compound (RC) in Juba, South Sudan

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

ARE

ARE

ARE NOT ATTACHED

ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 29. AWARD OF CONTRACT: REF. OFFER

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

LESLIE PETERSEN

31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA - FAR (48 CFR) 53.212

SMALL BUSINESS

Issue Date: April 8, 2024

Deadline for Questions: April 18, 2024, C.O.B 5p.m. (CAT) South Sudan Time

Site Visit: April 16, 2024, at 10a.m. (CAT) South Sudan Time

Closing Date and Time: April 24, 2024, at 2300 (CAT) South Sudan Time. Late submissions WILL NOT be considered.

REQUEST FOR QUOTATION NO.:72066824Q00031 – MSGR REPAIR PROJECT

Dear Offerors, USAID/South Sudan – Construction Office is seeking quotations from reputable construction firms to renovate and repair Marine Security Guard Residence (MSGR) at the US Embassy Residential Compound (RC).

Award will be based on the Lowest Price Technically Acceptable (LPTA) process.

(i) This posting serves as a Combined Synopsis/Solicitation for Commercial Items prepared in accordance with the Federal Acquisition Regulation (FAR) 12.6, Streamlined Procedures for Evaluation and Solicitation for Commercial Items, as supplemented with additional information included in this notice.

(ii) This announcement constitutes the only solicitation.

(iii) This is a Request for Quotations only. Issuance of this RFQ does not in any way obligate USAID to make an award or pay for costs incurred by potential offerors in the preparation and submission of an offer.

(iv) The solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular (FAC) 2021-06 (06/10/2021). It is the responsibility of the Offeror to be familiar with the applicable clauses and provisions. The full text of the referenced FAR Clauses may be accessed electronically at https://www.acquistion.gov/far/.

https://www.acquistion.gov/far/

(v) The associated North American Industrial Classification Code (NAICS) for this procurement is 423390 - Other Construction Material Merchant Wholesalers 100.

(vi) The US Mission in South Sudan is exempt from all Government taxes.

(vii) The Government will award a contract resulting from this solicitation to the responsible offeror under the LPTA process.

(i) For the Site Visit: Please provide names/ID for technical company representatives to attend by April 12, 2024, 1p.m. (CAT) South Sudan Time.

(ii) Quotations in response to this RFQ must be priced on a Firm-Fixed-Price basis.

Offers must remain valid for no less than thirty (30) calendar days after the offer submission date. Offerors are requested to provide quotations on their official quotation format or letterhead. The quotation proposal must not be more than 15 pages and must be on A-4 paper size.

(iii) USAID/South Sudan anticipates awarding a Firm Fixed Price Purchase Order as a result of this RFQ.

(iv) Submission method: Electronically - email your offer or questions to npoggo@usaid.gov with copy to jubaprocurements@usaid.gov

IMPORTANT NOTE: All vendors dealing with the United States Government MUST be registered in the SAM (System for Award Management) Database https://www.sam.gov prior to contract award pursuant to FAR provision 52.204-7. Therefore, prospective offerors are encouraged to register prior to the submission of quotations/proposals.

Only vendors who have fully complied with this requirement are eligible for award.

Regards, USAID/South Sudan/Procurement Office mailto:npoggo@usaid.gov mailto:jubaprocurements@usaid.gov http://www.sam.gov/

USAID/South Sudan Marine Security Guard Residence (MSGR)

Crack Repair Project

Statement of Work

1. Purpose

The U.S. American Embassy requests construction repair services for the installation of ferrocement jacketing for the purpose of repairing interior non-bearing masonry walls exhibiting heavy cracking.

The services shall include, but shall not be limited to mobilization, protection of existing facilities, shoring, removal of existing plaster in specified areas, installation of ferrocement jacketing comprising welded wire mesh and mortar cement plaster, paint, clean up, and demobilization.

The facility, MSGR, is located on the US Residential Compound in Juba, South Sudan. Access to the site shall be requested through the Embassy’s Facility Manager (FM) or Contracting Officer Representative (COR).

The Contractor for this work shall be a licensed or registered construction company, registered in South Sudan, with at least 10 years of demonstrated experience and expertise in the installation and execution of masonry and masonry repairs. The contractor shall be familiar with United States building code regulations including the International Building Code (IBC), the American Concrete Institute (ACI), and the American Society for Testing Materials (ASTM) as all works shall comply with the above referenced standards, as specified in the contract documents.

2. Background

There have been severable notable full-height cracks in the interior walls of the MSGR. A structural evaluation report, dated, October 16, 2023, and prepared by Green Powered Technology determined that the walls affected are non-bearing unreinforced masonry affected by large steel security doors previously affixed to the walls and by live load and wind load transferred through the truss system above bearing on the interior walls as a result of an overloaded ceiling structure and deformation over time.

The cracks were determined to be non-structural in nature, so the recommended repairs have been proposed in order to maintain the interior walls’ stability, reduce the emergence of future cracks and to extend the useful life of the walls.

3. Scope of Work

Contractor awarded with this project should provide professional hand labor, materials, and tools to perform all the work required in this scope of work.

The Contractor shall provide all required personnel, equipment, materials, tools, and supervision as needed to complete the services that meet the technical requirements in this Statement of Work [SOW]. It is expected that the Contractor shall partner closely with Embassy personnel.

The work consists of removal of existing plaster and installation of ferrocement jacketing in select locations in the MSGR. The contractor is required to supply and install all resources including tools, labor, materials, and equipment necessary for the work including supervision during installation.

The intent of this project is to repair existing interior nonbearing walls exhibiting large cracks at the MSGR. The repair method is ferrocement jacketing. Seven major cracks were identified in the southwest section of the building, in the common area, bedroom 1, pantry and hallways connecting common area with kitchen and pantry. The contractor's work scope will include, but will not necessarily be limited to the following:

1. Obtain all relevant the building permit issued by the us embassy and comply with all applicable local, national, and united states codes, standards, and regulations.

2. Establish and maintain a safe construction site for workers, and for residents and guests at the property.

3. Verify all information provided in this set of drawings prior to starting work; request clarification as needed and notify the engineer of any discrepancies.

4. Install protective coverings on all furniture, windows, and interior elements as well as dust protection.

5. Install bracing and shoring adjacent to affected areas.

6. Prepare surfaces of existing masonry walls, sawcut plaster at extents of work, remove plaster to surface of masonry using hand tools.

7. Clean and prepare masonry surfaces

8. Install ferrocement jacketing comprising welded wire mesh affixed to masonry with masonry anchors and washers. Place plaster over mesh.

9. Clean and paint all new plaster to match existing.

10. Remove excess materials and restore the site to its pre-construction condition.

11. Remove existing steel security doors (3 total).

4. Specifications

4.1. General

The contractor must coordinate with the USAID Construction Team regarding the following sub-activities and deliverables:

● Project Management, Scheduling, Quality Control, and Health and Safety.

● Inspections and Tests.

● Final Acceptance and Work Closeout.

● Defects and Liability period for work as installed.

● Deliverables – (i.e., Drawings, Test Reports, Schedule, Reports, etc.).

● Coordinate work with relevant USAID offices and teams.

4.2. Ferrocement Jacketing

1. All concrete work shall comply with "ACI 301: Specifications for Structural Concrete" latest edition.

2. All concrete reinforcement shall be detailed, fabricated, labeled, supported and spaced in forms and secured in place in accordance with the procedures and requirements outlined in the latest edition of "ACI 318:

Building Code Requirements for Structural Concrete and Commentary" and 'SP-66: ACI detailing manual."

3. Unless otherwise noted, all concrete shall be ferrocement concrete without coarse aggregate having a minimum ultimate compressive strength of 2800 psi at 28 days. The contractor may base their mix design on Type M mortar.

4. Cement shall be Portland Type I or similar.

5. The maximum water cement ratio of all concrete shall be 0.4.

6. Welded wire fabric shall conform to ASTM A1064 Gauge 10 with 50mm x 50mm wire spacing. Development lengths of reinforcing (Ld, ldh, or Lda) shall be determined in accordance with the requirements of ACI 318, chapter 12.

7. All mesh supports shall be galvanized 3/8" x 3" strong-tie Titen HD screw anchor, zinc, or similar. Washers 3/8" x 1" ASTM F436.

8. Reinforcing mesh shall have a minimum clear cover of 3/8" against masonry and 3/4" outside face.

5. Planning and Work Schedules

This section describes the full range of Contractor support services, equipment, and equipment services that must be provided under this Contract.

5.1. Project Management Requirements

The Contractor must provide a Project Management Plan and submit the plan with its proposal.

The Contractor must develop milestones for mobilization, building protection and shoring, removals, installation of ferrocement jacketing, painting, cleaning, and the installation schedule for all tasks. The schedule will at a minimum identify material procurement and receipt.

The Contractor must submit weekly status progress reports to the USAID COR.

Project Management/Kick-Off Meeting: Within seven (7) business days following the Notice to proceed, the Contractor must attend a Kick-Off Meeting to review task order goals and objectives, and to discuss technical requirements, administrative matters, security requirements, Government Furnished Information (GFI)/Government Furnished Materials (GFM)/GFE, the milestone schedule, review cycles, and invoicing and on a weekly basis.

The Contractor must develop technical reports as directed by the USAID/South Sudan Contracting Office.

5.2. Site Survey

The Contractor must conduct a pre-award site survey at the RC

● The Contractor must coordinate with the Mission designated POC for the installation. The Contractor shall contact the site POC prior to the survey.

● In performing a basic or complex site survey, the Contractor must dispatch qualified technician(s) to USAID/South Sudan RC, assess the site conditions, and prepare a site survey report.

● Site survey results must be provided to USAID/South Sudan within 5 working days following the survey.

● Included in a site survey report, the Contractor must verify all dimensions of affected areas to be repaired. The Contractor is not to rely on dimensions provided in the drawings or contract documents, and must document all relevant wall and room dimensions, both horizontal and vertical in order to obtain an accurate quantity survey of the affected area.

5.3. Construction Tasks

The following subtasks must be performed by the Contractor in accordance with the general requirements described below.

This task will be started on the day of the notice to proceed and be completed in 120 calendar days from start date.

5.4. Site Preparation and Removals

1. The contractor shall be solely responsible for construction site safety, as well as the means and methods of construction, including temporary shoring (as required).

2. Attached plans and details were developed from limited project site observations. The contractor shall verify existing conditions and notify the engineer of any significant discrepancies between the construction drawings and as-built conditions.

3. Where indicated, plans and details are provided for reference only to identify locations/scopes of work.

4. Detail call-outs are typical. What is shown or referenced to at a given location shall be provided as though shown throughout unless otherwise noted.

5. Do not scale drawings. Written dimensions govern. In case of a conflict, the contractor shall notify the engineer.

6. All work shall conform to the contract documents, which include the drawings and all addendums or modifications issued by the engineer.

7. Perform all work in accordance with industry standards, manufacturer requirements, codes, laws, ordinances, rules and regulations of public authorities governing the work. In case of discrepancies, the contractor shall notify the engineer before proceeding.

9. The contractor shall visit the project site and be acquainted with all conditions relating to the construction of the project. The contractor shall obtain all field measurements required for the accurate fabrication and installation of the work.

10. The contractor shall examine, read, and be thoroughly familiar with the construction documents. Should the contractor find discrepancies or omissions in the drawings and/or notes, or should the contractor be in doubt as to the intent or meaning of any parts of the construction documents, the contractor shall request clarification from the engineer prior to performing the work in question.

11. The contractor shall submit requests for substitutions, revisions, or changes to the engineer for review and acceptance prior to purchase, fabrication or installation.

12. The contractor shall obtain all permits and inspections required by public authorities governing the work.

13. All work shall be performed in a safe and orderly manner without damage to other parts of the premises and/or adjacent properties. Damage or loss shall be corrected and/or replaced by the contractor at no cost to the owner.

14. The contractor shall provide traffic control and temporary barricades as required during construction when roadways and/or right-of-ways are blocked due to the work. The contractor shall minimize disruption to traffic flow for vehicles and maintain safety for pedestrians at the project site.

15. The contractor shall coordinate work with the owner and property manager, including scheduling times and locations for deliveries, building access, use of electricity, and use of water. Minimize disturbance of building functions and occupants.

16. Work areas shall remain secure throughout construction. The contractor shall coordinate with the owner to ensure security.

17. Maintain egress and access to the property in accordance with codes and ordinances.

18. The scope of work of these repair drawings are limited to the areas and conditions shown, and shall not be used beyond its specified purpose.

19. Instructions for access to site can be found in the contractor's statement of work.

20. Contractor to provide protection of existing furniture and surfaces.

21. Contractor to limit dust and debris from all plaster removal operations by use of barriers and other means.

22. All materials stored on site are the responsibility of the contractor. The owner will identify laydown areas for the contractors use, however, protection and security of the stored material is the responsibility of the contractor.

5.5. Installation of Ferrocement Jacketing

1. Upon completion of plaster removals, masonry walls shall be cleaned of all loose material.

2. Gaps in the masonry wall shall be filled with new masonry and non-shrink grout.

3. Areas of excessive mortar loss shall be repointed.

4. Contractor to install welded wire mesh (50x50 x Gauge 10)

5. Wire mesh shall be affixed with 10 ∅ x 75 strong tie titen hd screw anchor, zinc, or similar (e.g. Gr 55 anchor bolt) with 10 x 25 hardened galvanized washer. Wire mesh shall be installed 10 away from face of masonry wall.

6. Ferrocement grout shall be placed over mesh, 20 cover minimum. Maximum total thickness shall be no greater than 40.

6. Material and Equipment

6.1. Government Furnished Information (GFI)

USAID/South Sudan will provide technical data, applicable documents, plans, regulations, specifications, Site floor plans, specifications, and references that will be needed for the work.

6.2. Contractor Furnished Equipment (CFE)

The Contractor is required to furnish all necessary tools, equipment and materials required for performing all work associated with the completion of this requirement, which also includes testing and installation.

The Contractor is required to purchase, transport store, inventory, and handle installation material that is identified as CFE. Excess materials and prescribed spares must be turned over to USAID/South Sudan at the completion of the project. Material turned over at the completion of the project must be thoroughly documented including description, part numbers, and quantities.

6.3. Contractor Furnished Items (CFI)

Prior to the start of the work (minimum of 5 working days) the contractor must provide the list of all employees, vehicles, and tools scheduled to enter the RC premises. These need to be cleared with the Embassy security office.

7. Restoring the area in its original conditions.

The contractor must restore all the affected areas by the work in its original site conditions this includes cleaning and painting. The contractor must remove and dispose off-site all inert debris, which will remain after the removals process.

Contractor will clean and clear all work areas at the end of each day and on completion of the project.

8. Project Monitoring

Point of Contact: The COR will be the main point of contact for this Project. The Contractor must report to the COR on (a) status of the Project, (b) changes in Schedule, (c) accidents and safety issues, (d) disruptions to utility services, and any information necessary for Project.

Key Personnel: The Contractor will staff the site, full-time, with a competent senior manager who must perform project management. Remote project management is not an option. This individual must keep a detailed written history of the project and is required to update the COR weekly.

Site Security: The site security is provided by the RSO, but the Contractor is responsible for giving access to its site within the compound to ensure no unauthorized access to their work. sites. The Contractor is 100% responsible for securing their working materials and equipment. Any damage to facilities or infrastructure, which happens due to a lack of security, will be the responsibility of the Contractor to correct.

Contractor Staff Entrance: The Contractor must abide by US Embassy security regulations related to the work including providing names of staff and vehicles one week prior to when work is to be performed.

Due to the nature of this project, the contractor may be asked to work in the following hours:

Monday – Thursday: 8:00 am – 5:00 pm

Fridays: 8:00 am – 2:00 pm

Saturday; Sunday: 8:00 am – 5:00 pm (Prior arrangements and approval required)

9. As-built construction documents

As-built drawings and documentation must be delivered to the USG as part of the permanent project record. USG shall be the exclusive owner of this documentation.

10. Defects and Liability Period

All workmanship and installations must be covered by a one-year defects and liability period from the date the Contractor handed over the works to USAID whereby when required by USAID, the Contractor shall return to the site to affect repairs to the area of work.

11. INSTRUCTION TO OFFERORS AND EVALUATION CRITERIA

11.1 Instruction to Offerors

Offerors must submit quotes via email (see cover page). The offer must be separated into 2 parts: Technical and Price. The Technical part must not reference any pricing. The Offeror must submit the following documentation as part of the quote:

11.2 Evaluation Criteria

This RFQ will utilize a Lowest Price Technically Acceptable (LPTA) process. Lowest Price Technically Acceptable (LPTA) source selection process (FAR 15.101-2) is where the government determines that the lowest price is awardable over the compliant technical offering of all proposals. LPTA is appropriate only when the government “expects” it can achieve the best value from selecting the proposal that is technically acceptable and offers the lowest evaluated price.

The Government may award a contract without discussions with Offeror.

a) Technical Part: The Technical part must include the following:

1. Technical Understanding and Approach: The extent to which the Technical Understanding and Approach articulates a logical strategy for meeting all the requirements set forth in SOW, is technically sound, and demonstrates a clear understanding of the Project goals and objectives. This includes consideration of the Offeror’s approach to successfully complete all the work specified in the SOW.

2. Staffing Plan and Organizational Structure, Management Approach, and Mobilization Plan: The extent to which the proposal convincingly demonstrates a logical and well-thought-out staffing plan, organizational structure, and management approach. A convincing proposal will demonstrate how the Offeror will effectively and efficiently mobilize, manage the necessary resources to implement the proposed construction activities, and coordinate with relevant stakeholders to complete the requirements of the Project.

3. Organizational Capacity and Experience: The extent to which the Offeror convincingly demonstrates the capability and experience to successfully implement activities of a similar magnitude, scope, and complexity in similar country contexts. Offerors are required to identify the time required to readily mobilize to Juba, South Sudan and identify projects of the same type and value undertaken and successfully completed in South Sudan or similar conditions.

4. A draft schedule: In compliance with FAR 52.236-15 identifying the main elements of work and time for completion.

5. Construction and Safety Plan: The Offeror must provide a list of the equipment proposed for the construction. The Offeror must provide a safety plan with control measures for ensuring abounding properties are not subject to building/grounds damage; persons are not subject to harm and/or bodily damage, where applicable.

b) Price Part:

The Offeror must submit the cover page of this solicitation Standard Form (SF) 1449, with blocks 14 through 20 completed as well as provide the price for each CLIN as described in this solicitation. The Offeror must also submit the completed representations and certifications (see below) as applicable.

Mandatory Site Visit: Due to the nature of the work, there is a mandatory site visit that will be conducted on April 16th, 2024, at 10a.m. (CAT) at the proposed site (US Embassy RC). Please contact Nelson Poggo at npoggo@usaid.gov for further specifics. Offeror must attend the site visit to be eligible to submit a proposal.

mailto:npoggo@usaid.gov

12. Marine Security Guard Residence (MSGR) Repair - Bill of Quantity (BoQ).

USAID South Sudan MSGR Repair - BoQ Item # Description Name of Item Qty Unit U/Cost T/Cost Mobilization

Site Office

Site office and related items (including mobilization, equipment and personnel to site, demobilization, cleaning of site and disposal of construction debris)

1.0

LS

$0.00

$0.00

2 Insurance Insurance for liability and professional services indemnity 1.0 LS $0.00 $0.00

3 PPE Safety gear and equipment 3.0 LS $0.00 $0.00 4 Protection Installation of furniture and room protection including coverings and dust protection

1.0 LS $0.00 $0.00

5 Plaster Removals

Removal of existing plaster from affected areas 80.0 SM $0.00 $0.00

6 Steel Door Removal

Disassemble and remove steel security doors. 3.0 QTY $0.00 $0.00

Subtotal $0.00 Shoring 6 Planks Timber, 1" x 12" x 12' (3.5m) 15 number $0.00 $0.00

7 Bracing and Props Timber, 2" x 4" x 12' (3.5m) 30 number $0.00 $0.00

8 Assorted nails Wire nails 1 LS $0.00 $0.00 Subtotal $0.00

Ferrocement Jacketing

9 Welded Wire Mesh

50 x 50 welded wire mesh (gauge 10) 80.0 SM $0.00 $0.00

10 Plaster 1.5" wall plastering (1:3 cement: sand) 7.2 CM $0.00 $0.00

11 Fasteners and washers

3/8" grade 55 anchor bolts and 1" washers 1.0 LS $0.00 $0.00

12 Balance of Materials

1.0 LS $0.00 $0.00

Subtotal $0.00 Painting

13 Interior walls Emulsion, double coat 140.0 SM $0.00 $0.00

14 Painting accessories

Miscellaneous painting accessories 1.0 LS $0.00 $0.00

Subtotal $0.00 Grand Total

Submission of Quotes:

Proposals are due no later than 2300 (CAT) South Sudan time on April 24, 2024.

a. This RFQ will utilize a Lowest Price Technically Acceptable (LPTA) process.

Lowest Price Technically Acceptable (LPTA) source selection process (FAR 15.101-2) is where the government determines that the lowest price is awardable over the compliant technical offering of all proposals. LPTA is appropriate only when the government

“expects” it can achieve the best value from selecting the proposal that is technically acceptable and offers the lowest evaluated price.

b. The Government may award a contract without discussions with Offeror.

Provisions:

52.233-2 Service of Protest. (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the

Government Accountability Office (GAO), shall be served on the Contracting Officer

(Addressed as follows) by obtaining written and dated acknowledgment of receipt from

[Contracting Officer designate the official or location where a protest may be served on the Contracting Officer].

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

52.236-27 Site Visit (Construction) (Feb 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and

Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for April 16th, 2024, starting at 10a.m. (CAT) South Sudan time.

(c) Participants must email Nelson Poggo at npoggo@usaid.gov to get location and meeting specifics.

13. INSTRUCTIONS TO THE SUCCESSFUL BIDDER/CONTRACTOR

1. The contractor must familiarize himself with the Project sites, the work of other contractors, and work under the direction of the COR to ensure a smooth coordination of all activities without disrupting work being performed by other contractor(s), traffic, and daily use of any of the facilities.

2. Specifications for all contractor procured items, as well as construction procedures must be submitted to, and be approved by the COR prior to their implementation.

3. Construction/Renovation Schedule: All works must be completed within 365 days from the issuance of the signing of the Purchase Order. Contractor must submit a detailed schedule for all activities within 7 days upon signing the PO for review and approval by the COR.

4. The contractor shall ensure that crew members carry valid government issued photo identification cards with them, as well as observe U.S. Embassy safety and security regulations, policies, and procedures. All contractor staff and vehicles are subject to inspection upon entering/exiting all U.S. Government compounds.

5. The contractor is responsible for the health and safety of his personnel while on US Government property. USG shall carry no liability for any accidents and/or other unforeseeable events that might adversely impact the contractor and/or his staff. The contractor shall ensure all crew members are thoroughly instructed in safety procedures and that they wear appropriate head, and foot gears, and any other necessary PPE as may be required at the work site.

6. Equipment, tools, and supplies including drinking water and feeding are to be furnished by the contractor. The contractor shall always ensure the direct supervision of all crew members. Contractor’s staff must remain at the worksite. Escorts shall accompany the contractor’s staff during Compound entry (phones, computer, etc., shall not be permitted in the Compound unless COR permits, and obtains Security approval) and whenever anyone planned to, and/or is required to leave the site for any reason.

7. All contractors must be registered in the SAM (System for Award Management) Database https://www.sam.gov prior to contract award pursuant to FAR provision 52.204-7. Therefore, prospective offerors are encouraged to register prior to the submission of quotations/proposals. Only vendors who have fully complied with this requirement are eligible for award.

mailto:npoggo@usaid.gov http://www.sam.gov/

14. ATTACHMENTS

14.1 MSGR DRAWINGS.

CONTRACT CLAUSES:

52.202-1 Definitions 52.203-3 Gratuities 52.203-5 Covenant Against Contingent Fees 52.203-6 Restrictions on Subcontractor Sales to the Government 52.203-6 Alternate I 52.203-7 Anti-Kickback Procedures 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity 52.203-12 Limitation on Payments to Influence Certain Federal Transactions 52.203-13 Contractor Code of Business Ethics and Conduct 52.203-14 Display of Hotline Poster(s) 52.203-15 Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009 52.203-16 Preventing Personal Conflicts of Interest 52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of

52.203-19 Whistleblower Rights Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

52.204-1 Approval of Contract 52.204-2 Security Requirements 52.204-2 Alternate I 52.204-2 Alternate II

52.204-9 Personal Identity Verification of Contractor Personnel 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards 52.204-12 Unique Entity Identifier Maintenance 52.204-13 System for Award Management Maintenance 52.204-14 Service Contract Reporting Requirements 52.204-18 Commercial and Government Entity Code Maintenance 52.204-19 Incorporation by Reference of Representations and Certifications 52.204-21 Basic Safeguarding of Covered Contractor Information Systems 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided

52.204-25 by Kaspersky Lab and Other Covered Entities Prohibition on Contracting for Certain Telecommunications and Video Surveillance

52.204-26 Services or Equipment Covered Telecommunications Equipment or Services-Representation

52.207-3 Right of First Refusal of Employment 52.207-5 Option to Purchase Equipment 52.208-4 Vehicle Lease Payments 52.208-5 Condition of Leased Vehicles 52.208-6 Marking of Leased Vehicles 52.208-7 Tagging of Leased Vehicles 52.208-8 Required Sources for Helium and Helium Usage Data 52.208-9 Contractor Use of Mandatory Sources of Supply or Services 52.209-1 Qualification Requirements 52.209-3 First Article Approval-Contractor Testing

52.209-3 Alternate I 52.209-3 Alternate II 52.209-4 First Article Approval-Government Testing 52.209-4 Alternate I 52.209-4 Alternate II 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, 52.209-9 Suspended, or Proposed for Debarment Updates of Publicly Available Information Regarding Responsibility Matters

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations 52.210-1 Market Research 52.211-5 Material Requirements 52.211-8 Time of Delivery 52.211-8 Alternate I 52.211-8 Alternate II 52.211-8 Alternate III 52.211-9 Desired and Required Time of Delivery.

52.211-9 Alternate I 52.211-9 Alternate II 52.211-9 Alternate III 52.211-10 Commencement, Prosecution, and Completion of Work 52.211-10 Alternate I 52.211-11 Liquidated Damages-Supplies, Services, or Research and Development 52.211-12 Liquidated Damages-Construction 52.211-13 Time Extensions 52.211-15 Defense Priority and Allocation Requirements 52.211-16 Variation in Quantity 52.211-17 Delivery of Excess Quantities 52.211-18 Variation in Estimated Quantity 52.212-4 Contract Terms and Conditions-Commercial Items 52.212-4 Alternate I 52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders-

52.212-5 Commercial Items Alternate I

52.212-5 Alternate II 52.213-1 Fast Payment Procedure 52.213-2 Invoices 52.213-3 Notice to Supplier 52.213-4 Terms and Conditions-Simplified Acquisitions (Other Than Commercial Items) 2.214-26

52.214-26 Audit and Records-Sealed Bidding Alternate I

52.214-27 Price Reduction for Defective Certified Cost or Pricing Data-Modifications-Sealed Bidding 52.214-28 Subcontractor Certified Cost or Pricing Data-Modifications-Sealed Bidding 52.214-29 Order of Precedence-Sealed Bidding 52.214-31 Facsimile Bids 52.215-2 Audit and Records-Negotiation 52.215-2 Alternate I

52.215-2 Alternate II 52.215-2 Alternate III 52.215-8 Order of Precedence-Uniform Contract Format 52.215-9 Changes or Additions to Make-or-Buy Program 52.215-9 Alternate I 52.215-9 Alternate II 52.215-10 Price Reduction for Defective Certified Cost or Pricing Data 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data-Modifications 52.215-12 Subcontractor Certified Cost or Pricing Data 52.215-13 Subcontractor Certified Cost or Pricing Data-Modifications 52.215-14 Integrity of Unit Prices 52.215-14 Alternate I 52.215-15 Pension Adjustments and Asset Reversions 52.215-17 Waiver of Facilities Capital Cost of Money 52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions 52.215-19 Notification of Ownership Changes 52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or

52.215-21 Pricing Data-Modifications Alternate I

52.215-21 Alternate II 52.215-21 Alternate III 52.215-21 Alternate IV 52.215-23 Limitations on Pass-Through Charges 52.215-23 Alternate I 52.216-2 Economic Price Adjustment-Standard Supplies 52.216-3 Economic Price Adjustment-Semistandard Supplies 52.216-4 Economic Price Adjustment-Labor and Material 52.216-5 Price Redetermination-Prospective 52.216-6 Price Redetermination-Retroactive 52.216-7 Allowable Cost and Payment 52.216-7 Alternate I 52.216-7 Alternate II 52.216-7 Alternate III 52.216-7 Alternate IV 52.216-8 Fixed Fee 52.216-9 Fixed Fee-Construction 52.216-10 Incentive Fee 52.216-11 Cost Contract-No Fee 52.216-11 Alternate I 52.216-12 Cost-Sharing Contract-No Fee 52.216-12 Alternate I 52.216-15 Predetermined Indirect Cost Rates 52.216-16 Incentive Price Revision-Firm Target 52.216-16 Alternate I 52.216-17 Incentive Price Revision-Successive Targets 52.216-17 Alternate I

52.216-18 Ordering 52.216-19 Order Limitations 52.216-20 Definite Quantity 52.216-26 Payments of Allowable Costs Before Definitization 52.216-27 Single or Multiple Awards 52.216-28 Multiple Awards for Advisory and Assistance Services 52.216-29 Time-and-Materials/Labor-Hour Proposal Requirements-Non-Commercial Item

52.216-30 Acquisition with Adequate Price Competition Time-and-Materials/Labor-Hour Proposal Requirements-Non-Commercial Item

52.216-31 Acquisition Without Adequate Price Competition Time-and-Materials/Labor-Hour Proposal Requirements-Commercial Item Acquisition

52.216-32 Task-Order and Delivery-Order Ombudsman 52.216-32 Alternate I 52.217-2 Cancellation Under Multi-Year Contracts 52.217-3 Evaluation Exclusive of Options 52.217-4 Evaluation of Options Exercised at Time of Contract Award 52.217-5 Evaluation of Options 52.217-6 Option for Increased Quantity 52.217-7 Option for Increased Quantity-Separately Priced Line Item 52.217-8 Option to Extend Services 52.219-3 Notice of HUBZone Set-Aside or Sole Source Award 52.219-3 Alternate I 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns 52.219-4 Alternate I 52.219-6 Notice of Total Small Business Set-Aside 52.219-6 Alternate I 52.219-6 Alternate II 52.219-7 Notice of Partial Small Business Set-Aside 52.219-7 Alternate I 52.219-7 Alternate II 52.219-8 Utilization of Small Business Concerns 52.219-9 Small Business Subcontracting Plan 52.219-9 Alternate I 52.219-9 Alternate II 52.219-9 Alternate III 52.219-9 Alternate IV 52.219-10 Incentive Subcontracting Program 52.219-11 Special 8(a) Contract Conditions 52.219-14 Limitations on Subcontracting 52.219-16 Liquidated Damages-Subcontracting Plan 52.219-27 Notice of Service-Disabled Veteran-Owned Small Business Set-Aside 52.219-28 Post-Award Small Business Program Representation 52.219-28 Alternate I 52.219-29 Notice of Set-Aside for, or Sole Source Award to, Economically Disadvantaged Women-

Owned Small Business Concerns

52.219-30 Notice of Set-Aside for, or Sole Source Award to, Women-Owned Small Business Concerns

52.219-32 Eligible Under the Women-Owned Small Business Program Orders Issued Directly Under Small Business Reserves

52.219-33 Nonmanufacturer Rule 52.222-1 Notice to the Government of Labor Disputes 52.222-2 Payment for Overtime Premiums 52.222-3 Convict Labor 52.222-4 Contract Work Hours and Safety Standards -Overtime Compensation 52.222-7 Withholding of Funds 52.222-8 Payrolls and Basic Records 52.222-9 Apprentices and Trainees 52.222-10 Compliance with Copeland Act Requirements 52.222-11 Subcontracts (Labor Standards) 52.222-12 Contract Termination-Debarment 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations 52.222-14 Disputes Concerning Labor Standards 52.222-15 Certification of Eligibility 52.222-16 Approval of Wage Rates 52.222-17 [Reserved] 52.222-19 Child Labor-Cooperation with Authorities and Remedies 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment 52.222-21 Prohibition of Segregated Facilities 52.222-26 Equal Opportunity 52.222-26 Alternate I 52.222-27 Affirmative Action Compliance Requirements for Construction 52.222-29 Notification of Visa Denial 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified

52.222-31 Method) Construction Wage Rate Requirements-Price Adjustment (Percentage Method)

52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method) 52.222-34 Project Labor Agreement 52.222-34 Alternate I 52.222-37 Employment Reports on Veterans 52.222-40 Notification of Employee Rights Under the National Labor Relations Act 52.222-41 Service Contract Labor Standards 52.222-43 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment

52.222-44 (Multiple Year and Option Contracts) Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment

52.222-46 Evaluation of Compensation for Professional Employees 52.222-49 Service Contract Labor Standards-Place of Performance Unknown 52.222-50 Combating Trafficking in Persons 52.222-51 Exemption from Application of the Service Contract Labor Standards to Contracts for

52.222-53 Maintenance, Calibration, or Repair of Certain Equipment Requirements Exemption from Application of the Service Contract Labor Standards to Contracts for

52.222-54 Certain Services-Requirements Employment Eligibility Verification

52.222-55 Minimum Wages Under Executive Order 13658 52.222-62 Paid Sick Leave Under Executive Order 13706 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts 52.223-3 Hazardous Material Identification and Material Safety Data 52.223-3 Alternate I 52.223-5 Pollution Prevention and Right-to-Know Information 52.223-5 Alternate I 52.223-5 Alternate II 52.223-6 Drug-Free Workplace 52.223-7 Notice of Radioactive Materials 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items 52.223-9 Alternate I 52.223-10 Waste Reduction Program 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioner 52.223-13 Acquisition of EPEAT®–Registered Imaging Equipment 52.223-13 Alternate I 52.223-14 Acquisition of EPEAT®-Registered Televisions 52.223-14 Alternate I 52.223-15 Energy Efficiency in Energy-Consuming Products 52.223-16 Acquisition of EPEAT®-Registered Personal Computer Products 52.223-16 Alternate I 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving 52.223-19 Compliance with Environmental Management Systems 52.223-20 Aerosols 52.223-21 Foams 52.224-1 Privacy Act Notification 52.224-2 Privacy Act 52.224-3 Privacy Training 52.224-3 Alternate I 52.225-1 Buy American-Supplies 52.225-2 Buy American Certificate 52.225-3 Buy American-Free Trade Agreements-Israeli Trade Act 52.225-3 Alternate I 52.225-3 Alternate II 52.225-3 Alternate III 52.225-4 Buy American-Free Trade Agreements-Israeli Trade Act Certificate 52.225-5 Trade Agreements 52.225-13 Restrictions on Certain Foreign Purchases 52.225-14 Inconsistency between English Version and Translation of Contract 52.225-19 Contractor Personnel in a Designated Operational Area or Supporting a Diplomatic or

52.225-26 Consular Mission Outside the United States Contractors Performing Private Security Functions Outside the United States

52.222-35 Equal Opportunity for Veterans 52.222-36 Equal Opportunity for Workers with Disabilities

52.226-1 Utilization of Indian Organizations and Indian-Owned Economic Enterprises 52.227-1 Authorization and Consent 52.227-1 Alternate I 52.227-1 Alternate II 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement 52.227-3 Patent Indemnity 52.227-3 Alternate I 52.227-3 Alternate II 52.227-3 Alternate III 52.227-4 Patent Indemnity-Construction Contracts 52.227-4 Alternate I 52.227-5 Waiver of Indemnity 52.227-6 Royalty Information 52.227-9 Refund of Royalties 52.227-10 Filing of Patent Applications-Classified Subject Matter 52.227-11 Patent Rights-Ownership by the Contractor 52.227-11 Alternate I 52.227-11 Alternate II 52.227-11 Alternate III 52.227-11 Alternate IV 52.227-11 Alternate 52.227-13 Patent Rights-Ownership by the Government 52.227-13 Alternate I 52.227-13 Alternate II 52.227-14 Rights in Data-General 52.227-14 Alternate I 52.227-14 Alternate II 52.227-14 Alternate III 52.227-14 Alternate IV 52.227-14 Alternate 52.227-16 Additional Data Requirements 52.227-17 Rights in Data-Special Works 52.227-18 Rights in Data-Existing Works 52.227-19 Commercial Computer Software License 52.227-20 Rights in Data-SBIR Program 52.227-21 Technical Data Declaration, Revision, and Withholding of Payment-Major Systems 52.227-22 Major System-Minimum Rights 52.227-23 Rights to Proposal Data (Technical) 52.228-2 Additional Bond Security 52.228-3 Workers’ Compensation Insurance (Defense Base Act) 52.228-4 Workers’ Compensation and War-Hazard Insurance Overseas 52.228-5 Insurance-Work on a Government Installation 52.228-7 Insurance-Liability to Third Persons 52.228-8 Liability and Insurance-Leased Motor Vehicles 52.228-9 Cargo Insurance 52.228-10 Vehicular and General Public Liability Insurance

52.228-11 Pledges of Assets 52.228-12 Prospective Subcontractor Requests for Bonds 52.228-13 Alternative Payment Protections 52.228-14 Irrevocable Letter of Credit 52.228-15 Performance and Payment Bonds-Construction 52.229-1 State and Local Taxes 52.229-2 North Carolina State and Local Sales and Use Tax 52.229-2_ Alternate I 52.229-3 Federal, State, and Local Taxes 52.229-4 Federal, State, and Local Taxes (State and Local Adjustments) 52.229-6 Taxes-Foreign Fixed-Price Contracts 52.229-7 Taxes-Fixed-Price Contracts with Foreign Governments 52.229-8 Taxes-Foreign Cost-Reimbursement Contracts 52.229-9 Taxes-Cost-Reimbursement Contracts with Foreign Governments 52.229-11 Tax on Certain Foreign Procurements 52.229-12 Tax on Certain Foreign Procurements 52.230-2 Cost Accounting Standards 52.230-3 Disclosure and Consistency of Cost Accounting Practices 52.230-4 Disclosure and Consistency of Cost Accounting Practices-Foreign Concerns 52.230-5 Cost Accounting Standards-Educational Institution 52.230-6 Administration of Cost Accounting Standards 52.232-1 Payments 52.232-2 Payments under Fixed-Price Research and Development Contracts 52.232-3 Payments under Personal Services Contracts 52.232-4 Payments under Transportation Contracts and Transportation-Related Services Contracts 52.232-5 Payments under Fixed-Price Construction Contracts 52.232-6 Payment under Communication Service Contracts with Common Carriers 52.232-7 Payments under Time-and-Materials and Labor-Hour Contracts 52.232-8 Discounts for Prompt Payment 52.232-9 Limitation on Withholding of Payments 52.232-10 Payments under Fixed-Price Architect-Engineer Contracts 52.232-11 Extras 52.232-16 Progress Payments 52.232-16 Alternate I 52.232-16 Alternate II 52.232-16 Alternate III 52.232-17 Interest 52.232-18 Availability of Funds 52.232-20 Limitation of Cost 52.232-22 Limitation of Funds 52.232-23 Assignment of Claims 52.232-23 Alternate I 52.232-24 Prohibition of Assignment of Claims 52.232-25 Prompt Payment 52.232-25 Alternate I 52.232-26 Prompt Payment for Fixed-Price Architect-Engineer Contracts

52.232-27 Prompt Payment for Construction Contracts 52.232-30 Installment Payments for Commercial Items 52.232-33 Payment by Electronic Funds Transfer-System for Award Management 52.232-34 Payment by Electronic Funds Transfer-Other than System for Award Management 52.232-35 Designation of Office for Government Receipt of Electronic Funds Transfer Information 52.232-36 Payment by Third Party 52.232-37 Multiple Payment Arrangements 52.232-39 Unenforceability of Unauthorized Obligations 52.232-40 Providing Accelerated Payments to Small Business Subcontractors 52.233-1 Disputes 52.233-1 Alternate I 52.233-3 Protest after Award 52.233-3 Alternate I 52.233-4 Applicable Law for Breach of Contract Claim 52.234-4 Earned Value Management System 52.236-1 Performance of Work by the Contractor 52.236-2 Differing Site Conditions 52.236-3 Site Investigation and Conditions Affecting the Work 52.236-5 Material and Workmanship 52.236-6 Superintendence by the Contractor 52.236-7 Permits and Responsibilities 52.236-8 Other Contracts 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements 52.236-10 Operations and Storage Areas 52.236-11 Use and Possession Prior to Completion 52.236-12 Cleaning Up 52.236-13 Accident Prevention 52.236-13 Alternate I 52.236-14 Availability and Use of Utility Services 52.236-15 Schedules for Construction Contracts 52.236-16 Quantity Surveys 52.236-16_ Alternate I 52.236-17 Layout of Work 52.236-18 Work Oversight in Cost-Reimbursement Construction Contracts 52.236-19 Organization and Direction of the Work 52.236-21 Specifications and Drawings for Construction 52.236-21 Alternate I 52.236-21 Alternate II 52.236-22 Design Within Funding Limitations 52.236-23 Responsibility of the Architect-Engineer Contractor 52.236-24 Work Oversight in Architect-Engineer Contracts 52.236-25 Requirements for Registration of Designers 52.236-26 Preconstruction Conference 52.237-2 Protection of Government Buildings, Equipment, and Vegetation 52.237-3 Continuity of Services 52.237-4 Payment by Government to Contractor

52.237-4 Alternate…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .